Rs 10k crore in pipeline for coal-fired thermal power project in UP
POWER & RENEWABLE ENERGY

Rs 10k crore in pipeline for coal-fired thermal power project in UP

The Uttar Pradesh Government will invest nearly Rs 10,500 crore in a Greenfield 1,320 megawatt (MW) thermal power project in Etah district of Western UP. The Jawaharpur thermal power project, comprising two units of 660 MW each and thus totalling 1,320 MW, will help the UP government in meeting the rising power demand, which has already touched 26,000 MW during summer. The plant has already been delayed by more than two years now and the state is making all out efforts to expedite its synchronisation.

M Devraj, chairman of both the apex state power utilities - UP Power Corporation (UPPCL) and UP Rajya Vidyut Utpadan Nigam Limited (UPRVUNL), has issued ordered officials to speed up the project. Jawaharpur Vidyut Utpadan Nigam Limited, which is setting up the 1,320 Mw plant, is a full subsidiary of UPRVUNL. The plant, which was initially estimated to be synchronised in 2021, witnessed inordinate delays compounded by the impact of the lockdown.

Later, the plant was expected to be synchronised by April this year, but fresh timeline was also missed. The state energy department mandarins have expressed displeasure at the serial delays, prompting the UPPCL chief to take the concerned officials and agencies to task. “The UPRVUNL chairman has been arduously making spot visits of the various thermal power projects, nudging for the ongoing civil and other works,” a government spokesperson said.

The Jawaharpur plant is being equipped with supercritical technology. It will be fed with coal from the Saharpur Jamarpani coal block in Jharkhand to be developed by UPRVUNL. A ‘Bridge Linkage’ for the project has been granted by the coal ministry.

The Uttar Pradesh Government will invest nearly Rs 10,500 crore in a Greenfield 1,320 megawatt (MW) thermal power project in Etah district of Western UP. The Jawaharpur thermal power project, comprising two units of 660 MW each and thus totalling 1,320 MW, will help the UP government in meeting the rising power demand, which has already touched 26,000 MW during summer. The plant has already been delayed by more than two years now and the state is making all out efforts to expedite its synchronisation.M Devraj, chairman of both the apex state power utilities - UP Power Corporation (UPPCL) and UP Rajya Vidyut Utpadan Nigam Limited (UPRVUNL), has issued ordered officials to speed up the project. Jawaharpur Vidyut Utpadan Nigam Limited, which is setting up the 1,320 Mw plant, is a full subsidiary of UPRVUNL. The plant, which was initially estimated to be synchronised in 2021, witnessed inordinate delays compounded by the impact of the lockdown.Later, the plant was expected to be synchronised by April this year, but fresh timeline was also missed. The state energy department mandarins have expressed displeasure at the serial delays, prompting the UPPCL chief to take the concerned officials and agencies to task. “The UPRVUNL chairman has been arduously making spot visits of the various thermal power projects, nudging for the ongoing civil and other works,” a government spokesperson said.The Jawaharpur plant is being equipped with supercritical technology. It will be fed with coal from the Saharpur Jamarpani coal block in Jharkhand to be developed by UPRVUNL. A ‘Bridge Linkage’ for the project has been granted by the coal ministry.

Next Story
Resources

Madhya Pradesh Champions Inclusive Tourism at Heritage Sites

On the occasion of World Heritage Day, Madhya Pradesh is taking a significant step toward inclusive tourism by making its historical sites accessible to all — especially persons with disabilities. The state is rolling out its ‘Accessibility Infrastructure and Development’ project at Maheshwar, Mandu, Dhar, and Orchha, aiming to create a more welcoming experience at these iconic cultural destinations.The initiative, under the leadership of Chief Minister Dr Mohan Yadav and Tourism Minister Shri Dharmendra Bhav Singh Lodhi, includes infrastructure upgrades such as ramps, Braille signage, w..

Next Story
Resources

Runwal Realty Onboards Sonam Kapoor as Brand Ambassador

Real estate major Runwal has unveiled a refreshed identity as Runwal Realty, signalling a renewed commitment to crafting spaces that stand the test of time. With this refresh, the brand unveils its new philosophy: “Building for Generations to Come” and welcomes Bollywood star and global fashion icon Sonam Kapoor as its brand ambassador. This evolved identity reflects Runwal Realty’s commitment to creating not just homes, but heirlooms—crafted through visionary design, meticulous planning, global design expertise and an unwavering focus on quality. With the customer at its core, each de..

Next Story
Infrastructure Urban

Emerging Trends in Infrastructure and Transport 2025: KPMG

KPMG’s latest report, The Great Reset: Emerging Trends in Infrastructure and Transport 2025 edition, sheds light on the profound changes transforming the global infrastructure landscape. As industries adapt to the challenges posed by climate change, economic pressures, and technological advancements, the report identifies key trends and provides actionable insights for leaders in infrastructure and transport sectors. “In today’s interconnected world, the lack of standardized supply chain practices is not just an operational challenge—it’s an environmental and economic one. We’..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?