Maharashtra discom opens tender for 500 MW wind-solar hybrid projects
POWER & RENEWABLE ENERGY

Maharashtra discom opens tender for 500 MW wind-solar hybrid projects

The Maharashtra State Electricity Distribution Company (MSEDCL) has opened a tender inviting bids for procuring 500 MW wind-solar hybrid power on a long-term basis from grid-connected interstate and intrastate projects.

MSEDCL will enter into a power purchase agreement (PPA) with the selected bidders for purchasing wind-solar hybrid power for 25 years from the commercial operational date of the projects.

The minimum size of a single hybrid power project for the intrastate projects should be 25 MW, with at least 10 MW project at one site. It should be 50 MW for interstate projects at one site to be interconnected to a single delivery point.

The voltage level for intrastate projects is required to be 33 kV or above of state transmission utility (STU)/Maharashtra State Electricity Transmission Company (MSETCL) substation.

Maharashtra STU/MSETCL limits will be the energy settlement and delivery point for interstate projects. The projects to be selected should provide for the deployment of wind-solar hybrid power technology. The bidding document also specifies that only commercially established and operational technologies should be used to minimise the technology risk and achieve timely commissioning of the projects.

The intrastate or interstate projects already commissioned, but lacking any long-term PPA with any agency will be considered if these projects are not already accepted under any other central or state programmes, and do not have any obligations towards existing buyers.

Eligibility:

The bidder’s net worth should not be less than Rs 1 crore per MW for the last financial year (FY) to qualify in the bidding process.

The minimum annual turnover of the bidder should be Rs 75 lakh per MW of the quoted capacity during the last FY as of the date at least seven days before the bid submission date. In the form of profit before depreciation, interest, and taxes, the internal resource generation capacity should be at least Rs 15 lakh per MW of the quoted capacity on the last date of the previous FY. The bidder should have a letter from the lending institution committing a ‘line of credit’ for a minimum amount of Rs 18.70 lakh per MW of the quoted capacity. This is needed to meet the working capital requirement of the project.

The last date to submit the bids is June 8, 2021.

The responsibility of getting the grid connectivity with the central transmission utility or the state transmission utility will be entirely with the successful bidder.

According to the tender, the developer should maintain generation to achieve an annual capacity utilisation factor (CUF) not less than 90% of the declared value and not more than 120% of the declared CUF value during the PPA duration of 25 years.

Earlier, MSEDCL had issued a tender for the procurement of hybrid renewable power to meet its renewable purchase obligation. It had set a ceiling tariff of Rs 2.80 per kWh for the projects. Another wind-solar hybrid tender from MSEDCL had a tariff cap of Rs 2.75 per kWh. MSEDCL has also invited bids to procure power from 500 MW of interstate or intrastate grid-connected solar projects on a long-term basis.

Click here to get the tender details.

Image Source


Also read: Maharashtra to spend Rs 25 bn on Mahavitaran power infra

Redefine the future of urban mobility! Join us at the Metro Rail Conference 2025 to explore groundbreaking ideas and insights. 👉 Register today!

The Maharashtra State Electricity Distribution Company (MSEDCL) has opened a tender inviting bids for procuring 500 MW wind-solar hybrid power on a long-term basis from grid-connected interstate and intrastate projects. MSEDCL will enter into a power purchase agreement (PPA) with the selected bidders for purchasing wind-solar hybrid power for 25 years from the commercial operational date of the projects. The minimum size of a single hybrid power project for the intrastate projects should be 25 MW, with at least 10 MW project at one site. It should be 50 MW for interstate projects at one site to be interconnected to a single delivery point. The voltage level for intrastate projects is required to be 33 kV or above of state transmission utility (STU)/Maharashtra State Electricity Transmission Company (MSETCL) substation. Maharashtra STU/MSETCL limits will be the energy settlement and delivery point for interstate projects. The projects to be selected should provide for the deployment of wind-solar hybrid power technology. The bidding document also specifies that only commercially established and operational technologies should be used to minimise the technology risk and achieve timely commissioning of the projects. The intrastate or interstate projects already commissioned, but lacking any long-term PPA with any agency will be considered if these projects are not already accepted under any other central or state programmes, and do not have any obligations towards existing buyers. Eligibility: The bidder’s net worth should not be less than Rs 1 crore per MW for the last financial year (FY) to qualify in the bidding process. The minimum annual turnover of the bidder should be Rs 75 lakh per MW of the quoted capacity during the last FY as of the date at least seven days before the bid submission date. In the form of profit before depreciation, interest, and taxes, the internal resource generation capacity should be at least Rs 15 lakh per MW of the quoted capacity on the last date of the previous FY. The bidder should have a letter from the lending institution committing a ‘line of credit’ for a minimum amount of Rs 18.70 lakh per MW of the quoted capacity. This is needed to meet the working capital requirement of the project. The last date to submit the bids is June 8, 2021. The responsibility of getting the grid connectivity with the central transmission utility or the state transmission utility will be entirely with the successful bidder. According to the tender, the developer should maintain generation to achieve an annual capacity utilisation factor (CUF) not less than 90% of the declared value and not more than 120% of the declared CUF value during the PPA duration of 25 years. Earlier, MSEDCL had issued a tender for the procurement of hybrid renewable power to meet its renewable purchase obligation. It had set a ceiling tariff of Rs 2.80 per kWh for the projects. Another wind-solar hybrid tender from MSEDCL had a tariff cap of Rs 2.75 per kWh. MSEDCL has also invited bids to procure power from 500 MW of interstate or intrastate grid-connected solar projects on a long-term basis. Click here to get the tender details. Image SourceAlso read: Maharashtra to spend Rs 25 bn on Mahavitaran power infra

Next Story
Infrastructure Transport

Banihal Bypass Started, Milestone Achieved By NHAI On NH44

The National Highways Authority of India (NHAI) has achieved another milestone on the Jammu-Srinagar four-lane highway after nearly four years of construction. The NHAI has completed the Banihal Bypass, and one side of the bypass was opened for traffic following a post by Union Minister for Road Transport and highways Nitin Gadkari on his official X handle. Traffic has been allowed from Jammu to Srinagar on one tube of the much awaited Banihal bypass.Project head of Banihal bypass from NHAI Kumar Jainendra told Greater Kashmir that the full public cooperation and support from locals was u..

Next Story
Infrastructure Transport

Hyderabad: Rs 70 Bn Sanctioned For Road Infra Works

As part of the Hyderabad City Innovative and Transformative Infrastructure (H-CITI) program the state government sanctioned Rs 70 billion for 38 works, including the construction of flyovers, underpasses, and road-over-bridges (ROB) to ease the traffic in various parts of Hyderabad and its nearby municipalities. As part of the Strategic Road Development Programme (SRDP) initiated by the previous BRS government, several flyovers and road infrastructure projects were taken up mostly under the limits of the Greater Hyderabad Municipal Corporation (GHMC). Out of the 42 works under SRDP, 36 projec..

Next Story
Infrastructure Transport

India's Second Cable-Stayed Bridge to Be Built In Howrah

Eastern Railways is set to construct India’s second cable-stayed steel deck bridge in Howrah, aimed at easing traffic congestion on the Howrah Bridge. The new bridge will span the existing GT Road route, linking Howrah Station with the Howrah Bridge. The new structure is a response to the rising volume of vehicular traffic, which has been placing significant strain on the 75-year-old Howrah Bridge, leading to regular traffic jams and delays.The new cable-stayed bridge will feature a four-lane design and will measure 134 m in length, an expansion from the existing 60 meters of the Chandmari B..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000