BGRESL to commence work on Ennore thermal power station project
POWER & RENEWABLE ENERGY

BGRESL to commence work on Ennore thermal power station project

After five years, the physical work on the 660 MW Ennore thermal power station expansion project is likely to commence with the handing over of the site to the contractor BGR Energy Systems (BGRESL).

The ETPS expansion project site was handed over to the BGRESL in June and they have started work on the testing of the structures with a team of IIT Madras experts. After the completion of the tests, the contractor will commence the work.

ETPS expansion project work has been facing delay after delay. Tangedco awarded the EPC contract to Lanco Infra Tech (LITL) in May 2014. However, the LITL faced financial troubles and work came to a halt in August 2017. Tangedco terminated the contract in April 2018 ever since the project came to a standstill.

After five years, the physical work on the 660 MW Ennore thermal power station expansion project is likely to commence with the handing over of the site to the contractor BGR Energy Systems (BGRESL). The ETPS expansion project site was handed over to the BGRESL in June and they have started work on the testing of the structures with a team of IIT Madras experts. After the completion of the tests, the contractor will commence the work. ETPS expansion project work has been facing delay after delay. Tangedco awarded the EPC contract to Lanco Infra Tech (LITL) in May 2014. However, the LITL faced financial troubles and work came to a halt in August 2017. Tangedco terminated the contract in April 2018 ever since the project came to a standstill.

Next Story
Infrastructure Energy

REC Transfers HVDC Project to Power Grid

REC Limited has successfully handed over the Special Purpose Vehicle (SPV) for a High-Voltage Direct Current (HVDC) transmission project to Power Grid Corporation of India Limited (PGCIL). This strategic move aligns with the nation's objectives to strengthen its power transmission network. Key Highlights: Project Overview: The HVDC project, under the inter-state transmission system (ISTS) initiative, is a critical component of India's push toward robust and efficient electricity transmission. It aims to handle bulk power transfer across long distances while ensuring minimal losses. Role of RE..

Next Story
Infrastructure Transport

NF Railway Collaborates with IIT Guwahati

The Northeast Frontier (NF) Railway has signed strategic Memorandums of Understanding (MoUs) with IIT Guwahati to foster technological advancements and improve railway operations in the region. This partnership focuses on innovative solutions to enhance safety, efficiency, and sustainability in rail infrastructure. Key Highlights: Purpose of MoUs: The collaboration aims to leverage IIT Guwahati's expertise in technology and research for implementing cutting-edge solutions across railway operations. Key areas of focus include: Automation and digitization in maintenance. Sustainability initiati..

Next Story
Infrastructure Transport

Danapur Division Modernization Plans Revealed

The Railway Board has unveiled ambitious plans for the expansion and modernization of the Danapur Division, a critical hub under the East Central Railway. The initiative focuses on infrastructure development, enhanced passenger amenities, and operational efficiency. Key Highlights: Scope of Modernization: The Railway Board's blueprint emphasizes: Upgrading existing infrastructure to accommodate more passenger and freight traffic. Improving station facilities, such as platforms, waiting areas, and connectivity. Introducing advanced signal systems for safer and smoother operations. Freig..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000