Bangladesh govt procures electricity from Banskhali Coal Power Plants
POWER & RENEWABLE ENERGY

Bangladesh govt procures electricity from Banskhali Coal Power Plants

The Bangladesh government is preparing to purchase 500 MW of electricity from the under-construction Banskhali Coal Power Plant starting from June 13. The plant is owned by the Bangladeshi conglomerate S Alam Group, SEPCO III Electric Power Construction Corporation, and HTG Development Group from China. This project is part of China's Belt and Road Initiative (BRI).

To address the ongoing power crisis, the government will also purchase approximately 400 MW of electricity from the second unit of the Adani Power Plant, which is currently in the testing phase, before the end of this month.

Furthermore, the Power Cell Director General, Mohammad Hossain, stated that an additional 5 per cent or 400 MW of electricity will be obtained from liquefied fuel-based power plants starting the following week. This increase aims to support industrial, commercial, and residential consumers across the country.

Regarding the Banskhali Coal Power Plant, a senior official from the Bangladesh Power Development Board (BPDB) mentioned that although the commercial operation date (COD) for the plant has not been finalised, the government urgently requires power and is expected to receive around 500 MW of electricity soon. The official also mentioned that the payment for the electricity will be based on a "no electricity, no payment" policy. Currently, 200 MW of electricity is being received from this plant.

The Power Purchasing Agreement (PPA) initially projected the COD for the Banskhali plant to be on November 16, 2019, but due to construction delays, the sponsors incurred a penalty of Tk 2.00 billion (US$24 million) on July 12, 2020. They were subsequently granted a two-year extension, allowing them to complete the project by December 2022.

In addition to the Banskhali plant, the second unit of the Adani Power Plant is expected to supply around 400 MW to 500 MW of electricity from the last week of June 2023. If all goes as planned, this additional capacity, along with other power generation projects, will contribute approximately 1,500 MW to the national grid, alleviating the current power shortage.

Officials from the Bangladesh Power Development Board (BPDB) have projected the country's highest power demand to reach 14,500 MW, while the highest power generation capacity is expected to be 12,677 MW, resulting in a shortage of approximately 1,741 MW.

Despite the recent reduction in temperature due to rain, excessive load shedding persists across the country, with power supply remaining low. Rural areas experience more frequent power cuts compared to urban areas, especially in the capital city of Dhaka and other major cities. Some rural areas report power outages lasting over 12 hours per day.

The Godda Power Plant in India, established by the Adani Group, was designed to exclusively supply electricity to Bangladesh with its 1,600 MW capacity coal-fired power plant. The first 800 MW unit began commercial operation in March, while the second unit is currently undergoing testing and generates between 50 MW and 100 MW daily.

Currently, only 49 out of 153 power plants are operating at full capacity, with 53 of the remaining 104 plants shut down for maintenance, rehabilitation, or due to fuel shortages (gas or coal) caused by a dollar crisis. These 53 plants have a combined capacity of 4,930 MW. Among the remaining 51 plants, which have the capacity to produce 7,855 MW, only 3,568 MW is being generated due to fuel shortages.

The Bangladesh government is preparing to purchase 500 MW of electricity from the under-construction Banskhali Coal Power Plant starting from June 13. The plant is owned by the Bangladeshi conglomerate S Alam Group, SEPCO III Electric Power Construction Corporation, and HTG Development Group from China. This project is part of China's Belt and Road Initiative (BRI).To address the ongoing power crisis, the government will also purchase approximately 400 MW of electricity from the second unit of the Adani Power Plant, which is currently in the testing phase, before the end of this month.Furthermore, the Power Cell Director General, Mohammad Hossain, stated that an additional 5 per cent or 400 MW of electricity will be obtained from liquefied fuel-based power plants starting the following week. This increase aims to support industrial, commercial, and residential consumers across the country.Regarding the Banskhali Coal Power Plant, a senior official from the Bangladesh Power Development Board (BPDB) mentioned that although the commercial operation date (COD) for the plant has not been finalised, the government urgently requires power and is expected to receive around 500 MW of electricity soon. The official also mentioned that the payment for the electricity will be based on a no electricity, no payment policy. Currently, 200 MW of electricity is being received from this plant.The Power Purchasing Agreement (PPA) initially projected the COD for the Banskhali plant to be on November 16, 2019, but due to construction delays, the sponsors incurred a penalty of Tk 2.00 billion (US$24 million) on July 12, 2020. They were subsequently granted a two-year extension, allowing them to complete the project by December 2022.In addition to the Banskhali plant, the second unit of the Adani Power Plant is expected to supply around 400 MW to 500 MW of electricity from the last week of June 2023. If all goes as planned, this additional capacity, along with other power generation projects, will contribute approximately 1,500 MW to the national grid, alleviating the current power shortage.Officials from the Bangladesh Power Development Board (BPDB) have projected the country's highest power demand to reach 14,500 MW, while the highest power generation capacity is expected to be 12,677 MW, resulting in a shortage of approximately 1,741 MW.Despite the recent reduction in temperature due to rain, excessive load shedding persists across the country, with power supply remaining low. Rural areas experience more frequent power cuts compared to urban areas, especially in the capital city of Dhaka and other major cities. Some rural areas report power outages lasting over 12 hours per day.The Godda Power Plant in India, established by the Adani Group, was designed to exclusively supply electricity to Bangladesh with its 1,600 MW capacity coal-fired power plant. The first 800 MW unit began commercial operation in March, while the second unit is currently undergoing testing and generates between 50 MW and 100 MW daily.Currently, only 49 out of 153 power plants are operating at full capacity, with 53 of the remaining 104 plants shut down for maintenance, rehabilitation, or due to fuel shortages (gas or coal) caused by a dollar crisis. These 53 plants have a combined capacity of 4,930 MW. Among the remaining 51 plants, which have the capacity to produce 7,855 MW, only 3,568 MW is being generated due to fuel shortages.

Next Story
Infrastructure Energy

Apollo Green Energy targets Rs 100 billion in renewables

Apollo Green Energy Limited (AGEL), a subsidiary of Apollo International Group, is set to grow its renewable energy portfolio to Rs 100 billion by 2025, with plans for an initial public offering (IPO) to fuel this expansion. AGEL currently holds an order book of Rs 35 billion and manages Rs 25 billion in solar projects across several states. Operating in eight states, AGEL’s portfolio includes 400 MW of solar power installations and a Rs 7 billion Flue Gas Desulfurization (FGD) project aimed at reducing emissions in power generation. These projects support India’s ambitious target of reac..

Next Story
Infrastructure Transport

Kolkata Metro’s Orange Line Phase II deadline moved to March 2025

The completion date for the Orange Line's Phase II extension, stretching from Ruby to Sector V, has been shifted to March 2025. Rail Vikas Nigam Ltd. (RVNL), the agency overseeing the project, initially aimed for a December 2024 deadline but cited a delay in bridging an 800-meter viaduct gap at Chingrighata as the reason for the revised schedule. Work to bridge an additional 125-meter gap at Metropolitan is ongoing. Despite land challenges at locations such as Tagore Park, Chingrighata, and Nicco Park, the corridor received safety approval from the Commission of Railway Safety (CRS) for opera..

Next Story
Infrastructure Energy

Solar efficiency, cost cuts vital for energy transition: Pralhad Joshi

Union Minister for New and Renewable Energy, Pralhad Joshi, emphasised the global focus on advancing solar technology to achieve significant cost reductions and efficiency gains during a conference on clean energy transition. As President of the International Solar Alliance (ISA), he remarked, “The world is united in the energy transition, harnessing global efforts.” Joshi highlighted the need for more efficient solar technology, stating, “Traditional solar panels typically convert only 15-20% of sunlight to electricity, but innovations like bifacial panels and solar paint are increasin..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000