Haryana seeks bids to procure 500 MW of solar power
POWER & RENEWABLE ENERGY

Haryana seeks bids to procure 500 MW of solar power

In order to deliver 500 MW of solar electricity from grid-connected solar projects in Haryana, the Haryana electricity Purchase Center (HPPC), a joint forum of the Uttar Haryana Bijli Vitran Nigam (UHBVN) and Dakshin Haryana Bijli Vitran Nigam (DHBVN), has issued an invitation for bids.

The deadline for submitting online bids is May 24, 2023. The following day, the bids will be opened. As a bid processing cost, bidders must deposit Rs 10 million ($121.87)/MW plus 18% GST. They must additionally provide an earnest money deposit of Rs 80 billions ($9,749/MW).

After issuing the Letter of Intent and prior to signing the power purchase agreement (PPA), the successful bidder will be required to provide a bank guarantee in the amount of $2 million (or $24,373/MW).

For the tender, HPPC has set a ceiling rate of 3.38 ($0.041)/kWh.

With the winning bids, HPPC will sign PPAs that will last 25 years from the solar projects' start of commercial operation.

After the PPA is signed, the solar developer has 18 months to complete the project.

According to the terms of the PPA that will be signed between the solar power developer and HPPC, the developer will be in charge of the design, financing, acquisition of land, engineering, acquisition, construction, operation, and maintenance of the projects. The 500 MW total capacity of the projects that will be chosen under this contract may be put anywhere in Haryana with a maximum of 10 MW coming from a single developer. To reduce technology risk and complete project commissioning on schedule, only commercially viable and operational technologies can be chosen.

The net worth of bidders should not be less than Rs 10 million ($121,866)/MW of the quoted capacity for the most recent fiscal year. Either bidders must have internal resource generation capability in the form of profit before depreciation, interest, and taxes for at least Rs 1 million (or $12,187)/MW of the quoted capacity during the previous financial year, or bidders must have a minimum annual turnover of at least Rs 5 million (or $60,933)/MW of the quoted capacity.

Alternatively, bidders must obtain a letter of in-principle approval from a lender committing a Line of Credit for at least $1.25 million (about $15,233) per MW of the specified capacity toward the project's need for working capital.

The winning bidder will be solely responsible for obtaining grid connectivity and ongoing access from the distribution firms. There should be a minimum declared yearly capacity utilization factor of 21%.

The solar modules that will be utilized for the projects must have a warranty for their peak output wattage, which cannot be less than 90% after ten years and 80% after 25 years from the planned start of commercial operation.

The Ministry of New and Renewable Energy's Approved List of Models and Manufacturers should be used to source the solar modules for the project.

To develop and commission 121 MW of grid-connected solar power projects at Faridabad (78 MW), Panipat (25 MW), and Yamuna Nagar (18 MW), the Haryana Power Generation Corporation issued a bid invitation in June of last year.

See also:
MSEDCL releases tender for 615 MW Solar Power Projects
Maharashtra seeks Bids for a 62 MW Solar Project

In order to deliver 500 MW of solar electricity from grid-connected solar projects in Haryana, the Haryana electricity Purchase Center (HPPC), a joint forum of the Uttar Haryana Bijli Vitran Nigam (UHBVN) and Dakshin Haryana Bijli Vitran Nigam (DHBVN), has issued an invitation for bids.The deadline for submitting online bids is May 24, 2023. The following day, the bids will be opened. As a bid processing cost, bidders must deposit Rs 10 million ($121.87)/MW plus 18% GST. They must additionally provide an earnest money deposit of Rs 80 billions ($9,749/MW). After issuing the Letter of Intent and prior to signing the power purchase agreement (PPA), the successful bidder will be required to provide a bank guarantee in the amount of $2 million (or $24,373/MW). For the tender, HPPC has set a ceiling rate of 3.38 ($0.041)/kWh. With the winning bids, HPPC will sign PPAs that will last 25 years from the solar projects' start of commercial operation. After the PPA is signed, the solar developer has 18 months to complete the project. According to the terms of the PPA that will be signed between the solar power developer and HPPC, the developer will be in charge of the design, financing, acquisition of land, engineering, acquisition, construction, operation, and maintenance of the projects. The 500 MW total capacity of the projects that will be chosen under this contract may be put anywhere in Haryana with a maximum of 10 MW coming from a single developer. To reduce technology risk and complete project commissioning on schedule, only commercially viable and operational technologies can be chosen. The net worth of bidders should not be less than Rs 10 million ($121,866)/MW of the quoted capacity for the most recent fiscal year. Either bidders must have internal resource generation capability in the form of profit before depreciation, interest, and taxes for at least Rs 1 million (or $12,187)/MW of the quoted capacity during the previous financial year, or bidders must have a minimum annual turnover of at least Rs 5 million (or $60,933)/MW of the quoted capacity. Alternatively, bidders must obtain a letter of in-principle approval from a lender committing a Line of Credit for at least $1.25 million (about $15,233) per MW of the specified capacity toward the project's need for working capital. The winning bidder will be solely responsible for obtaining grid connectivity and ongoing access from the distribution firms. There should be a minimum declared yearly capacity utilization factor of 21%. The solar modules that will be utilized for the projects must have a warranty for their peak output wattage, which cannot be less than 90% after ten years and 80% after 25 years from the planned start of commercial operation. The Ministry of New and Renewable Energy's Approved List of Models and Manufacturers should be used to source the solar modules for the project. To develop and commission 121 MW of grid-connected solar power projects at Faridabad (78 MW), Panipat (25 MW), and Yamuna Nagar (18 MW), the Haryana Power Generation Corporation issued a bid invitation in June of last year. See also: MSEDCL releases tender for 615 MW Solar Power ProjectsMaharashtra seeks Bids for a 62 MW Solar Project

Next Story
Building Material

JSW Steel and POSCO to Invest ?650 Billion in Odisha Steel Plant

India's JSW Steel and South Korea's POSCO have announced plans to jointly invest ?650 billion (~$7.73 billion) in constructing a steel plant in Odisha. The plant, which will have an initial capacity of 5 million tons of steel annually, is part of their strategy to tap into India's rapidly growing steel market, fueled by its fast-paced economic expansion. The cooperation agreement was signed last week, although specific financial details were not disclosed. The initial investment for the project will be ?200 billion, with the plant expected to be operational by next year. Over the following thr..

Next Story
Infrastructure Urban

India's EV Charging Market Set to Reach $3.7 Billion by 2030

India’s electric vehicle (EV) charging market is projected to grow to $3.7 billion by 2030, driven by increasing EV adoption and the need for efficient charging solutions. The sector is expected to expand at a compound annual growth rate (CAGR) of 16%, supported by environmental concerns and fluctuating fuel prices. Globally, the EV charging infrastructure market is also experiencing significant growth, with revenues forecast to surge from $25.9 billion in 2023 to $164 billion by 2030, reflecting a CAGR of approximately 12%. "Fast-charging technologies and battery-swapping solutions are esse..

Next Story
Resources

IIA Kerala to host SRC 2024 on November 29-30

The Southern Regional Conference (SRC) 2024, hosted by The Indian Institute of Architects (IIA) Kerala Chapter and organised by IIA Kannur Centre, will take place on November 29-30, 2024 at Vythiri Village Resort in Wayanad. This prestigious conference will bring together visionary architects from across the country  and beyond to foster a rich dialogue and exchange of innovative ideas in the field of architecture.The Southern Regional Conference serves as a premier platform for professional development, knowledge sharing, and networking within the architectural community. This year’s t..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000