TBM ‘Parvati’ Begins Tunneling on Kanpur Metro Line 2
31 Mar 2025 CW Team
The Kanpur Metro Project has reached another milestone as Kalpataru Projects International Ltd. (KPIL) – Gulermak JV deployed its third Tunnel Boring Machine (TBM) ""Parvati"" at Rawatpur Station for Line 2. This 8.38 km corridor stretches from Agriculture University to Barra-8.
About TBM Parvati
TBM Type: Herrenknecht Earth Pressure Balance (EPB) Machine (Refurbished, Ø6.5m)
7th TBM commissioned for Kanpur Metro Phase 1
3rd TBM for Package KNPCC-11, following TBMs Gomati (S-1408A) and Saraswati (S-839C)
Tunneling Assignments
First Task: Construct a 750m tunnel for the upline from Rawatpur to Kakadeo
Second Task: Dragged towards Kakadeo Station box, constructing a 700m tunnel to Double Pullia
Package KNPCC-11 Overview
Contractor: KPIL – Gulermak JV
Awarded: December 2023
Contract Value: Rs 7.62 billion
Deadline: 30 months
This package involves the twin tunnels for Line 2's 4.08 km underground section, along with the construction of three underground stations:
Rawatpur
Kakadeo
Double Pullia
Recent Developments
CMRS Inspection recently conducted for Kanpur Metro Line 1 between Moti Jheel and Kanpur Central Station, paving the way for passenger operations.
Kanpur Metro continues to push forward with cutting-edge tunneling technology, ensuring efficient underground connectivity for the city.