Apco will build NHAI's B’luru-Chennai expressway segment
NHAI had invited bids for the package in December 2020 with a completion deadline of two years. This section between Baireddypalle and Bangarupalem lies in Andhra Pradesh. Technical bids were opened in February this year, to reveal eight bidders.
Apco Infratech: Rs 1,909.26 crore
HG Infra Engineering: Rs 2,073.08 crore
Adani Road Transport: Rs 2,190.63 crore
Megha Engineering and Infrastructures: Rs 2,266.44 crore
Ramalingam Construction: Rs 2,432.54 crore
GR Infraprojects: Rs 2,433.67 crore
Montecarlo: Rs 2,453.40 crore
KNR Constructions: Rs 4,063.32 crore
The scope of work includes construction of a 31 km four-lane stretch, under the Hybrid Annuity Model (HAM) as a part of the Bharatmala Pariyojna (phase-2 package-2).
Apco’s bid was 6.82% higher than NHAI’s estimate of Rs 1,783.83 crore, and the company is likely to receive a letter of award (LoA) in the coming weeks for the construction of the four-lane stretch.
The Bengaluru–Chennai Expressway project has been divided into three phases with a total of 10 packages between their terminals at Hoskote and Sriperumbudur.