Government Issues Bidding Guidelines for Pumped Storage Projects
POWER & RENEWABLE ENERGY

Government Issues Bidding Guidelines for Pumped Storage Projects

The Ministry of Power has released tariff-based competitive bidding guidelines for procuring stored energy from existing, under-construction, or new Pumped Storage Projects (PSP). 
According to the National Electricity Plan 2023, India will require 74 GW/411 GWh of energy storage systems (ESS) by 2031-32, including 27 GW/175 GWh from PSPs and 47 GW/236 GWh from Battery Energy Storage Systems (BESS). 

Procurement models 

Mode 1: PSPs developed on sites identified by the procurer 

• The procurer selects the site, and the project is developed on a Build-Own-Operate-Transfer (BOOT) basis for 25 to 40 years. 
• A Special Purpose Vehicle (SPV) will handle pre-feasibility activities, including environmental and statutory clearances. 
• The SPV, initially owned by the procurer, will be transferred to the successful bidder at a pre-specified cost. 

Mode 2: PSPs identified by the bidder or already commissioned 

• PSPs may be developed on self-identified sites or existing facilities on a Build-Own-Operate (BOO) basis for 15 to 40 years. 
• Developers must secure environmental, forest, and land clearances before construction. 
• The procurer is not responsible for clearance-related delays. 

Key bidding criteria Minimum bid capacity 

• ISTS-connected projects: 50 MW 
• InSTS-connected projects: 10 MW (lower capacities may be permitted in the Northeast and Special Category States). 

Eligibility requirements 
• Developers must have infrastructure project experience from the last five years. 
• Minimum capital expenditure thresholds will be defined in the bidding documents. 
• Net worth or assets under management must be at least 20% of the estimated capital cost of the project. 

Financial obligations 
• Earnest Money Deposit (EMD): 2% of the estimated project cost. 
• Performance Bank Guarantee (PBG): 5% of the estimated project cost. 

Contractual and regulatory framework 
• The Power Purchase Agreement (PPA) must be signed within six months of the Letter of Award (LoA), or the awarded capacity may be cancelled. 
• The tariff adoption process must be completed within 60 days of application to the relevant Commission. 

Additional provisions 
• Transmission connectivity: Developers must secure access to the ISTS network at their own cost. 
• Force majeure: Developers must notify the procurer within 15 days of any such event. 
• Financial closure: Must be completed within 12 months, with penalties for delays. 
• Minimum commissioning capacity: 50% of the project capacity or 50 MW, whichever is lower. 

The government has also modified its budgetary support for hydroelectric and PSP projects, allocating Rs 124.6 billion for development. These guidelines aim to accelerate energy storage expansion and support India’s growing renewable energy sector. 
(Mercom) 

The Ministry of Power has released tariff-based competitive bidding guidelines for procuring stored energy from existing, under-construction, or new Pumped Storage Projects (PSP). According to the National Electricity Plan 2023, India will require 74 GW/411 GWh of energy storage systems (ESS) by 2031-32, including 27 GW/175 GWh from PSPs and 47 GW/236 GWh from Battery Energy Storage Systems (BESS). Procurement models Mode 1: PSPs developed on sites identified by the procurer • The procurer selects the site, and the project is developed on a Build-Own-Operate-Transfer (BOOT) basis for 25 to 40 years. • A Special Purpose Vehicle (SPV) will handle pre-feasibility activities, including environmental and statutory clearances. • The SPV, initially owned by the procurer, will be transferred to the successful bidder at a pre-specified cost. Mode 2: PSPs identified by the bidder or already commissioned • PSPs may be developed on self-identified sites or existing facilities on a Build-Own-Operate (BOO) basis for 15 to 40 years. • Developers must secure environmental, forest, and land clearances before construction. • The procurer is not responsible for clearance-related delays. Key bidding criteria Minimum bid capacity • ISTS-connected projects: 50 MW • InSTS-connected projects: 10 MW (lower capacities may be permitted in the Northeast and Special Category States). Eligibility requirements • Developers must have infrastructure project experience from the last five years. • Minimum capital expenditure thresholds will be defined in the bidding documents. • Net worth or assets under management must be at least 20% of the estimated capital cost of the project. Financial obligations • Earnest Money Deposit (EMD): 2% of the estimated project cost. • Performance Bank Guarantee (PBG): 5% of the estimated project cost. Contractual and regulatory framework • The Power Purchase Agreement (PPA) must be signed within six months of the Letter of Award (LoA), or the awarded capacity may be cancelled. • The tariff adoption process must be completed within 60 days of application to the relevant Commission. Additional provisions • Transmission connectivity: Developers must secure access to the ISTS network at their own cost. • Force majeure: Developers must notify the procurer within 15 days of any such event. • Financial closure: Must be completed within 12 months, with penalties for delays. • Minimum commissioning capacity: 50% of the project capacity or 50 MW, whichever is lower. The government has also modified its budgetary support for hydroelectric and PSP projects, allocating Rs 124.6 billion for development. These guidelines aim to accelerate energy storage expansion and support India’s growing renewable energy sector. (Mercom) 

Next Story
Infrastructure Energy

Samridh, CEID Launch High-Capacity Biogas Plant in Moradabad

Samridh Bioenergy has broken ground on a 12 TPD compressed biogas (CBG) plant in Moradabad, Uttar Pradesh, under the MNRE’s National Bioenergy Programme. Spread across 12 acres, the plant will process 270 tonne of organic waste daily and generate 30,000 cubic metre of biogas per day.CEID Consultants and Engineering Pvt Ltd has been appointed as the EPC contractor, responsible for the complete design, procurement, and construction of the plant. Equipped with four multi-feed digesters, the facility will accept a mix of press mud, cow dung, chicken litter, and vegetable waste, supporting contin..

Next Story
Real Estate

Delhi Micro-Markets Drive Up Housing Prices: Grihum Study

A new study by Grihum Housing Finance reveals that the rise of micro-markets across Delhi-NCR is fuelling real estate price appreciation, especially in the affordable housing segment. Key drivers include renewed post-pandemic interest, migration trends, and government schemes like PMAY.According to the study, over the past two decades, floor rates have risen 267 per cent, from Rs 1,500 per sq ft in 2005 to Rs 5,500 in 2024. In the same period, land rates surged 492 per cent, from Rs 1,300 to Rs 7,700 per sq ft. The sharp increase highlights strong capital appreciation in Delhi’s emerging loc..

Next Story
Resources

Covestro Develops PCR Polycarbonates from End-of-Life Headlamps

Materials manufacturer Covestro has launched post-consumer recycled (PCR) polycarbonates made from end-of-life automotive headlamps, in a move aimed at strengthening circularity in the auto industry. These TÜV Rheinland-certified grades, containing 50 per cent recycled content, are now commercially available for new automotive applications.Developed under a joint programme led by GIZ, with Volkswagen and NIO as key partners, the recycled material is currently being validated for use in future vehicle models.""This new line of polycarbonate represents a significant step in supporting the autom..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?