RUMSL invites tender for 170MW Neemuch solar project
POWER & RENEWABLE ENERGY

RUMSL invites tender for 170MW Neemuch solar project

RUMSL issued a request for proposal (RFP) for the development of a 170 MW grid-connected ground-mounted solar photovoltaic project in the Neemuch Solar Park in Madhya Pradesh. It was stated that the power generated from the project would be procured by Madhya Pradesh Power Management Company (MPPMCL) and West Central Railway (WCR).

The deadline to submit bids was mentioned as June 07, 2024, with bids set to be opened on the same day.

It was specified that RUMSL / Government of Madhya Pradesh (GoMP) would provide land for the project?s development, adhering to the terms and conditions outlined in the relevant land use agreement. Additionally, it was stated that RUMSL would provide bidders with the land layout within Neemuch Solar Park, identifying approximately 341 hectares of land for the project, which would then be handed over to the solar project developer.

Further details indicated that RUMSL would provide the power evacuation infrastructure, known as RUMSL Internal Evacuation Infrastructure, which included a 33/220 kV outdoor sub-station dedicated to the project at the Neemuch Solar Park site (Project Substation). This substation was to comprise two 110 MVA transformers, five 220 kV bays, nine 33 kV circuit terminals, and a single circuit 220 kV transmission line connecting the project substation to the bay at the 220/400 kV substation.

Regarding financial requirements, bidders were instructed to furnish an earnest money deposit equal to Rs 157.8 million as part of their Qualification Proposal. The selected bidder was also required to provide performance securities of Rs 2.32 million per MW within three days of accepting the letter of award. Additionally, bidders were mandated to have a minimum net worth of Rs 9.28 million per MW of the quoted capacity.

Consequences for project delays were outlined, stating that if the project?s commissioning exceeded six months from the Schedule Commencement of Supply Date (SCSD), and if 90% of the project?s capacity mentioned in the power purchase agreement had not been commissioned by that date, the developer would be excluded from participating in future bids issued by the procurers.

Furthermore, it was specified that bidders or any of their associates/affiliates should not have failed to perform any contract exceeding a contract value of Rs 3.94 billion, or had any contract terminated by any government or government instrumentality for breach by the bidder in the three years immediately preceding the Proposal Due Date.

RUMSL issued a request for proposal (RFP) for the development of a 170 MW grid-connected ground-mounted solar photovoltaic project in the Neemuch Solar Park in Madhya Pradesh. It was stated that the power generated from the project would be procured by Madhya Pradesh Power Management Company (MPPMCL) and West Central Railway (WCR). The deadline to submit bids was mentioned as June 07, 2024, with bids set to be opened on the same day. It was specified that RUMSL / Government of Madhya Pradesh (GoMP) would provide land for the project?s development, adhering to the terms and conditions outlined in the relevant land use agreement. Additionally, it was stated that RUMSL would provide bidders with the land layout within Neemuch Solar Park, identifying approximately 341 hectares of land for the project, which would then be handed over to the solar project developer. Further details indicated that RUMSL would provide the power evacuation infrastructure, known as RUMSL Internal Evacuation Infrastructure, which included a 33/220 kV outdoor sub-station dedicated to the project at the Neemuch Solar Park site (Project Substation). This substation was to comprise two 110 MVA transformers, five 220 kV bays, nine 33 kV circuit terminals, and a single circuit 220 kV transmission line connecting the project substation to the bay at the 220/400 kV substation. Regarding financial requirements, bidders were instructed to furnish an earnest money deposit equal to Rs 157.8 million as part of their Qualification Proposal. The selected bidder was also required to provide performance securities of Rs 2.32 million per MW within three days of accepting the letter of award. Additionally, bidders were mandated to have a minimum net worth of Rs 9.28 million per MW of the quoted capacity. Consequences for project delays were outlined, stating that if the project?s commissioning exceeded six months from the Schedule Commencement of Supply Date (SCSD), and if 90% of the project?s capacity mentioned in the power purchase agreement had not been commissioned by that date, the developer would be excluded from participating in future bids issued by the procurers. Furthermore, it was specified that bidders or any of their associates/affiliates should not have failed to perform any contract exceeding a contract value of Rs 3.94 billion, or had any contract terminated by any government or government instrumentality for breach by the bidder in the three years immediately preceding the Proposal Due Date.

Next Story
Infrastructure Transport

Bengaluru-Chennai Expressway: 72km Karnataka Stretch Completed

The National Highways Authority of India (NHAI) has completed the 72-km stretch of the Bengaluru-Chennai Expressway that falls within Karnataka. The project, which faced delays due to local objections over the relocation of the Guddamma Temple at Jinnagara, has now moved past its final hurdle. After over two years of negotiations with villagers and the state government, NHAI successfully shifted the temple and constructed the remaining 500-meter section of the road. Despite the construction being completed, NHAI has yet to announce when motorists will be allowed to use the new road. The expres..

Next Story
Infrastructure Transport

NHAI Officials Inspect NH 181 Ghat Section

Officials from the environment wing of the National Highways Authority of India (NHAI) inspected the ghat section of NH 181 between Kallar and Ooty on Monday, following a directive from the Madras High Court. The inspection was carried out in connection with a case concerning vertical cuttings made by the National Highways-Tamil Nadu state wing on the uphill side of the ghat road. The chief general manager of the NHAI's environmental wing, a respondent in the case, led the inspection of the 38-km stretch. During the visit, officials discovered multiple instances of illegal rock quarrying, wher..

Next Story
Infrastructure Urban

Andhra Govt Allocates Rs.167 Billion for Panchayat Raj

In a move to bolster rural development and promote local self-governance, the TDP-led NDA government in Andhra Pradesh has allocated Rs.167 billion for the Panchayat Raj and Rural Development Department. The government's commitment to reviving the Panchayat Raj system follows what it considers a period of neglect during the previous YSRC regime. Finance Minister Payyavula Keshav highlighted the state's efforts to restore the glory of the Panchayat Raj system, focusing on grassroots governance. As part of this initiative, Special Gram Sabhas were held across 13,326 panchayats on August 23 to a..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000