Turbine Installation Completed at Rooppur NPP Unit 1 in Bangladesh
The barring gear ensures correct alignment and balancing of the turbine rotor before the start-up and shutdown, which prevents the turbine components form wearing and ensures safe and efficient work.
The experts carried out control checks that confirmed accuracy of the alignment and high quality of assembly of the turbine set.
“Installation of the turbine at Rooppur NPP Unit 1 has been completed successfully and this is an important step to the physical start-up of the plant. The turbine set placement on the barring gear and successful control checks confirm accuracy of the assembly and reliability of the equipment. This result is an accomplishment of a highly qualified team of specialists and another evidence of the reliability of Russian technologies”, noted Alexey Deriy, Atomstroyexport JSC Vice President for Projects in Bangladesh.