Maharashtra orders twice a month contract revision for C&I customers
POWER & RENEWABLE ENERGY

Maharashtra orders twice a month contract revision for C&I customers

In a recent order, the Maharashtra Electricity Regulatory Commission (MERC) allowed for contract demand revisions up to two times for high-tension (HT) commercial and industrial (C&I) consumers and once for low-tension (LT) C&I consumers in a billing cycle up to 31 March 2022.

Kalika Steel Alloys and 27 other companies had petitioned the Commission, requesting that the contract be revised. They sought an extension of the Commission's earlier order, which allowed for multiple revisions of the contract demand in light of the disruption caused by the Covid-19 pandemic.

In an earlier order, the Commission granted relief from monthly contract demand revisions, which was later extended until 31 March 2021. Contract demand is the amount of electricity (kW) that a customer requests from a distribution company (discom) over a specific time period.

The petitioners claimed that they had carried out their operations in such a way that the Maharashtra State Electricity Distribution Company Limited's (MSEDCL) operations had not been put under undue stress over the last nine months.

In their submissions, the petitioners stated that they believe the economic situation will not improve for some time due to the magnitude of the Covid-19 crisis. They acknowledged that they were in a severe financial bind, as the cost of electricity accounted for roughly 60% of their total cost of production.

MSEDCL added in its response that the Commission's earlier order was due to the difficulties faced by the industries as a result of lower demand. The current situation was different because demand had returned to normal.

The discom also stated that only a small number of consumers had taken advantage of the Commission's benefits. As a result, the difficulties cited by the petitioners did not affect the vast majority of Maharashtra consumers.

However, Adani Electricity Mumbai Limited responded that the entire country, as well as Maharashtra, was currently reeling from the second wave of the Covid-19 pandemic and that the lockdown had resulted in the closure of most non-essential establishments.

Taking these factors into account, the company stated that it had no objections to the Commission's earlier order's extension request, allowing the contract demand to be revised.

Tata Power Corporation expressed similar sentiments and stated that it would follow the Commission's order.

The Commission noted that citing the consequences of the Covid-19 pandemic, the petitioners stated that the economic scenario was unlikely to improve anytime soon, creating uncertainty in business, supply chain planning, and logistics. As a result, they requested permission to extend the provision for multiple revisions in the contract demand until 31 March 2022.

MERC observed that, given the current pandemic situation, consumers required the flexibility to revise their contract demand for a longer period of time. In addition, the number of occasions permitted in previous practice directions needed to be adjusted to account for changed circumstances.

As a result, the Commission determined that it was appropriate to allow contract demand revisions for HT C&I customers on two occasions during a billing month. Similarly, the LT consumer can only change the contract demand once per billing month.

MERC stated that for short-term open access consumers, contract demand revision would be prohibited during the open access period. Furthermore, medium- and long-term open access consumers should apply for a revision in open access permissions commensurate with their intended revised contract demand.

The Commission noted that MSEDCL had raised the provision of net-metering regulations that linked maximum allowable net metering rooftop capacity to consumer contract demand, subject to a higher limit of 1 MW. Because of the change in contract demand, the allowable capacity of net metering had to be reduced accordingly.

The Delhi Electricity Regulatory Commission reduced fixed charges for industrial and non-domestic consumers by 50% in September of last year. The Commission's notification stated that several C&I establishments had not used their contracted capacity during the lockdown period (until 30 May 2020).

Image Source


Also read: Govt urges electricity regulators to issue tariff orders on time

Also read: Power ministry asks regulators to revise tariffs by April 1 each year

In a recent order, the Maharashtra Electricity Regulatory Commission (MERC) allowed for contract demand revisions up to two times for high-tension (HT) commercial and industrial (C&I) consumers and once for low-tension (LT) C&I consumers in a billing cycle up to 31 March 2022. Kalika Steel Alloys and 27 other companies had petitioned the Commission, requesting that the contract be revised. They sought an extension of the Commission's earlier order, which allowed for multiple revisions of the contract demand in light of the disruption caused by the Covid-19 pandemic. In an earlier order, the Commission granted relief from monthly contract demand revisions, which was later extended until 31 March 2021. Contract demand is the amount of electricity (kW) that a customer requests from a distribution company (discom) over a specific time period. The petitioners claimed that they had carried out their operations in such a way that the Maharashtra State Electricity Distribution Company Limited's (MSEDCL) operations had not been put under undue stress over the last nine months. In their submissions, the petitioners stated that they believe the economic situation will not improve for some time due to the magnitude of the Covid-19 crisis. They acknowledged that they were in a severe financial bind, as the cost of electricity accounted for roughly 60% of their total cost of production. MSEDCL added in its response that the Commission's earlier order was due to the difficulties faced by the industries as a result of lower demand. The current situation was different because demand had returned to normal. The discom also stated that only a small number of consumers had taken advantage of the Commission's benefits. As a result, the difficulties cited by the petitioners did not affect the vast majority of Maharashtra consumers. However, Adani Electricity Mumbai Limited responded that the entire country, as well as Maharashtra, was currently reeling from the second wave of the Covid-19 pandemic and that the lockdown had resulted in the closure of most non-essential establishments. Taking these factors into account, the company stated that it had no objections to the Commission's earlier order's extension request, allowing the contract demand to be revised. Tata Power Corporation expressed similar sentiments and stated that it would follow the Commission's order. The Commission noted that citing the consequences of the Covid-19 pandemic, the petitioners stated that the economic scenario was unlikely to improve anytime soon, creating uncertainty in business, supply chain planning, and logistics. As a result, they requested permission to extend the provision for multiple revisions in the contract demand until 31 March 2022. MERC observed that, given the current pandemic situation, consumers required the flexibility to revise their contract demand for a longer period of time. In addition, the number of occasions permitted in previous practice directions needed to be adjusted to account for changed circumstances. As a result, the Commission determined that it was appropriate to allow contract demand revisions for HT C&I customers on two occasions during a billing month. Similarly, the LT consumer can only change the contract demand once per billing month. MERC stated that for short-term open access consumers, contract demand revision would be prohibited during the open access period. Furthermore, medium- and long-term open access consumers should apply for a revision in open access permissions commensurate with their intended revised contract demand. The Commission noted that MSEDCL had raised the provision of net-metering regulations that linked maximum allowable net metering rooftop capacity to consumer contract demand, subject to a higher limit of 1 MW. Because of the change in contract demand, the allowable capacity of net metering had to be reduced accordingly. The Delhi Electricity Regulatory Commission reduced fixed charges for industrial and non-domestic consumers by 50% in September of last year. The Commission's notification stated that several C&I establishments had not used their contracted capacity during the lockdown period (until 30 May 2020). Image Source Also read: Govt urges electricity regulators to issue tariff orders on time Also read: Power ministry asks regulators to revise tariffs by April 1 each year

Next Story
Products

Viva ACP Launches FR A1-Rated Honeycomb Panels for Fire Safety

Viva, Asia’s largest manufacturer and supplier of aluminium composite panels (ACP) introduced its FR A1-rated Honeycomb Panels, setting a new industry benchmark for fire safety and architectural excellence. Engineered to deliver exceptional performance, these panels combine advanced fire-resistance technology with aesthetic versatility, offering a revolutionary solution for safety-critical environments.The FR A1 rating represents the highest standard of fire resistance under the European Standard EN 13501-1, signifying non-combustibility and zero contribution to fire, smoke, or toxic emissio..

Next Story
Real Estate

Almal Real Estate Expands into Commercial, Global Markets

Almal Real Estate Development is soon to announce its upcoming expansion into new verticals and international markets as part of its strategic growth plans for 2030. The company, known for its innovative luxury residential and hospitality developments, is preparing to diversify into the commercial sector with the introduction of The Smart Space, a network of business centers in UAE featuring five-star amenities. Additionally, Almal is entering new markets in Bali and Thailand as a community developer, focusing on villa and townhouse projects.The expansion into the commercial real estate sector..

Next Story
Infrastructure Urban

NABARD Approves Rs 9.03 Billion for 127 Projects in Himachal

The Himachal Pradesh government has secured approval from the National Bank for Agriculture and Rural Development (NABARD) for 127 projects worth Rs 9.03 billion for the 2024-25 fiscal, Chief Minister Sukhvinder Singh Sukhu announced. During a meeting with MLAs from Kangra, Kullu, Kinnaur, Solan, Chamba, Bilaspur, and Lahaul-Spiti districts to discuss priorities for the 2025-26 budget, Sukhu said the approved projects include 50 MLA-priority schemes under the Public Works Department, valued at Rs 4.12 billion, and 23 MLA-priority schemes under the Jal Shakti Vibhag, costing Rs 1.79 billio..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?