NH-55 Cuttack-Angul Expansion Set for Completion by April 2025
Project Scope and Challenges The NH-55 expansion is divided into three segments:
Cuttack to Dhenkanal (Package 1) Dhenkanal to Angul (Package 2) Angul to Sambalpur (Package 3) – already completed
The minister acknowledged that delays were caused by land acquisition hurdles, forest clearance issues, financial constraints faced by contractors, and disruptions due to the COVID-19 pandemic.
Efforts to Expedite Completion To accelerate progress, the Ministry of Road Transport and Highways is conducting regular stakeholder meetings and coordinating closely with the state government to ensure smooth execution.
Revised deadlines have been set, with Package 1 expected to conclude by March 2025 and Package 2 by April 2025, ensuring the completion of this critical infrastructure project.