Delays in Solar Power Projects Due to Land Acquisition Issues
POWER & RENEWABLE ENERGY

Delays in Solar Power Projects Due to Land Acquisition Issues

India’s ambitious renewable energy targets are facing significant delays in solar power project commissioning, largely due to land acquisition challenges and slow transmission capacity expansion. According to Ember’s latest report on renewable energy (RE) risks in India, utility-scale solar projects are experiencing an average delay of 17 months from their scheduled completion date, with extreme cases seeing delays of up to 34 months, and some projects even being abandoned.

The report highlights that these delays are measured from the Scheduled Commercial Operation Date (SCOD) specified in tender documents, which typically falls 18 to 24 months after the execution of power purchase agreements (PPAs).

Assessing Risk Premiums in Solar Investments The report evaluates risk premiums for solar power projects using two benchmarks:

P50 (Average Scenario): A balanced estimate, where there is a 50% probability that actual results will meet or exceed this level. P90 (Conservative Scenario): A more cautious estimate, used by risk-averse investors, where there is a 90% probability that actual results will meet or exceed this level. Investors use P50 and P90 estimates to assess risk tolerance. For example, if historical data shows a capacity utilisation factor (CUF) for a solar project between 18% and 22%, a risk-averse investor might assume 18%, while a less cautious investor might estimate 20%.

Key Factors Contributing to Project Delays 1. Land Acquisition Bottlenecks Land acquisition, expected to take 6-9 months, often extends to 18-24 months in some states, significantly affecting project timelines. Issues such as administrative hurdles, non-digitised land records, fragmented local regulations, and lack of centralised land policies make project development more complex and delay financial closure. 2. Grid Connectivity & Transmission Expansion Challenges General Network Access (GNA) or interstate transmission system (ISTS) connectivity takes between 4.5 and 13.5 months, depending on the need for network expansion. Transmission line construction can take 24-36 months, but delays are common due to: Right-of-way disputes Geographical barriers (rivers, hills, ecological zones) Environmental concerns, particularly the Great Indian Bustard (GIB) protection zones in Rajasthan, where construction timelines can extend up to 48 months. The Role of High-Voltage Direct Current (HVDC) Transmission To support renewable energy integration, significant HVDC transmission capacity has been planned and auctioned. However, HVDC systems take longer to commission than traditional High-Voltage Alternating Current (HVAC) networks, as they require specialised equipment such as converter stations and thyristor valves.

Future Outlook: Grid Expansion & Renewable Integration India has granted grid connectivity for solar, wind, and hybrid projects totaling 147 GW, but this capacity will only become fully operational over the next 3-5 years. Addressing land acquisition hurdles and transmission infrastructure constraints will be crucial in achieving India’s renewable energy targets and maintaining investor confidence in the sector.

India’s ambitious renewable energy targets are facing significant delays in solar power project commissioning, largely due to land acquisition challenges and slow transmission capacity expansion. According to Ember’s latest report on renewable energy (RE) risks in India, utility-scale solar projects are experiencing an average delay of 17 months from their scheduled completion date, with extreme cases seeing delays of up to 34 months, and some projects even being abandoned. The report highlights that these delays are measured from the Scheduled Commercial Operation Date (SCOD) specified in tender documents, which typically falls 18 to 24 months after the execution of power purchase agreements (PPAs). Assessing Risk Premiums in Solar Investments The report evaluates risk premiums for solar power projects using two benchmarks: P50 (Average Scenario): A balanced estimate, where there is a 50% probability that actual results will meet or exceed this level. P90 (Conservative Scenario): A more cautious estimate, used by risk-averse investors, where there is a 90% probability that actual results will meet or exceed this level. Investors use P50 and P90 estimates to assess risk tolerance. For example, if historical data shows a capacity utilisation factor (CUF) for a solar project between 18% and 22%, a risk-averse investor might assume 18%, while a less cautious investor might estimate 20%. Key Factors Contributing to Project Delays 1. Land Acquisition Bottlenecks Land acquisition, expected to take 6-9 months, often extends to 18-24 months in some states, significantly affecting project timelines. Issues such as administrative hurdles, non-digitised land records, fragmented local regulations, and lack of centralised land policies make project development more complex and delay financial closure. 2. Grid Connectivity & Transmission Expansion Challenges General Network Access (GNA) or interstate transmission system (ISTS) connectivity takes between 4.5 and 13.5 months, depending on the need for network expansion. Transmission line construction can take 24-36 months, but delays are common due to: Right-of-way disputes Geographical barriers (rivers, hills, ecological zones) Environmental concerns, particularly the Great Indian Bustard (GIB) protection zones in Rajasthan, where construction timelines can extend up to 48 months. The Role of High-Voltage Direct Current (HVDC) Transmission To support renewable energy integration, significant HVDC transmission capacity has been planned and auctioned. However, HVDC systems take longer to commission than traditional High-Voltage Alternating Current (HVAC) networks, as they require specialised equipment such as converter stations and thyristor valves. Future Outlook: Grid Expansion & Renewable Integration India has granted grid connectivity for solar, wind, and hybrid projects totaling 147 GW, but this capacity will only become fully operational over the next 3-5 years. Addressing land acquisition hurdles and transmission infrastructure constraints will be crucial in achieving India’s renewable energy targets and maintaining investor confidence in the sector.

Next Story
Infrastructure Urban

Andhra Pradesh to Develop 30,000 Women-Led Enterprises by 2025

The Municipal Administration and Urban Development (MAUD) Department is accelerating efforts to create sustainable livelihoods for women in urban areas, in line with Chief Minister Nara Chandrababu Naidu’s goal of fostering one lakh women entrepreneurs by 2025. Under this initiative, the MAUD Department has set a target to establish 30,000 women-led enterprises across towns and cities in Andhra Pradesh. To support this vision, the department plans to establish Micro, Small & Medium Enterprises (MSMEs) for women in TIDCO housing complexes. Vacant plots across 163 colonies have been earmarked ..

Next Story
Infrastructure Energy

G Kishan Reddy discusses mining expansion, clearances with Chhattisgarh CM

Coal and Mines Minister G Kishan Reddy met Chhattisgarh CM Vishnu Deo Sai on Friday to expedite land acquisition and environmental clearances for mining projects. Reddy, who was on a two-day visit to review operations at South Eastern Coalfields Ltd (SECL), discussed measures to boost mining-led economic growth in the state. Key topics included speeding up land acquisition for mine expansions, obtaining quicker environmental approvals, and setting up integrated rehabilitation and resettlement sites. The minister also highlighted the importance of developing critical minerals in the region, alo..

Next Story
Infrastructure Urban

NITI Aayog's Vision for India's Auto Industry

NITI Aayog has launched the report titled "Automotive Industry: Powering India’s Participation in Global Value Chains," offering a roadmap for the country’s automotive future. Released by Shri Suman Bery, Vice Chairman, the report outlines key strategies to grow India’s automotive sector to $145 bn in component production by 2030. India is currently the fourth-largest automobile producer globally, but with only a modest three per cent share in the global automotive component market. The report emphasises the need to strengthen India’s position through competitive manufacturing, skill d..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?