132 kV Ramban-Khellani power line upgraded to 220 MW capacity
POWER & RENEWABLE ENERGY

132 kV Ramban-Khellani power line upgraded to 220 MW capacity

In a significant step towards strengthening the power infrastructure in the twin Districts of Doda and Kishtwar, the Power Development Department (PDD) has achieved a historic milestone by inaugurating the first-ever double-circuit transmission line after a long period of 75 years.

The transformative project has established a critical link between the 220 kV Grid Station in Ramban and the 132 kV Grid Station at Khellani in Doda district, heralding a new era of connectivity and reliability for the regions.

The newly commissioned 132 kV double-circuit transmission line, which became operational on February 1, 2024, with a power transmission capacity of 150 MW (approximately 75 MW for each circuit), will ensure a threefold increase in the overall power transmission capacity for the hilly districts of Doda and Kishtwar.

This development comes as a timely solution to the challenges faced by the aging 132 kV single-circuit Udhampur-Dul Hasti Line (UDH Tx Line). Despite its commendable service over three decades, the line struggled to meet the escalating power demand, especially during harsh winters.

A senior PDD official mentioned, "The UDH Tx Line, with a rated transmission capacity of nearly 75 MW, had been catering to the power requirements of the twin districts since its inception. However, with the load demand surging to 200 MW and weather-induced wear and tear taking a toll, the line faced limitations, leading to curtailments and impacting the reliability of power supply."

He added that the radial configuration and the absence of an alternate transmission system exacerbated these challenges, leaving Doda and Kishtwar vulnerable to frequent blackouts.

According to him, the newly operational transmission line will not only address these issues but also ensure an alternative power source, complementing the existing UDH Tx Line.

"With a combined capacity of over 220 MW, the existing and the new double-circuit transmission lines will now create a resilient network ensuring uninterrupted power supply, even in the event of failures or breakdowns," said the official.

The construction of the 132 kV double-circuit Ramban to Khellani Transmission Line started some years back. Due to various technical delays, the project couldn?t progress, and the works remained held up.

Overcoming these bottlenecks, the Government awarded the project afresh to Power Grid Corporation of India (PGCIL), a key player in the country?s power sector.

The swift and efficient execution by PGCIL allowed the transmission line to be commissioned well ahead of schedule, providing much-needed relief to the public of Doda and Kishtwar.

The PDD official added that the feeding grid Khellani (20+50 MVA) is also being augmented to 100 MVA (50+50 MVA), the contract of which stands awarded while the other grid, Katersamna (2?20 MVA), is shortly being augmented to 70 MVA (20+50 MVA), thereby making Doda and Kishtwar Districts self-sufficient concerning power.

"These upgrades, coupled with the newly commissioned transmission line, are part of a broader strategy aimed at fortifying the power infrastructure in the region," he said.

Furthermore, the Government has also given approval for a Rs 10 bn investment in the upcoming Financial Year for the construction of three major 400 kV Grid Stations in Akhnoor, Rajouri, and Katra in the Jammu region and two 220 kV level Grid Stations at Wahipora and Sallar in the Kashmir Region.

In a significant step towards strengthening the power infrastructure in the twin Districts of Doda and Kishtwar, the Power Development Department (PDD) has achieved a historic milestone by inaugurating the first-ever double-circuit transmission line after a long period of 75 years. The transformative project has established a critical link between the 220 kV Grid Station in Ramban and the 132 kV Grid Station at Khellani in Doda district, heralding a new era of connectivity and reliability for the regions. The newly commissioned 132 kV double-circuit transmission line, which became operational on February 1, 2024, with a power transmission capacity of 150 MW (approximately 75 MW for each circuit), will ensure a threefold increase in the overall power transmission capacity for the hilly districts of Doda and Kishtwar. This development comes as a timely solution to the challenges faced by the aging 132 kV single-circuit Udhampur-Dul Hasti Line (UDH Tx Line). Despite its commendable service over three decades, the line struggled to meet the escalating power demand, especially during harsh winters. A senior PDD official mentioned, The UDH Tx Line, with a rated transmission capacity of nearly 75 MW, had been catering to the power requirements of the twin districts since its inception. However, with the load demand surging to 200 MW and weather-induced wear and tear taking a toll, the line faced limitations, leading to curtailments and impacting the reliability of power supply. He added that the radial configuration and the absence of an alternate transmission system exacerbated these challenges, leaving Doda and Kishtwar vulnerable to frequent blackouts. According to him, the newly operational transmission line will not only address these issues but also ensure an alternative power source, complementing the existing UDH Tx Line. With a combined capacity of over 220 MW, the existing and the new double-circuit transmission lines will now create a resilient network ensuring uninterrupted power supply, even in the event of failures or breakdowns, said the official. The construction of the 132 kV double-circuit Ramban to Khellani Transmission Line started some years back. Due to various technical delays, the project couldn?t progress, and the works remained held up. Overcoming these bottlenecks, the Government awarded the project afresh to Power Grid Corporation of India (PGCIL), a key player in the country?s power sector. The swift and efficient execution by PGCIL allowed the transmission line to be commissioned well ahead of schedule, providing much-needed relief to the public of Doda and Kishtwar. The PDD official added that the feeding grid Khellani (20+50 MVA) is also being augmented to 100 MVA (50+50 MVA), the contract of which stands awarded while the other grid, Katersamna (2?20 MVA), is shortly being augmented to 70 MVA (20+50 MVA), thereby making Doda and Kishtwar Districts self-sufficient concerning power. These upgrades, coupled with the newly commissioned transmission line, are part of a broader strategy aimed at fortifying the power infrastructure in the region, he said. Furthermore, the Government has also given approval for a Rs 10 bn investment in the upcoming Financial Year for the construction of three major 400 kV Grid Stations in Akhnoor, Rajouri, and Katra in the Jammu region and two 220 kV level Grid Stations at Wahipora and Sallar in the Kashmir Region.

Next Story
Infrastructure Urban

Karnataka Seeks Rs.5,000 Crore World Bank Aid for Disaster Resilience

To strengthen Bengaluru's status as a global IT-BT hub while addressing its vulnerability to natural disasters, the Karnataka government has sought Rs.50 billion in financial assistance from the World Bank under a proposal called the Disaster Resilience Initiative. Of this, Rs.35 billion is earmarked for Bengaluru, with the remaining Rs.15 bilion allocated for disaster-prone cities like Belagavi and Mangaluru. According to government officials, Rs.25 billion will go to the Bruhat Bengaluru Mahanagara Palike (BBMP) for modernising the city’s stormwater drains, which have been neglected for t..

Next Story
Building Material

JSW Group and POSCO to Establish Greenfield Steel Plant in Keonjhar

Odisha Chief Minister Mohan Charan Majhi announced that JSW Group, in collaboration with South Korean steel giant POSCO, will set up a greenfield steel facility in his home district of Keonjhar. This development follows speculation regarding the location of the joint venture. During his two-day visit to Keonjhar to celebrate Diwali, Majhi disclosed that discussions about the steel plant took place during roadshows for the upcoming Make-in-Odisha conclave held in Delhi and Mumbai. He confirmed that the two companies have signed a Memorandum of Understanding (MoU) to establish the plant, which w..

Next Story
Infrastructure Energy

Coal India Eyes Dividend Return

Coal India Ltd. (CIL) is optimistic about rejoining the list of dividend-paying companies, primarily due to a notable improvement in the performance of its subsidiary, Eastern Coalfields Ltd. (ECL). ECL’s operational efficiency and financial performance have seen considerable progress, contributing positively to CIL’s overall profitability. After missing its dividend payout last year—a rarity given its history as a reliable dividend stock—CIL is working to restore shareholder confidence through enhanced production targets and cost-cutting measures. ECL's focused strategy on boosting pr..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000