NTPC hopes to commission Telangana STTP by fiscal year-end
POWER & RENEWABLE ENERGY

NTPC hopes to commission Telangana STTP by fiscal year-end

The Telangana Super Thermal Power Plant (STPP) of the National Thermal Power Corporation is (NTPC) likely to be commissioned before the end of the current financial year (2022-23).

The NTPC plant at Ramagundam, which got delayed due to Covid and the re-engineering of the boiler as per new environment norms, among other things, is now in an advanced stage of completion.

The issue was raised in the Lok Sabha last week by several Telangana MPs, who sought reasons for the delay in conducting the trial run of the Telangana STPP Station-I of 800 MW, which was to be conducted in May 2020.

Union Minister of State for Power and Renewable Energy R K Singh said the first phase of the Telangana STPP (2×800 MW) had been delayed by 31 months.

The actual expenditure incurred and accrued to date was within the approved project cost of Rs 109.98 billion, he added. Singh further said that the first unit of the project was in an advanced stage of commissioning and after the completion of steam blowing and related advanced commissioning activities, the process will be authorised likely by the end of this fiscal year. The Centre had promised to establish a 4,000 MW (5x800 MW) supercritical thermal power plant at Ramagundam under the Andhra Pradesh Reorganisation Act.

See also:
L&T wins orders from Vedanta for its hydrocarbon business
India plans to commission 20 N-power plants by 2031


The Telangana Super Thermal Power Plant (STPP) of the National Thermal Power Corporation is (NTPC) likely to be commissioned before the end of the current financial year (2022-23). The NTPC plant at Ramagundam, which got delayed due to Covid and the re-engineering of the boiler as per new environment norms, among other things, is now in an advanced stage of completion. The issue was raised in the Lok Sabha last week by several Telangana MPs, who sought reasons for the delay in conducting the trial run of the Telangana STPP Station-I of 800 MW, which was to be conducted in May 2020. Union Minister of State for Power and Renewable Energy R K Singh said the first phase of the Telangana STPP (2×800 MW) had been delayed by 31 months. The actual expenditure incurred and accrued to date was within the approved project cost of Rs 109.98 billion, he added. Singh further said that the first unit of the project was in an advanced stage of commissioning and after the completion of steam blowing and related advanced commissioning activities, the process will be authorised likely by the end of this fiscal year. The Centre had promised to establish a 4,000 MW (5x800 MW) supercritical thermal power plant at Ramagundam under the Andhra Pradesh Reorganisation Act. See also: L&T wins orders from Vedanta for its hydrocarbon businessIndia plans to commission 20 N-power plants by 2031

Next Story
Infrastructure Transport

Railway stations in Prayagraj undergo major passenger facility expansion

The Railway Board Chairman and CEO, Satish Kumar, conducted an extensive inspection on Saturday alongside the General Manager of Northern Railway and the officiating General Manager of North Central Railway. Their visit focused on various ongoing projects at multiple stations across the Northern and North Central Railway zones, with particular attention to enhancing facilities for the upcoming Maha Kumbh. During the inspection, Chairman Kumar reviewed the construction of a vital bridge over the River Ganga, specifically between Jhunsi and Prayagraj Rambagh. This bridge is expected to significa..

Next Story
Infrastructure Transport

Madurai-Thoothukudi broad gauge line works under review

The construction of the Madurai-Thoothukudi broad gauge line, which includes the crucial Melmarudur-Tiruparankundram project, is currently under careful review. This update comes from Southern Railway's assistant public information officer, J Kumarasubramanian, following an RTI inquiry made by a concerned citizen, Dayanand Krishnan. The new broad gauge line is projected to cover a total length of 143.5 km, with the initial 18 km stretch between Milavittan and Melmarudur completed and sanctioned by the Commission of Railway Safety on March 8, 2022. While substantial progress has been made on t..

Next Story
Real Estate

DLF expects Rs 26,000 cr from super luxury project in Gurugram

Realty giant DLF is projecting impressive revenue of Rs 26,000 crore from its newly unveiled super-luxury project, The Dahlias, situated in the heart of Gurugram. Ashok Tyagi, the Managing Director of DLF, shared these insights during a recent conference call with market analysts, highlighting the project's potential amidst rising demand for high-end residential properties. The Dahlias project spans an expansive 17 acres and is set to feature approximately 420 ultra-luxury apartments, each boasting a minimum size of 10,300 square feet. This ambitious development has already garnered significan..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000