NTPC invites bids for BoS Package for solar projects of 1,000 MW
POWER & RENEWABLE ENERGY

NTPC invites bids for BoS Package for solar projects of 1,000 MW

NTPC Renewable Energy Limited (NTPC REL) has issued a Request For Proposals (RFP) for a Balance of System (BoS) package with land for up to 1,000 MW of ISTS-connected solar projects to be built anywhere in India.

Bids must be received by February 3, 2022, to be considered. The next day, bids will be accepted. On the 24th of January, there will be a pre-bid meeting.

Bidders quoting for capacity between 50 MW and 110 MW should submit a bid security deposit of Rs 20 million. The bid security amount is Rs 5 million for capacity above 110 MW up to 220 MW, and Rs 100 million for capacity between 220 MW and 440 MW. The bid security deposit for capacity between 440 MW and 600 MW is Rs 200 million.

Identification, acquisition, and transfer of land ownership or lease in favour of NTPC Renewable Energy are all part of the project's scope. Engineering, design, manufacturing, supply, packaging, forwarding, transporting, unloading, storage, installation, testing, and commissioning of solar projects will also be the responsibility of the successful bidders, excluding solar module supply.

The successful bidders must provide comprehensive operation and maintenance services for three years after commissioning these projects, including switchyard and power evacuation systems until the interconnecting grid substation.

At least 40 MW of grid-connected solar projects should have been designed and commissioned by bidders. One project must have a capacity of 10 MW or more and have been operational for at least six months before the techno-commercial bid opening date.

Alternatively, bidders must have completed grid-connected solar projects with a total capacity of at least 40 MW. One solar project should have a capacity of at least 10 MW. The project must have been up and running for at least six months before the opening of the techno-commercial bid.

Bidders must have completed an industrial project in the power, steel, oil, gas, petrochemical, fertiliser, cement, or coal mining sectors in the previous ten years, either as developers or as Engineering, Procurement, and Construction (EPC) contractors. Before the date of the techno-commercial bid opening, the project should have been in operation for at least one year.

Bidders must have completed at least one electrical substation with a voltage level of 33 kV or higher, including equipment such as power transformers and circuit breakers.

In the previous three financial years, the bidders' minimum average annual turnover for quoted capacity between 50 MW and 300 MW should have been Rs 1.1 billion. If the capacity is between 300 MW and 600 MW, their average annual turnover must not be less than Rs 2.2 billion in the previous three financial years. In the previous financial year, their net worth had to be equal to or greater than their paid-up share capital.

NTPC Renewable Energy issued a request for proposals last month for a BoS package for 325 MW of projects in Madhya Pradesh's Shajapur Solar Park.

The 735 MW Nokh solar power project in Rajasthan was reissued in November by NTPC Limited as a balance of system package tender.

Image Source

Also read: UPNEDA floats tenders to empanel installers for 38 MW rooftop solar

NTPC Renewable Energy Limited (NTPC REL) has issued a Request For Proposals (RFP) for a Balance of System (BoS) package with land for up to 1,000 MW of ISTS-connected solar projects to be built anywhere in India. Bids must be received by February 3, 2022, to be considered. The next day, bids will be accepted. On the 24th of January, there will be a pre-bid meeting. Bidders quoting for capacity between 50 MW and 110 MW should submit a bid security deposit of Rs 20 million. The bid security amount is Rs 5 million for capacity above 110 MW up to 220 MW, and Rs 100 million for capacity between 220 MW and 440 MW. The bid security deposit for capacity between 440 MW and 600 MW is Rs 200 million. Identification, acquisition, and transfer of land ownership or lease in favour of NTPC Renewable Energy are all part of the project's scope. Engineering, design, manufacturing, supply, packaging, forwarding, transporting, unloading, storage, installation, testing, and commissioning of solar projects will also be the responsibility of the successful bidders, excluding solar module supply. The successful bidders must provide comprehensive operation and maintenance services for three years after commissioning these projects, including switchyard and power evacuation systems until the interconnecting grid substation. At least 40 MW of grid-connected solar projects should have been designed and commissioned by bidders. One project must have a capacity of 10 MW or more and have been operational for at least six months before the techno-commercial bid opening date. Alternatively, bidders must have completed grid-connected solar projects with a total capacity of at least 40 MW. One solar project should have a capacity of at least 10 MW. The project must have been up and running for at least six months before the opening of the techno-commercial bid. Bidders must have completed an industrial project in the power, steel, oil, gas, petrochemical, fertiliser, cement, or coal mining sectors in the previous ten years, either as developers or as Engineering, Procurement, and Construction (EPC) contractors. Before the date of the techno-commercial bid opening, the project should have been in operation for at least one year. Bidders must have completed at least one electrical substation with a voltage level of 33 kV or higher, including equipment such as power transformers and circuit breakers. In the previous three financial years, the bidders' minimum average annual turnover for quoted capacity between 50 MW and 300 MW should have been Rs 1.1 billion. If the capacity is between 300 MW and 600 MW, their average annual turnover must not be less than Rs 2.2 billion in the previous three financial years. In the previous financial year, their net worth had to be equal to or greater than their paid-up share capital. NTPC Renewable Energy issued a request for proposals last month for a BoS package for 325 MW of projects in Madhya Pradesh's Shajapur Solar Park. The 735 MW Nokh solar power project in Rajasthan was reissued in November by NTPC Limited as a balance of system package tender. Image Source Also read: UPNEDA floats tenders to empanel installers for 38 MW rooftop solar

Next Story
Infrastructure Urban

CONCOR Launches Double-stack Service Between NCR and Varnama

State-run Container Corporation of India (CONCOR) has launched double-stack container train services between the National Capital Region (NCR) and Varnama near Baroda. This initiative aims to facilitate customers at Nhava Sheva near Mumbai, home to Jawaharlal Nehru Port (J N Port). On December 21, the first double-stack container train from Khatuwas and Dadri in NCR reached CONCOR’s Gati Shakti Multimodal Cargo Terminal (GCT) at Varnama, situated along the Western Dedicated Freight Corridor (WDFC). The train carried export cargo destined for J N Port, according to a statement from the state..

Next Story
Infrastructure Transport

Less than 10% of Rs 40 Billion State-aid for Shipbuilding Utilised

A government-sanctioned financial assistance program worth Rs 40 billion, intended to support local shipbuilders over a decade starting in April 2016, has seen minimal utilisation, with only Rs 3.85 billion—less than 10 per cent of the total fund—disbursed thus far. With 15 months remaining before the scheme concludes, its uptake has been limited. The financial aid applies to shipbuilding contracts signed between April 1, 2016, and March 31, 2026. According to a written response provided by Union Minister of Ports, Shipping, and Waterways Sarbananda Sonowal to the Rajya Sabha on December ..

Next Story
Infrastructure Transport

Civil Aviation Minister Opens New ATC Tower at Indore Airport

The Minister for Civil Aviation, Ram Mohan Naidu Kinjarapu, inaugurated the new Air Traffic Control (ATC) Tower-cum-technical block at Devi Ahilyabai Holkar International Airport in Indore, Madhya Pradesh. During the inauguration, the minister toured the facility, where ATC experts explained various technical aspects of tracking and coordinating flights from the newly constructed tower. In addition to the ATC tower, the airport has also introduced a zero-waste plant. The union minister confirmed that this initiative aligns with the government’s commitment to sustainability. Minister Ki..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000