MNRE Extends Timeline for Ultra Mega Solar Park Program
POWER & RENEWABLE ENERGY

MNRE Extends Timeline for Ultra Mega Solar Park Program

The 'Development of Solar Parks and Ultra Mega Solar Power Projects' programme now has a deadline of March 31, 2026 (FY 2026), as opposed to the former deadline of FY 2024, according to the Ministry of New and Renewable Energy (MNRE).

There are no financial consequences to the longer schedule. It occurs at a time when the construction of the solar power park has been extremely slow, with only nine of the 57 permitted solar parks completed as of February 2023 and an additional eight halfway installed, with a combined capacity of 10,117 MW.

The programme, which was initially implemented in December 2014, was launched with the goal of establishing at least 25 solar parks and 20 GW ultra mega solar power plants within five years beginning with FY 2014–15.

In March 2017, the program's capacity was raised to 40 GW, and it was suggested that parks be constructed by FY 2023–2024.

In order to qualify for the programme, solar parks must have a capacity of 500 MW or more. Smaller parks are only taken into consideration in cases where there is a severe lack of contiguous or non- agricultural land.

The programme was put in place to promote the quick installation of grid-connected solar power projects for massive electricity production. As they addressed the issues of land acquisition and availability, solar parks were appealing. Solar parks have fewer potential legal problems and other obstacles, which makes them a financially viable choice for developers.

The 'Development of Solar Parks and Ultra Mega Solar Power Projects' programme now has a deadline of March 31, 2026 (FY 2026), as opposed to the former deadline of FY 2024, according to the Ministry of New and Renewable Energy (MNRE). There are no financial consequences to the longer schedule. It occurs at a time when the construction of the solar power park has been extremely slow, with only nine of the 57 permitted solar parks completed as of February 2023 and an additional eight halfway installed, with a combined capacity of 10,117 MW. The programme, which was initially implemented in December 2014, was launched with the goal of establishing at least 25 solar parks and 20 GW ultra mega solar power plants within five years beginning with FY 2014–15. In March 2017, the program's capacity was raised to 40 GW, and it was suggested that parks be constructed by FY 2023–2024. In order to qualify for the programme, solar parks must have a capacity of 500 MW or more. Smaller parks are only taken into consideration in cases where there is a severe lack of contiguous or non- agricultural land. The programme was put in place to promote the quick installation of grid-connected solar power projects for massive electricity production. As they addressed the issues of land acquisition and availability, solar parks were appealing. Solar parks have fewer potential legal problems and other obstacles, which makes them a financially viable choice for developers.

Next Story
Infrastructure Transport

Locals urge CM to opt for road bypass over flyover at Dandeavaddo

Chinchinim villagers respectfully requested Pramod Sawant, Chief Minister, to instruct the Public Works Department (PWD) and the National Highway authorities to construct a road bypass instead of a flyover on the Dandeavaddo stretch of NH66. The villagers, led by Sarpanch Frank Viegas and Velim MLA Cruz Silva, also raised the long-standing issue of building the Chinchinim Panchayat Ghar and a multi-purpose project on panchayat land that was acquired more than 15 years ago. The delegation met the Chief Minister at the St. Sebastian Chapel junction in Chinchinim as he was returning home from a..

Next Story
Infrastructure Transport

MLA Yashpal Suvarna Announces Malpe-Udupi Highway Construction from Nov 6

MLA Yashpal Suvarna instructed officials to commence work on the Malpe-Udupi Highway on Wednesday. A meeting took place, attended by MP Kota Shrinivas Poojary, Udupi MLA Yashpal Suvarna, and Kaup MLA Suresh Shetty Gurme, to discuss the National Highway 169A project, which spans from Malpe to Udupi, covering areas like Hiriyadka, Parkala, and Perdur. The project had experienced delays due to incomplete land acquisition, but compensation notices have now been issued to the landowners. Of the 214 land acquisition files, 19 pertain to government land, while 195 involve private owners. Notices ha..

Next Story
Infrastructure Transport

NHAI to build flyover and underpass on Jaipur's 200-Feet bypass

Following a recent survey, the National Highways Authority of India (NHAI) decided to construct a flyover and an underpass at the 200-Feet Bypass crossing, known to be one of the city's most congested areas. The Union Ministry of Road, Transport and Highways (MoRTH) is expected to float tenders for the project in January of the following year. Once construction begins, it is projected to take approximately one and a half years to complete. NHAI plans to submit a detailed project report (DPR) within the next two months. Ajay Arya from NHAI explained that the initiative aims to alleviate tra..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000