How Afcons reduced construction time at Chhara by 9 days
Cement

How Afcons reduced construction time at Chhara by 9 days

At LNG Tanks, Chhara, the major scope of work included the construction of two LNG storage tanks (outer diameter 89.6 m and inner diameter 88 m). The tank construction entailed the construction of a prestressed concrete (PC) wall, 37.36 m high, to be constructed in 10 lifts. The team was able to reduce the cycle time of the PC wall construction for Tank 2 by 25 per cent (nine days) compared to Tank 1 by adopting LPS, 5S and waste elimination practices. PC wall activities involve multiple teams interfacing with each other: rebar fixing, H beams for compression ring support, laying prestressing ducts, VTL and HZT embedded plate installation, formwork installation, etc.

  • Minimising transportation and multiple handling by stacking rebar mats, links, vertical and horizontal inserts close to the corresponding area of the PC wall
  • Work sequence standardised and coordination meetings at the start of the day to minimise interference between multiple teams Analysis of variance in planned versus actual progress to identify root causes of delay
  • Design modification in TCP plate connections to minimise rework and improve speed of alignment.

At LNG Tanks, Chhara, the major scope of work included the construction of two LNG storage tanks (outer diameter 89.6 m and inner diameter 88 m). The tank construction entailed the construction of a prestressed concrete (PC) wall, 37.36 m high, to be constructed in 10 lifts. The team was able to reduce the cycle time of the PC wall construction for Tank 2 by 25 per cent (nine days) compared to Tank 1 by adopting LPS, 5S and waste elimination practices. PC wall activities involve multiple teams interfacing with each other: rebar fixing, H beams for compression ring support, laying prestressing ducts, VTL and HZT embedded plate installation, formwork installation, etc. Minimising transportation and multiple handling by stacking rebar mats, links, vertical and horizontal inserts close to the corresponding area of the PC wall Work sequence standardised and coordination meetings at the start of the day to minimise interference between multiple teams Analysis of variance in planned versus actual progress to identify root causes of delay Design modification in TCP plate connections to minimise rework and improve speed of alignment.

Next Story
Infrastructure Urban

Larsen & Toubro Secures Contract from Defence Ministry

The Ministry of Defence, Government of India, has awarded a significant contract to Larsen & Toubro (L&T) for supplying K9 Vajra-T Artillery Platforms to the Indian Army. As per the company's project classification, the contract is valued between Rs 50 billion and Rs 100 billion. The K9 Vajra-T, a 155 mm, 52-calibre tracked self-propelled artillery platform, is an adaptation of the globally renowned South Korean K9 Thunder howitzer. It has been co-developed by L&T and Hanwha Aerospace to meet the Indian Army's specific operational needs across diverse terrains, including deserts, plains, and..

Next Story
Real Estate

Delhi-NCR Housing Market sees 25% Sales Growth

The Delhi-NCR property market has maintained its momentum during the December quarter, with housing sales and new supply estimated to grow by 25 per cent and 59 per cent, respectively, as reported by PropEquity. Data from the real estate analytics firm suggests that housing sales in Delhi-NCR are likely to rise to 12,915 units during the October-December period of this year, compared to 10,354 units in the corresponding period of the previous year. New supply in the region is expected to increase significantly, reaching 11,223 units, a 59 per cent rise from 7,072 units in the year-ago quarter..

Next Story
Infrastructure Urban

DDC Approves Five Key Projects Under Kasaragod Development Package

The District Development Committee (DDC) has approved a budget of Rs 100.08 million for five key projects under the Kasaragod Development Package. This funding is part of the Rs 700 million allocated in the State budget for the 2024-25 financial year, with administrative approval formally amended to incorporate these initiatives. The decision was made during a meeting chaired by District Collector K. Inbasekar on Saturday, December 21. The approved projects include Rs 40.99 million for constructing Udayapuram Thungal Road in Kottom Belur grama panchayat and Rs 20.56 million for setting up a ..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000