Cement grinding capacity expansion
Cement

Cement grinding capacity expansion

Split location of a plant is an accepted concept. It is an easy route to add capacities where market exists. Shreekant Datar, who has wide experience of handling projects in multinational companies, shares deta...

Split location of a plant is an accepted concept. It is an easy route to add capacities where market exists. Shreekant Datar, who has wide experience of handling projects in multinational companies, shares details of one such case. ABC Cement is a 10-year old cement manufacturing company. The plant started with a clinkering capacity of 1 MTPA, i.e., around 3,000 MT per day. Over the years, as the demand for cement grew, the plant has undertaken upgradation work in phases every year, and after all debottlenecking, the plant has stabilised with a clinker production capacity of 4,000 MT per day. This amounts to an excess clinker availability of 1,000 MT per day. All other plant capacities have reached their peak levels and finding a proper time for maintenance of equipment to ensure availability, has become a problem for the management. The management is forced to curtail the production to avoid overproduction of clinker as storage is a big limitation. The top management team has been mulling over an idea of investing some capital to enhance the capacities as market is growing at 8 to 10 per cent per annum. The management also thinks that this expansion will help in: retaining their market share as other players in the region are trying to take a slice of market, and maintaining cost effectiveness and competitiveness. The existing cement plant has no space for expansion and management has thought to put up a plant away from clinkering unit. Questions that arose was, “Where do we put up this unit”? Since it required a thorough study before taking any further decision and a project team was made and they were given the task of formulating this plant project. The team consisted of personnel from technical, financial, legal and marketing department. The technical person heading it was the most senior and had back up experience of installing a project. How did the project team work? They prepared a project charter which was somewhat like this: Objective: To enhance cement grinding capacity and liquidate 1000 MT of excess clinker Project steps Find a suitable location List down all the necessary statutory requirements of government to be filled in. Hire a consultant to understand and arrive at the overall requirements of project like technology selection, working out area requirements, capital cost involved, operating costs, logistics cost and finally the financial feasibility Two teams were formed in which one worked on technical proposal and second on the location and market perspective. Technical concept The proposed plant should be a grinding unit with packing facility. It should be for making blended cement like fly ash based PPC or slag-based cement. Clinker to be handled by road by trucks. The cement despatch to be handled by road. The control systems shall be PLC/DCS based and remote control, with lowest manpower is possible. The technology available for grinding is: Closed circuit ball mill system A vertical roller mill system A combined roller press and ball mill system Required capacity is 1,550 TPD or 5.11 LTPA. (0.5 million TPA). After a lot of deliberation with consultant and internal team, it was decided to adopt a 75 TPH roll press + ball mill system technology. The advantages seen with this were a good and consistent surface (Blaine) generation, which the market valued and flexibility to use either fly ash or other additives in future.Main equipment: Sl. No. Particulars Capacity 1 Hydraulic roll press with a static separator 60 TPH output/360 TPH throughput 2 Ball mill 75 TPH output 3 High efficiency separator 200 TPH 4 Auto Rotary packer 6 spout X 2 numbers 180 TPH – to be used in two shifts operation 5 Truck loaders – X 3 numbers One additional loader to ensure availability and minimise truck waiting time. 6 Other material handling equipment for clinker unloading, belt conveyors, elevators etc. Suitably sized to match the system outputs 7 Electrical power receiving, distribution and PLC based process control systems Suitably sized for the proposed capacity  Main storage: Sl. No. Particulars Capacity 1 Clinker storage – 15 days, closed type with bottom extraction 25000 MT 2 Gypsum storage – 30 days stock – closed type 2000 MT 3 Fly ash storage – 15 days stock 7000 MT 4 Cement storage – 2 silos 5000 X 2 numbers Plant layout: In line process equipment and storage with provision for similar second line Total plant area required: About 20 acres Overall timeframe for project 1. Land procurement – six months 2. Statutory approvals – 10 months after land procurement 3. Engineering – three months after statutory approval 4. Procurement and delivery – eight months after first critical order 5. Detailed engineering and construction – eight months after two months of critical equipment ordering 6. Commissioning – one month Total – 30 months from start of land procurement. It was noted that this can be shortened by about six months if land procurement is expedited and some engineering work is done before necessary statutory clearances are obtained. Location finalisation To begin with, a brainstorming was carried out and it was zeroed on following characteristics: 1) The location should be close to our market place 2) The location should be within 500 km distance from main plant 3) Should have land availability at a reasonable price 4) Should have infrastructure like roads, railway, electricity source, water source, a reasonably big town for housing the operating personnel 5) Availability of trucks for final product transfer 6) The location should be close to an additives source Considering the above factors, a land parcel of 22 acres was available close to a power plant and clinkering unit. This was a private agricultural land. Land procurement The land team verified following land characteristics 1. There are no man settlements or natural waterbodies with in arial radius of 2.0 km 2. The nearest highway is within 5 km of location 3. The railway station is with in 10 km 4. Airport is within 100 km 5. Electrical substation for power sourcing is within 5 km range 6. Water source(borewell) is available in the finalised land 7. An inhabitable township is within 30 to 50 km radius. This would help in housing the families of staff working in the area. 8. The political situation and people’s attitude towards Industry was assessed 9. The land parcels have no encumbrances and are free of any litigation. All the documents of the land lineage for 20 years were checked. Wherever mutations were pending they were done quickly with the help of Gram Panchayat and Tehsil office. The team did a wonderful job of developing good relationship with influential and in power people and manged to procure land with reasonable price and applied for conversion of agricultural land to non-agricultural category with local district authorities. After winning confidence of local Gram Panchayat officials and the influential persons in the area, NA was obtained with in six months, i.e. a saving of four months in execution time. Statutory clearances The following were essential ones for starting the project 1. Register project with the district Industrial Development Corporation 2. Apply for environmental clearance from MOEF (essential for clinker grinding) 3. Engage environmental consultants to establish the TOR and furnish for EC 4. Meetings were held with the concerned officials and EC was obtained six months period 5. Application was made to State pollution control board and consent to establish a plant was obtained in three months. Hence a saving of one more month in execution. 6. Application was made to Electricity Board for getting power connection. All clearances were available and the liaison team developed good relationships. The board agreed to provide connection with in six months. They also agreed to provide construction power from a nearby agricultural line. 7. Other local clearances like those from Gram Panchayat were obtained along with above activities. 8. Further clearances necessary like factories inspectorate, electrical inspectorate, town planning, etc. were listed, scheduled and completed very religiously Procurement and EngineeringTenders were prepared with the help of engineering consultants and floated to prospective vendors in a month after obtaining the consent to establish with efforts by engineering team. Important conditions in the tender were: The battery limits for supply, engineering deliverable were very critically set to ensure that there are no grey areas and miss outs The core equipment load data and GA drawings will be furnished within two months Complete system engineering and layout with in battery limit to be done by suppliers The engineering data furnishing and deliveries were fully aligned with project execution requirements and payment terms were purely based on these outputs. Separate tender committee was formed under existing purchase department and equipment ordering was done quickly in three months’ time from getting the Consent to Establish from pollution control board. In due course, contracts were made and agencies for execution of civil, mechanical and E&I work were released after some engineering outputs were received. Project management A core team of six persons (project manager, planner, process engineering, mechanical engineering, drawing and design and E&I engineering) Review of drawings was made by sitting together by above team as a conference and a quick review and progress of drawings was made possible. Whole project execution plan was made using project planning software like MS project and monitored closely by above team. Alarms were incorporated in way of Flags and milestones. This would act as an early warning system for both time and cost matters. Regular visits were undertaken to debottleneck and expedite consultant’s drawing output. The floor areas of multi-storeyed building were critically examined and areas were optimised, which lead to a saving 5 per cent cost of such buildings in normal course All statutory requirements of factories Inspectorate with respect to safety, Site management A team of dedicated engineers with experience in construction work as well as operation was made and placed at site under an able project leader who had a record of executing five such projects The team made following arrangements before moving to site: 1. Locate a good hotel and make arrangements for stay 2. A local conveyance agency engaged for necessary vehicles 3. Doctors were identified 4. Good houses were identified for staff to stay 5. A bachelor’s accommodation with mess was tied up to begin with 6. Container offices were arranged for site work 7. Genset agency was hired for site power 8. Internet facility was tied up with a service providerStrict discipline to be followed to ensure only latest drawing is issued and used at site by exercising control to withdraw old drawings and stamp them as superseded. Give a regular communication to contractors and engineers as soon as a new version has been received. In some projects new drawings have been issued after construction was done which lead to serious re-working. The area cleaning and grading was done based on the contour survey to optimise excavation and fillings. The plant lay out was suitably adjusted to ensure water flow out in natural slope direction. Slightly hilly area was not erased but some structures requiring elevation, like in case of clinker unloading tippler was placed there. Plant roads were laid and worked up to WBM level to ensure easy movement of vehicles during execution of project. Temporary drains were created to ensure no water logging during rains. Cross over pipes were laid in pre-defined way to ensure passage of cables during the construction.The foundation designs were reviewed and corrected, based on the strata actually observed during excavations. This helped in reducing depths of certain structures like clinker silosAreas for storage of equipment, steel fabrication, contractor’s office were so planned and established so that there is least interference in peak project period. It also helped in keeping project site neat and clean.Discipline was inculcated to remove dirt and scrap on daily/weekly basis Labour colonies were constructed using ready made structures and allocated to contractors for their labour housing just outside the plant area. Water and electricity arrangements were made but limits on consumption were laid and recovery made from contractors. This helped in reducing labour turnover in holidays and keep them in a healthy spirit.Strict adherence to QAP’s for all construction activities and front release for next work was done very religiously to ensure smooth continuity and reduce re-working and time loss to minimum.Payments were done to contractor on the bases of % work completed against plan and not only on random quantities presented. This was based on microplanning on weekly basis with contractors and regular monitoring to keep the project on course as desired.Monthly meetings with contractor’s project head from their main offices were held at site and problems were troubleshot to achieve the rate of progress and be on the defined time course. The team made SOP’s for ensuring timely and correct inputs to contractor’s to ensure deliverance of a good quality in defined time limits based on their past experience and following are some of the important matters they incorporated.Commissioning The operations team was inducted about four months before the commissioning so that hey get familiarised with the plan, documentation and also were encouraged to come out with suggestion for convenience and unhindered operability. The pre-commissioning checklists were prepared by the commissioning team and religiously implemented to ensure a plant run at: ONE GO After the team worked so hard and dedication the plant got commissioned and went on production stream with in four weeks of commissioning. Least problems were faced due strict quality adherence at each stage and extensive pre-commissioning checks. In this period, consent to operate was applied for with Pollution Control Board and same was obtained in time to declare commercial production. Hence it can be concluded that with a great team, planning and dedication, it was possible to complete half a MTPA capcity cement grinding unit in 26 months from the idea was frozen by top management team. Some of the points enumerated above may be of use to some one planning a project and I am sure; it can be improved further. There is always a scope for improvement. ABOUT THE AUTHOR: Shreekant Datar is a mechanical engineer with 37 years experience in the cement industry. Out of which, he has 20 plus years experience in projects with organisations like ACC, UltraTech Cement and Indiabulls. He has international exposure of projects in Nigeria in the capacity as project management consultant. Presently, he is a freelance consultant on cement projects. He can be reached at: datarsv12@gmail.com.

Next Story
Infrastructure Transport

Odisha to Get Kharagpur-Visakhapatnam Expressway Soon: Minister

A new greenfield highway connecting Kharagpur in West Bengal and Visakhapatnam in Andhra Pradesh, passing through Odisha, is set to be constructed soon. This expressway is poised to become a vital logistics corridor, enhancing high-speed transportation in the region. Works Minister Prithviraj Harichandan shared that preliminary preparations for the project have already commenced. He emphasised that the expressway would play a crucial role in the Gati Shakti Framework of the Central government, describing it as a groundbreaking initiative in road construction for Odisha. Greenfield roads typi..

Next Story
Infrastructure Urban

LTTS wins project to develop smart cities in Colorado USA

Mid-sized Indian IT services company L&T Technology Services (LTTS) announced on Monday a strategic partnership with the Colorado Smart Cities Alliance (CSCA) to develop smart city projects across Colorado by integrating innovation and technology. In a regulatory filing, LTTS stated that the collaboration would utilize its advanced engineering expertise to support CSCA's mission of enhancing urban living and creating sustainable ecosystems through smart city solutions. The partnership aims to develop sustainable, efficient, and technologically advanced communities by pooling resources and exp..

Next Story
Infrastructure Transport

Bengaluru Metro to Expand to 175 km by 2026, Boosting Urban Mobility

Bengaluru’s metro network is set for a major expansion, aiming to extend its total length to 175 km by 2026. This ambitious project is part of the Namma Metro initiative, designed to improve connectivity across the city, alleviate traffic congestion, and promote sustainable urban mobility. The expansion involves constructing new metro corridors, such as the Purple Line and the Outer Ring Road-Airport Line, which will link major city hubs, commercial centres, and residential areas. This development is expected to enhance accessibility for commuters throughout Bengaluru. A key highlight of t..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000