Maharashtra: MSEDCL invite bids for 431 MW solar electricity projects
POWER & RENEWABLE ENERGY

Maharashtra: MSEDCL invite bids for 431 MW solar electricity projects

Under Component-A of the Pradhan Mantri Kisan Urja Suraksha evam Utthan Mahabhiyan (PM KUSUM) initiative, the Maharashtra State Electricity Distribution Company Limited (MSEDCL) has invited bids for 431 MW of solar electricity from decentralised solar projects with capacities ranging from 500 kW to 2 MW.

The deadline for bid submissions is June 3, 2022. The tender has a ceiling tariff of 23.10/kWh established by MSEDCL.

The government plans to build 10,000 MW of grid-connected solar power plants with individual project sizes of up to 2 MW under Component A of the PM-KUSUM programme.

As an earnest money deposit, bidders must contribute $100,000 per MW.

Within 30 days of receiving the letter of award, the winning bidder must provide a performance bank guarantee in the amount of 500,000 per MW.

The chosen bidders will engage in power purchase agreements (PPAs) with MSEDCL for 25 years from the start of commercial operation.

To prevent the high cost of sub-transmission lines and reduce transmission losses, solar power projects will be placed within a five-kilometre radius of substations.

To reduce technological risk and ensure project commissioning on schedule, only commercially established and operational technologies can be chosen.

Construction projects that have not yet been commissioned, and projects that have been commissioned but have no long-term PPA with any agency and are selling electricity on a short-term or merchant plant basis would be eligible.

Bidders can participate as an individual or as a group of farmers, cooperatives, panchayats, farmer producer associations, or water user organisations, and the project can be built upon their land.

If bidders can't come up with the money, they can put up the projects by signing a land leasing arrangement with a developer.

The annual lease rate to be paid to the landowner will be $730,000 per acre, with a 3% annual increase. The leasing deal would last between 26 and 30 years, as both sides have agreed.

Individual farmers, farmer groups, cooperatives, panchayats, farmer producer organisations, water user associations, and farmers establishing the project on their lands are excluded from the financial qualifying criteria.

If the project is to be built on leased property, the bidder's net worth must be at least $10 million. The bidder's yearly turnover should be at least $2.5 million.

As of the end day of the preceding financial year (FY), the developer must have an internal resource generating capability in the form of profit before depreciation, interest, and taxes for a minimum of 1 million of the quoted capacity.

To satisfy the working capital need, the developer should obtain an in-principle commitment from a financing institution pledging a Line of Credit for a minimum of 21.25 million of the stated capacity.

The project should be built to supply energy at the MSEDCL substation's 11/22 kV level. The selected bidder would be responsible for establishing grid connectivity with MSEDCL.

According to MSEDCL, the claimed capacity usage factor should not be less than 15% throughout the year.

Image Source

Also read: SJVN invites bid from consultants to draft DPR for solar projects

Under Component-A of the Pradhan Mantri Kisan Urja Suraksha evam Utthan Mahabhiyan (PM KUSUM) initiative, the Maharashtra State Electricity Distribution Company Limited (MSEDCL) has invited bids for 431 MW of solar electricity from decentralised solar projects with capacities ranging from 500 kW to 2 MW. The deadline for bid submissions is June 3, 2022. The tender has a ceiling tariff of 23.10/kWh established by MSEDCL. The government plans to build 10,000 MW of grid-connected solar power plants with individual project sizes of up to 2 MW under Component A of the PM-KUSUM programme. As an earnest money deposit, bidders must contribute $100,000 per MW. Within 30 days of receiving the letter of award, the winning bidder must provide a performance bank guarantee in the amount of 500,000 per MW. The chosen bidders will engage in power purchase agreements (PPAs) with MSEDCL for 25 years from the start of commercial operation. To prevent the high cost of sub-transmission lines and reduce transmission losses, solar power projects will be placed within a five-kilometre radius of substations. To reduce technological risk and ensure project commissioning on schedule, only commercially established and operational technologies can be chosen. Construction projects that have not yet been commissioned, and projects that have been commissioned but have no long-term PPA with any agency and are selling electricity on a short-term or merchant plant basis would be eligible. Bidders can participate as an individual or as a group of farmers, cooperatives, panchayats, farmer producer associations, or water user organisations, and the project can be built upon their land. If bidders can't come up with the money, they can put up the projects by signing a land leasing arrangement with a developer. The annual lease rate to be paid to the landowner will be $730,000 per acre, with a 3% annual increase. The leasing deal would last between 26 and 30 years, as both sides have agreed. Individual farmers, farmer groups, cooperatives, panchayats, farmer producer organisations, water user associations, and farmers establishing the project on their lands are excluded from the financial qualifying criteria. If the project is to be built on leased property, the bidder's net worth must be at least $10 million. The bidder's yearly turnover should be at least $2.5 million. As of the end day of the preceding financial year (FY), the developer must have an internal resource generating capability in the form of profit before depreciation, interest, and taxes for a minimum of 1 million of the quoted capacity. To satisfy the working capital need, the developer should obtain an in-principle commitment from a financing institution pledging a Line of Credit for a minimum of 21.25 million of the stated capacity. The project should be built to supply energy at the MSEDCL substation's 11/22 kV level. The selected bidder would be responsible for establishing grid connectivity with MSEDCL. According to MSEDCL, the claimed capacity usage factor should not be less than 15% throughout the year. Image Source Also read: SJVN invites bid from consultants to draft DPR for solar projects

Next Story
Infrastructure Energy

Oil Prices Rise Amid Iran-Israel Tensions Despite Record U.S. Output

Oil prices increased due to reports that Iran was preparing a retaliatory strike on Israel from Iraq, although record output from the United States tempered these gains. Brent crude futures rose by 29 cents, or 0.4%, to settle at $73.10 a barrel, while U.S. West Texas Intermediate (WTI) crude gained 23 cents, or 0.3%, closing at $69.49. Both benchmarks had reached session highs of over $2 a barrel earlier in the day. Analyst Ole Hvalbye from SEB Research commented that any Iranian response might be restrained, similar to Israel's limited strike from the previous weekend, suggesting that such a..

Next Story
Infrastructure Urban

South and Southeast Asia to Invest Over $20 Billion in EV Development

A recent report by S&P Global Ratings projects that South and Southeast Asia will invest over $20 billion in electric vehicle (EV) development in the coming years, with India poised to attract significant EV-related investments. The report highlights India's vast market potential as a key driver for this growth. According to the report, the Tata and JSW groups are expected to invest over $30 billion in EVs and EV materials over the next decade, with approximately $10 billion allocated specifically for projects in South and Southeast Asia. The adoption of electric vehicles in India is anticip..

Next Story
Infrastructure Urban

India and Saudi Arabia Explore Collaboration in Emerging Sectors

India and Saudi Arabia are exploring partnerships in emerging fields such as fintech, new technologies, energy efficiency, clean hydrogen, textiles, and mining to strengthen trade and investment ties, an official statement revealed on Friday. The discussions took place during Commerce and Industry Minister Piyush Goyal's visit to Riyadh, where he co-chaired the second meeting of the Economy and Investment Committee under the India-Saudi Strategic Partnership Council (SPC) with Saudi Energy Minister Abdulaziz bin Salman Al-Saud on October 30. These sectors were identified as high-potential are..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000