KERC okays Rs 8.40 per kWh tariff for Cambria Solar PPA with BESCOM
POWER & RENEWABLE ENERGY

KERC okays Rs 8.40 per kWh tariff for Cambria Solar PPA with BESCOM

The Karnataka Electricity Regulatory Commission (KERC) has given its nod for a tariff of Rs 8.40 per kWh as per the power purchase agreement (PPA) signed between Bangalore Electricity Supply Company Ltd (BESCOM) and the developer of the project—Cambria Solar.

KERC also approved the extension of six months granted by BESCOM for the commissioning date of the solar project.

Cambria Solar had filed a petition requesting the KERC to approve the extension of six months granted by BESCOM to the scheduled commercial operation date (SCOD) as agreed between the parties. It had also requested the regulator to approve the tariff of Rs 8.40 per kWh from the project’s commercial operation date for the whole term of the PPA.

A land-owning farmer, Gangaraju, had applied for a 3 MW solar power project under the solar program initiated by the Karnataka Renewable Energy Development Ltd (KREDL). The project was allotted to him.

BESCOM, in its meeting held in July 2015, gave consent for the purchase of solar power from the project. Both the parties signed the PPA in the same month, and subsequently, the PPA was approved by the KERC in August 2015.

As per the PPA, the scheduled date of completion was to be achieved within 18 months from the PPA signing. The power to extend the time for commissioning was vested with BESCOM.

According to the PPA, the project promoter had the right to form a special purpose vehicle (SPV) after the PPA execution. Accordingly, Cambria Solar was incorporated as an SPV.

The developer informed BESCOM in November 2016 that it had applied for the bay allocation from the Karnataka Power Transmission Corporation Limited (KPTCL) but had not received the bay allotment due to augmentation of the transformer at 66/11 KV Moregere Substation.

The developer sought an extension of six months from January 6, 2017, which it perceived to be the SCOD. KPTCL granted evacuation approval to the petitioner.

Later, BESCOM granted an extension of six months from the SCOD as per the PPA, subject to the bank guarantee extension. The developer said it was entitled to a tariff of Rs 8.40 per kWh, according to the PPA.

BESCOM, in its submission, said that as the developer was unable to execute the project on time, a letter was addressed to it seeking an extension of time for commissioning the project.

The Karnataka government issued an order in November 2016, directing all the electricity supply companies (escoms) to constitute a three-member committee to consider and dispose of the farmers’ and developers’ requests.

After detailed discussions, the committee suggested the approval be granted for the extension of SCOD for up to six months. According to KERC, it was not in dispute that PPA was executed on 7 July 2015, and the effective date meant the date of signing of the agreement by the parties, ie, 7 July 2015.

The regulator noted that in pursuance of the government’s direction, a three-member committee decided to approve an extension of SCOD by six months.

KERC noted that the developer had applied for power evacuation in September 2016, and KPTCL gave approval for evacuation in December 2016, after a lapse of more than two months.

BESCOM granted an extension by six months considering these facts and considering a substantial investment in the project.

The regulator noted that the petitioner was entitled to the tariff of Rs 8.40 per kWh from the commercial operation date because it had implemented the project within the extended time. Due to the ‘force majeure’ event, it could not commission the project within 18 months from the effective date.

Image Source


Also read: GESCOM invites bids for 10 MW rooftop solar net metering in Karnataka

The Karnataka Electricity Regulatory Commission (KERC) has given its nod for a tariff of Rs 8.40 per kWh as per the power purchase agreement (PPA) signed between Bangalore Electricity Supply Company Ltd (BESCOM) and the developer of the project—Cambria Solar. KERC also approved the extension of six months granted by BESCOM for the commissioning date of the solar project. Cambria Solar had filed a petition requesting the KERC to approve the extension of six months granted by BESCOM to the scheduled commercial operation date (SCOD) as agreed between the parties. It had also requested the regulator to approve the tariff of Rs 8.40 per kWh from the project’s commercial operation date for the whole term of the PPA. A land-owning farmer, Gangaraju, had applied for a 3 MW solar power project under the solar program initiated by the Karnataka Renewable Energy Development Ltd (KREDL). The project was allotted to him. BESCOM, in its meeting held in July 2015, gave consent for the purchase of solar power from the project. Both the parties signed the PPA in the same month, and subsequently, the PPA was approved by the KERC in August 2015. As per the PPA, the scheduled date of completion was to be achieved within 18 months from the PPA signing. The power to extend the time for commissioning was vested with BESCOM. According to the PPA, the project promoter had the right to form a special purpose vehicle (SPV) after the PPA execution. Accordingly, Cambria Solar was incorporated as an SPV. The developer informed BESCOM in November 2016 that it had applied for the bay allocation from the Karnataka Power Transmission Corporation Limited (KPTCL) but had not received the bay allotment due to augmentation of the transformer at 66/11 KV Moregere Substation. The developer sought an extension of six months from January 6, 2017, which it perceived to be the SCOD. KPTCL granted evacuation approval to the petitioner. Later, BESCOM granted an extension of six months from the SCOD as per the PPA, subject to the bank guarantee extension. The developer said it was entitled to a tariff of Rs 8.40 per kWh, according to the PPA. BESCOM, in its submission, said that as the developer was unable to execute the project on time, a letter was addressed to it seeking an extension of time for commissioning the project. The Karnataka government issued an order in November 2016, directing all the electricity supply companies (escoms) to constitute a three-member committee to consider and dispose of the farmers’ and developers’ requests. After detailed discussions, the committee suggested the approval be granted for the extension of SCOD for up to six months. According to KERC, it was not in dispute that PPA was executed on 7 July 2015, and the effective date meant the date of signing of the agreement by the parties, ie, 7 July 2015. The regulator noted that in pursuance of the government’s direction, a three-member committee decided to approve an extension of SCOD by six months. KERC noted that the developer had applied for power evacuation in September 2016, and KPTCL gave approval for evacuation in December 2016, after a lapse of more than two months. BESCOM granted an extension by six months considering these facts and considering a substantial investment in the project. The regulator noted that the petitioner was entitled to the tariff of Rs 8.40 per kWh from the commercial operation date because it had implemented the project within the extended time. Due to the ‘force majeure’ event, it could not commission the project within 18 months from the effective date. Image Source Also read: GESCOM invites bids for 10 MW rooftop solar net metering in Karnataka

Next Story
Building Material

JK Cement emerges successful bidder for Mahan coal mine in Madhya Pradesh

This marks the company’s second commercial coal block win, following its acquisition of the West of Shahdol (South) coal block. "The company is committed to becoming self-reliant for its existing cement plants and upcoming projects," JKC stated. The surplus coal from the mine will be sold commercially. The vesting order was handed over to JK Cement during a ceremony at Shastri Bhawan, New Delhi, a critical milestone for commencing mining operations within the stipulated timeline...

Next Story
Building Material

Prism Johnson's cement division goes live with Ramco ERP Suite

Prism Johnson has successfully gone live with the Ramco ERP Suite for its Cement Division. This milestone marks a significant step in Prism Johnson's digital transformation journey, leveraging Ramco Systems' advanced enterprise solutions and process control systems to streamline business processes, manufacturing operations and drive efficiency. The implementation includes cutting-edge modules for Maintenance, Sales, Distribution, Finance, Procurement, Manufacturing, Quality, and HR Management (HRM). These solutions enable Prism Johnson to achieve seamless integration across its business and wo..

Next Story
Infrastructure Urban

Indian shadow bank Shriram Finance gets record $1.28 billion loan

Shriram Finance Ltd. is reported to have borrowed $1.28 billion in a multi-currency social loan, marking the largest offshore facility ever undertaken by an Indian shadow lender. According to a press release issued by Shriram, the deal is divided across the dollar, euro, and dirham. Sources familiar with the transaction, who wished to remain anonymous, indicated that the tenors in the multi-tranche deal range from three to five years. This loan adds to the surge of offshore debt sales by Indian shadow lenders this year, a trend prompted by the Reserve Bank of India's tightening of rules in Nov..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000