132 kV Ramban-Khellani power line upgraded to 220 MW capacity
POWER & RENEWABLE ENERGY

132 kV Ramban-Khellani power line upgraded to 220 MW capacity

In a significant step towards strengthening the power infrastructure in the twin Districts of Doda and Kishtwar, the Power Development Department (PDD) has achieved a historic milestone by inaugurating the first-ever double-circuit transmission line after a long period of 75 years.

The transformative project has established a critical link between the 220 kV Grid Station in Ramban and the 132 kV Grid Station at Khellani in Doda district, heralding a new era of connectivity and reliability for the regions.

The newly commissioned 132 kV double-circuit transmission line, which became operational on February 1, 2024, with a power transmission capacity of 150 MW (approximately 75 MW for each circuit), will ensure a threefold increase in the overall power transmission capacity for the hilly districts of Doda and Kishtwar.

This development comes as a timely solution to the challenges faced by the aging 132 kV single-circuit Udhampur-Dul Hasti Line (UDH Tx Line). Despite its commendable service over three decades, the line struggled to meet the escalating power demand, especially during harsh winters.

A senior PDD official mentioned, "The UDH Tx Line, with a rated transmission capacity of nearly 75 MW, had been catering to the power requirements of the twin districts since its inception. However, with the load demand surging to 200 MW and weather-induced wear and tear taking a toll, the line faced limitations, leading to curtailments and impacting the reliability of power supply."

He added that the radial configuration and the absence of an alternate transmission system exacerbated these challenges, leaving Doda and Kishtwar vulnerable to frequent blackouts.

According to him, the newly operational transmission line will not only address these issues but also ensure an alternative power source, complementing the existing UDH Tx Line.

"With a combined capacity of over 220 MW, the existing and the new double-circuit transmission lines will now create a resilient network ensuring uninterrupted power supply, even in the event of failures or breakdowns," said the official.

The construction of the 132 kV double-circuit Ramban to Khellani Transmission Line started some years back. Due to various technical delays, the project couldn?t progress, and the works remained held up.

Overcoming these bottlenecks, the Government awarded the project afresh to Power Grid Corporation of India (PGCIL), a key player in the country?s power sector.

The swift and efficient execution by PGCIL allowed the transmission line to be commissioned well ahead of schedule, providing much-needed relief to the public of Doda and Kishtwar.

The PDD official added that the feeding grid Khellani (20+50 MVA) is also being augmented to 100 MVA (50+50 MVA), the contract of which stands awarded while the other grid, Katersamna (2?20 MVA), is shortly being augmented to 70 MVA (20+50 MVA), thereby making Doda and Kishtwar Districts self-sufficient concerning power.

"These upgrades, coupled with the newly commissioned transmission line, are part of a broader strategy aimed at fortifying the power infrastructure in the region," he said.

Furthermore, the Government has also given approval for a Rs 10 bn investment in the upcoming Financial Year for the construction of three major 400 kV Grid Stations in Akhnoor, Rajouri, and Katra in the Jammu region and two 220 kV level Grid Stations at Wahipora and Sallar in the Kashmir Region.

In a significant step towards strengthening the power infrastructure in the twin Districts of Doda and Kishtwar, the Power Development Department (PDD) has achieved a historic milestone by inaugurating the first-ever double-circuit transmission line after a long period of 75 years. The transformative project has established a critical link between the 220 kV Grid Station in Ramban and the 132 kV Grid Station at Khellani in Doda district, heralding a new era of connectivity and reliability for the regions. The newly commissioned 132 kV double-circuit transmission line, which became operational on February 1, 2024, with a power transmission capacity of 150 MW (approximately 75 MW for each circuit), will ensure a threefold increase in the overall power transmission capacity for the hilly districts of Doda and Kishtwar. This development comes as a timely solution to the challenges faced by the aging 132 kV single-circuit Udhampur-Dul Hasti Line (UDH Tx Line). Despite its commendable service over three decades, the line struggled to meet the escalating power demand, especially during harsh winters. A senior PDD official mentioned, The UDH Tx Line, with a rated transmission capacity of nearly 75 MW, had been catering to the power requirements of the twin districts since its inception. However, with the load demand surging to 200 MW and weather-induced wear and tear taking a toll, the line faced limitations, leading to curtailments and impacting the reliability of power supply. He added that the radial configuration and the absence of an alternate transmission system exacerbated these challenges, leaving Doda and Kishtwar vulnerable to frequent blackouts. According to him, the newly operational transmission line will not only address these issues but also ensure an alternative power source, complementing the existing UDH Tx Line. With a combined capacity of over 220 MW, the existing and the new double-circuit transmission lines will now create a resilient network ensuring uninterrupted power supply, even in the event of failures or breakdowns, said the official. The construction of the 132 kV double-circuit Ramban to Khellani Transmission Line started some years back. Due to various technical delays, the project couldn?t progress, and the works remained held up. Overcoming these bottlenecks, the Government awarded the project afresh to Power Grid Corporation of India (PGCIL), a key player in the country?s power sector. The swift and efficient execution by PGCIL allowed the transmission line to be commissioned well ahead of schedule, providing much-needed relief to the public of Doda and Kishtwar. The PDD official added that the feeding grid Khellani (20+50 MVA) is also being augmented to 100 MVA (50+50 MVA), the contract of which stands awarded while the other grid, Katersamna (2?20 MVA), is shortly being augmented to 70 MVA (20+50 MVA), thereby making Doda and Kishtwar Districts self-sufficient concerning power. These upgrades, coupled with the newly commissioned transmission line, are part of a broader strategy aimed at fortifying the power infrastructure in the region, he said. Furthermore, the Government has also given approval for a Rs 10 bn investment in the upcoming Financial Year for the construction of three major 400 kV Grid Stations in Akhnoor, Rajouri, and Katra in the Jammu region and two 220 kV level Grid Stations at Wahipora and Sallar in the Kashmir Region.

Next Story
Infrastructure Urban

Development of ICT in Indian Judiciary through e-Courts Phases

The eCourts project, launched under the National eGovernance Plan in 2007, is a Mission Mode Project aimed at modernisng the Indian judiciary through the adoption of Information and Communication Technology (ICT). The initiative is grounded in the "National Policy and Action Plan for Implementation of ICT in the Indian Judiciary" and has been implemented in multiple phases. Phase I (2011–2015) focused on the computerization of judicial infrastructure and ensuring connectivity across courts. During this phase, 14,249 district and subordinate courts were computerised, and Local Area Networks ..

Next Story
Infrastructure Urban

Minority Affairs Minister to Launch PM VIKAS Project via DGSMC

On 29th March 2025, the Ministry of Minority Affairs will launch a new program under the Pradhan Mantri Virasat Ka Samvardhan (PM VIKAS) scheme, aimed at enhancing skill development and educational support for minority communities. The initiative, which will be implemented by the Delhi Sikh Gurdwara Management Committee (DSGMC), will benefit a total of 31,600 candidates across the country. Out of the total beneficiaries, 29,600 individuals will receive skill training in industry-relevant fields, while 2,000 candidates will receive educational support. The training will focus on job roles ali..

Next Story
Infrastructure Urban

DARPG and Bhashini Launch Multilingual Tool for Citizen Grievances

To enhance the effectiveness, accessibility, and responsiveness of the grievance redressal system, the Department of Administrative Reforms and Public Grievances (DARPG) has signed a Master Service Agreement with Digital India Bhashini on March 28, 2025. This agreement marks the implementation of a multimodal, multilingual e-Governance solution for the Centralised Public Grievance Redress and Monitoring System (CPGRAMS), in line with the directive of the Prime Minister of India to bring qualitative improvements to citizen service delivery. The new solution aims to empower citizens from diver..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?