Rs 10k crore in pipeline for coal-fired thermal power project in UP
POWER & RENEWABLE ENERGY

Rs 10k crore in pipeline for coal-fired thermal power project in UP

The Uttar Pradesh Government will invest nearly Rs 10,500 crore in a Greenfield 1,320 megawatt (MW) thermal power project in Etah district of Western UP. The Jawaharpur thermal power project, comprising two units of 660 MW each and thus totalling 1,320 MW, will help the UP government in meeting the rising power demand, which has already touched 26,000 MW during summer. The plant has already been delayed by more than two years now and the state is making all out efforts to expedite its synchronisation.

M Devraj, chairman of both the apex state power utilities - UP Power Corporation (UPPCL) and UP Rajya Vidyut Utpadan Nigam Limited (UPRVUNL), has issued ordered officials to speed up the project. Jawaharpur Vidyut Utpadan Nigam Limited, which is setting up the 1,320 Mw plant, is a full subsidiary of UPRVUNL. The plant, which was initially estimated to be synchronised in 2021, witnessed inordinate delays compounded by the impact of the lockdown.

Later, the plant was expected to be synchronised by April this year, but fresh timeline was also missed. The state energy department mandarins have expressed displeasure at the serial delays, prompting the UPPCL chief to take the concerned officials and agencies to task. “The UPRVUNL chairman has been arduously making spot visits of the various thermal power projects, nudging for the ongoing civil and other works,” a government spokesperson said.

The Jawaharpur plant is being equipped with supercritical technology. It will be fed with coal from the Saharpur Jamarpani coal block in Jharkhand to be developed by UPRVUNL. A ‘Bridge Linkage’ for the project has been granted by the coal ministry.
Redefine the future of urban mobility! Join us at the Metro Rail Conference 2025 to explore groundbreaking ideas and insights. 👉 Register today!

The Uttar Pradesh Government will invest nearly Rs 10,500 crore in a Greenfield 1,320 megawatt (MW) thermal power project in Etah district of Western UP. The Jawaharpur thermal power project, comprising two units of 660 MW each and thus totalling 1,320 MW, will help the UP government in meeting the rising power demand, which has already touched 26,000 MW during summer. The plant has already been delayed by more than two years now and the state is making all out efforts to expedite its synchronisation.M Devraj, chairman of both the apex state power utilities - UP Power Corporation (UPPCL) and UP Rajya Vidyut Utpadan Nigam Limited (UPRVUNL), has issued ordered officials to speed up the project. Jawaharpur Vidyut Utpadan Nigam Limited, which is setting up the 1,320 Mw plant, is a full subsidiary of UPRVUNL. The plant, which was initially estimated to be synchronised in 2021, witnessed inordinate delays compounded by the impact of the lockdown.Later, the plant was expected to be synchronised by April this year, but fresh timeline was also missed. The state energy department mandarins have expressed displeasure at the serial delays, prompting the UPPCL chief to take the concerned officials and agencies to task. “The UPRVUNL chairman has been arduously making spot visits of the various thermal power projects, nudging for the ongoing civil and other works,” a government spokesperson said.The Jawaharpur plant is being equipped with supercritical technology. It will be fed with coal from the Saharpur Jamarpani coal block in Jharkhand to be developed by UPRVUNL. A ‘Bridge Linkage’ for the project has been granted by the coal ministry.

Next Story
Infrastructure Urban

BHP Reports Higher Copper and Iron Ore Production in December Quarter

BHP Group, the world’s largest listed miner, reported increased production for the December quarter, with iron ore output inching up and copper production surging 17%. The gains were driven by operational efficiencies and richer ore quality at its key sites.Iron ore production at the South Flank operations in Western Australia reached 73.1 million metric tonne, slightly up from 72.7 million tonnein the same quarter last year and in line with the Visible Alpha consensus estimate of 72.8 million tonne.Copper output rose sharply to 510,700 tonne, attributed to improved processing and richer ore..

Next Story
Infrastructure Urban

India to Prioritise Railway Modernisation in 2025/26 Budget

The Indian government is set to significantly increase funding for railway modernisation in the upcoming federal budget while making a modest rise in road infrastructure allocations, according to two government sources. Prime Minister Narendra Modi’s administration, which has prioritised infrastructure spending to boost economic growth post-pandemic, is now shifting focus to railways due to challenges in road project execution. Finance Minister Nirmala Sitharaman will unveil the 2025/26 budget on February 1. The railways ministry is expected to receive a budget allocation of Rs 2.9..

Next Story
Infrastructure Transport

MSC Launches Feeder Service Linking Haldia and Vizhinjam Ports

Mediterranean Shipping Company S.A. (MSC), the world’s largest container shipping line, has introduced a feeder service connecting the Haldia Dock Complex of the Syama Prasad Mookerjee Port Authority with the newly operational container transshipment terminal at Vizhinjam, Kerala, managed by Adani Ports and Special Economic Zone Ltd. Previously, containers for the Kolkata/Haldia trade route were transshipped through Colombo, a regional hub. The new "Haldia Shuttle" service, operating every ten days, marks the first feeder service linking an Indian gateway port to Vizhinjam after India estab..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000