UPNEDA unveils 7 MW rooftop solar tenders with battery backup
POWER & RENEWABLE ENERGY

UPNEDA unveils 7 MW rooftop solar tenders with battery backup

Uttar Pradesh New and Renewable Energy Development Agency (UPNEDA) have released three tenders for the installation of 7 MW grid-connected net-metered rooftop solar projects with battery backup.

UPNEDA retains the flexibility to adjust the capacity by up to 25% during the contract negotiation and execution phase, and bidders are required to consent to these potential modifications to their orders.

Successful bidders are tasked with installing grid-connected net-metered rooftop solar projects with battery backup, ranging from 51 kW to 75 kW, amounting to a cumulative capacity of 1 MW. The projects must be completed within 120 days of receiving the work order.

Bids are to be submitted by February 21, 2024, with bid opening scheduled for the same day. Bidders must provide an earnest money deposit (EMD) of Rs 3.47 million (~$41,805). Additionally, selected bidders are required to furnish 5% of the project cost as a performance bank guarantee.

Bidders, directly or through resellers, should have supplied similar services for 30% of the bid capacity in at least one of the last three financial years, along with maintaining an average annual turnover of Rs 52.1 million (~$627,687) during the same period.

The second tender calls for the installation of grid-connected net-metered rooftop solar projects with battery backup, ranging from 1 kW to 10 kW, for a total capacity of 2 MW. Similar to Tender 1, projects must be completed within 120 days of receiving the work order.

Bids for Tender 2 are due by February 21, 2024, with bid opening on the same day. Bidders must submit an EMD of Rs 7.11 million (~$85,659). The selected bidders are obligated to furnish 5% of the project cost as a performance bank guarantee.

Similar eligibility criteria apply, requiring bidders to demonstrate experience in supplying comparable services and maintain an average annual turnover of Rs 106.7 million (~$1.28 million) over the last three years. For the third tender, selected bidders are tasked with installing grid-connected net-metered rooftop solar projects with battery backup, ranging from 11 kW to 50 kW, for a total capacity of 4 MW. The estimated cost for the project is Rs 687.4 million (~$8.28 million). As with the previous tenders, projects must be completed within 120 days of receiving the work order.

Bids for Tender 3 are due by February 22, 2024, with bid opening on the same day. Bidders are required to submit an EMD of Rs 13.74 million (~$165,537), and selected bidders must provide 5% of the project cost as a performance bank guarantee.

The eligibility criteria remain consistent with the previous tenders, requiring bidders to demonstrate experience and maintain an average annual turnover of Rs 206.2 million (~$2.48 million) over the last three years.

In a related development, in January, UPNEDA invited bids for a five-year operation and maintenance contract for 2.921 MW of mini-grid and decentralised distributed generation solar power projects installed on a revenue model basis.

Redefine the future of urban mobility! Join us at the Metro Rail Conference 2025 to explore groundbreaking ideas and insights. 👉 Register today!

Uttar Pradesh New and Renewable Energy Development Agency (UPNEDA) have released three tenders for the installation of 7 MW grid-connected net-metered rooftop solar projects with battery backup. UPNEDA retains the flexibility to adjust the capacity by up to 25% during the contract negotiation and execution phase, and bidders are required to consent to these potential modifications to their orders. Successful bidders are tasked with installing grid-connected net-metered rooftop solar projects with battery backup, ranging from 51 kW to 75 kW, amounting to a cumulative capacity of 1 MW. The projects must be completed within 120 days of receiving the work order. Bids are to be submitted by February 21, 2024, with bid opening scheduled for the same day. Bidders must provide an earnest money deposit (EMD) of Rs 3.47 million (~$41,805). Additionally, selected bidders are required to furnish 5% of the project cost as a performance bank guarantee. Bidders, directly or through resellers, should have supplied similar services for 30% of the bid capacity in at least one of the last three financial years, along with maintaining an average annual turnover of Rs 52.1 million (~$627,687) during the same period. The second tender calls for the installation of grid-connected net-metered rooftop solar projects with battery backup, ranging from 1 kW to 10 kW, for a total capacity of 2 MW. Similar to Tender 1, projects must be completed within 120 days of receiving the work order. Bids for Tender 2 are due by February 21, 2024, with bid opening on the same day. Bidders must submit an EMD of Rs 7.11 million (~$85,659). The selected bidders are obligated to furnish 5% of the project cost as a performance bank guarantee. Similar eligibility criteria apply, requiring bidders to demonstrate experience in supplying comparable services and maintain an average annual turnover of Rs 106.7 million (~$1.28 million) over the last three years. For the third tender, selected bidders are tasked with installing grid-connected net-metered rooftop solar projects with battery backup, ranging from 11 kW to 50 kW, for a total capacity of 4 MW. The estimated cost for the project is Rs 687.4 million (~$8.28 million). As with the previous tenders, projects must be completed within 120 days of receiving the work order. Bids for Tender 3 are due by February 22, 2024, with bid opening on the same day. Bidders are required to submit an EMD of Rs 13.74 million (~$165,537), and selected bidders must provide 5% of the project cost as a performance bank guarantee. The eligibility criteria remain consistent with the previous tenders, requiring bidders to demonstrate experience and maintain an average annual turnover of Rs 206.2 million (~$2.48 million) over the last three years. In a related development, in January, UPNEDA invited bids for a five-year operation and maintenance contract for 2.921 MW of mini-grid and decentralised distributed generation solar power projects installed on a revenue model basis.

Next Story
Infrastructure Energy

Oil Prices Hover Near 4-Month Highs

Oil prices eased but remained near four-month highs as the impact of fresh U.S. sanctions on Russian oil remained the market's main focus, ahead of U.S. inflation data this week. Brent futures slipped 53 cents, or 0.7%, to $80.48 a barrel by 0746 GMT, while U.S. West Texas Intermediate (WTI) crude fell 44 cents, or 0.6% to $78.38 a barrel. Prices jumped 2% on Monday after the U.S. Treasury Department imposed sanctions on Gazprom Neft and Surgutneftegas as well as 183 vessels that trade oil as part of Russia's so-called "shadow fleet" of tankers. "Headlines surrounding Russia oil sanctions ha..

Next Story
Infrastructure Energy

Brightnight Commissions 115 MW Hybrid Renewable Projects

BrightNight, a global renewable energy producer, has commissioned the first phase of its 115 MW hybrid renewable power project, Optima Maharashtra, in Dharashiv, southern Maharashtra. This is one of the state’s first co-located wind-solar projects and marks BrightNight’s initial energy delivery to India’s power grid, advancing the country’s mission to decarbonize its energy sector. Spanning approximately 14,000 acres, the project integrates advanced wind and solar technologies supported by BrightNight’s proprietary AI-enabled PowerAlpha® platform. The facility will generate dispatc..

Next Story
Real Estate

Lucknow Development Body Razes Illegal Construction on Nazul Land

Amid protests by the residents, over 30 illegal encroachments were razed by the Lucknow Development Authority (LDA) near Balu Adda on Butler road, located in front of Dhenumati Apartment. LDA officials said the encroachers failed to comply despite repeated warnings to vacate the area. Subsequently, LDA vice-chairman Prathamesh Kumar instructed the LDA team to carry out a drive to remove the encroachments. The LDA team under the command of nazul officer Sanjay Singh demolished about 24 illegal structures during the operation. Encroachers were given three days to vacate the area, failing which..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000