Haryana seeks bids to procure 500 MW of solar power
POWER & RENEWABLE ENERGY

Haryana seeks bids to procure 500 MW of solar power

In order to deliver 500 MW of solar electricity from grid-connected solar projects in Haryana, the Haryana electricity Purchase Center (HPPC), a joint forum of the Uttar Haryana Bijli Vitran Nigam (UHBVN) and Dakshin Haryana Bijli Vitran Nigam (DHBVN), has issued an invitation for bids.

The deadline for submitting online bids is May 24, 2023. The following day, the bids will be opened. As a bid processing cost, bidders must deposit Rs 10 million ($121.87)/MW plus 18% GST. They must additionally provide an earnest money deposit of Rs 80 billions ($9,749/MW).

After issuing the Letter of Intent and prior to signing the power purchase agreement (PPA), the successful bidder will be required to provide a bank guarantee in the amount of $2 million (or $24,373/MW).

For the tender, HPPC has set a ceiling rate of 3.38 ($0.041)/kWh.

With the winning bids, HPPC will sign PPAs that will last 25 years from the solar projects' start of commercial operation.

After the PPA is signed, the solar developer has 18 months to complete the project.

According to the terms of the PPA that will be signed between the solar power developer and HPPC, the developer will be in charge of the design, financing, acquisition of land, engineering, acquisition, construction, operation, and maintenance of the projects. The 500 MW total capacity of the projects that will be chosen under this contract may be put anywhere in Haryana with a maximum of 10 MW coming from a single developer. To reduce technology risk and complete project commissioning on schedule, only commercially viable and operational technologies can be chosen.

The net worth of bidders should not be less than Rs 10 million ($121,866)/MW of the quoted capacity for the most recent fiscal year. Either bidders must have internal resource generation capability in the form of profit before depreciation, interest, and taxes for at least Rs 1 million (or $12,187)/MW of the quoted capacity during the previous financial year, or bidders must have a minimum annual turnover of at least Rs 5 million (or $60,933)/MW of the quoted capacity.

Alternatively, bidders must obtain a letter of in-principle approval from a lender committing a Line of Credit for at least $1.25 million (about $15,233) per MW of the specified capacity toward the project's need for working capital.

The winning bidder will be solely responsible for obtaining grid connectivity and ongoing access from the distribution firms. There should be a minimum declared yearly capacity utilization factor of 21%.

The solar modules that will be utilized for the projects must have a warranty for their peak output wattage, which cannot be less than 90% after ten years and 80% after 25 years from the planned start of commercial operation.

The Ministry of New and Renewable Energy's Approved List of Models and Manufacturers should be used to source the solar modules for the project.

To develop and commission 121 MW of grid-connected solar power projects at Faridabad (78 MW), Panipat (25 MW), and Yamuna Nagar (18 MW), the Haryana Power Generation Corporation issued a bid invitation in June of last year.

See also:
MSEDCL releases tender for 615 MW Solar Power Projects
Maharashtra seeks Bids for a 62 MW Solar Project

In order to deliver 500 MW of solar electricity from grid-connected solar projects in Haryana, the Haryana electricity Purchase Center (HPPC), a joint forum of the Uttar Haryana Bijli Vitran Nigam (UHBVN) and Dakshin Haryana Bijli Vitran Nigam (DHBVN), has issued an invitation for bids.The deadline for submitting online bids is May 24, 2023. The following day, the bids will be opened. As a bid processing cost, bidders must deposit Rs 10 million ($121.87)/MW plus 18% GST. They must additionally provide an earnest money deposit of Rs 80 billions ($9,749/MW). After issuing the Letter of Intent and prior to signing the power purchase agreement (PPA), the successful bidder will be required to provide a bank guarantee in the amount of $2 million (or $24,373/MW). For the tender, HPPC has set a ceiling rate of 3.38 ($0.041)/kWh. With the winning bids, HPPC will sign PPAs that will last 25 years from the solar projects' start of commercial operation. After the PPA is signed, the solar developer has 18 months to complete the project. According to the terms of the PPA that will be signed between the solar power developer and HPPC, the developer will be in charge of the design, financing, acquisition of land, engineering, acquisition, construction, operation, and maintenance of the projects. The 500 MW total capacity of the projects that will be chosen under this contract may be put anywhere in Haryana with a maximum of 10 MW coming from a single developer. To reduce technology risk and complete project commissioning on schedule, only commercially viable and operational technologies can be chosen. The net worth of bidders should not be less than Rs 10 million ($121,866)/MW of the quoted capacity for the most recent fiscal year. Either bidders must have internal resource generation capability in the form of profit before depreciation, interest, and taxes for at least Rs 1 million (or $12,187)/MW of the quoted capacity during the previous financial year, or bidders must have a minimum annual turnover of at least Rs 5 million (or $60,933)/MW of the quoted capacity. Alternatively, bidders must obtain a letter of in-principle approval from a lender committing a Line of Credit for at least $1.25 million (about $15,233) per MW of the specified capacity toward the project's need for working capital. The winning bidder will be solely responsible for obtaining grid connectivity and ongoing access from the distribution firms. There should be a minimum declared yearly capacity utilization factor of 21%. The solar modules that will be utilized for the projects must have a warranty for their peak output wattage, which cannot be less than 90% after ten years and 80% after 25 years from the planned start of commercial operation. The Ministry of New and Renewable Energy's Approved List of Models and Manufacturers should be used to source the solar modules for the project. To develop and commission 121 MW of grid-connected solar power projects at Faridabad (78 MW), Panipat (25 MW), and Yamuna Nagar (18 MW), the Haryana Power Generation Corporation issued a bid invitation in June of last year. See also: MSEDCL releases tender for 615 MW Solar Power ProjectsMaharashtra seeks Bids for a 62 MW Solar Project

Next Story
Infrastructure Transport

JNPA Becomes First Indian Port to Cross 10 Million TEU Capacity

The Jawaharlal Nehru Port Authority (JNPA), located at Uran in Navi Mumbai, has become the first port in India to achieve over 10 million TEUs (twenty-foot equivalent units) in container handling capacity.With the recent expansion, the port now operates five container terminals with a combined capacity of 10.4 million TEUs, alongside two liquid and two general cargo terminals.Handling more than half of India’s container traffic, JNPA processed 7.05 million TEUs in 2024 and has moved 15.39 million tonnes of containers and 16.64 million tonnes of total cargo in the first two months of FY 2025â..

Next Story
Infrastructure Transport

Nod for Rs. 36.26 billion Expansion of Pune Metro Line 2

The Union Cabinet has approved the Rs.36.26 billion expansion of Pune Metro Line 2, adding 12.75 km of track and 13 new stations to improve east–west connectivity across the city.The project aims to link Pune’s urban core with rapidly growing suburbs, supporting the city’s rising demand for efficient and sustainable transport solutions. This expansion is part of Corridor 2 of the Pune Metro and includes two key routes: Vanaz to Chandani Chowk (Corridor 2A) and Ramwadi to Wagholi/Vitthalwadi (Corridor 2B).It will connect residential, IT, and educational hubs in areas such as Bavdhan, Koth..

Next Story
Infrastructure Transport

Assembly begins for ‘Nayak’ TBM on Thane– Borivali Twin Tunnel Project

The assembly of ‘Nayak’, the first of four Tunnel Boring Machines (TBMs) for the Thane–Borivali Twin Tube Tunnel Project, has commenced at the Thane site. Built by German firm Herrenknecht AG and deployed by Megha Engineering & Infrastructure (MEIL), the TBM marks a key milestone in Mumbai’s ambitious 11.8-km underground road corridor beneath Sanjay Gandhi National Park.The twin tunnels will reduce the Thane–Borivali travel distance by 12 km and decongest Thane Ghodbunder Road. ‘Nayak’, with a 13.2-metre diameter, is designed to bore through challenging geological conditions ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?