NCLAT Clears Supertech to Resume Work on Doon Square in Dehradun

The National Company Law Appellate Tribunal (NCLAT) has granted approval for Supertech to resume construction of its Doon Square project in Dehradun. This decision follows the submission by Supertech that the lender, co-developer, and homebuyers had all accepted its proposal to complete the stalled project.

The approval paves the way for the project’s completion within 515 days, or just over one year and four months. Out of the 750 planned units, only 150 studio apartments have been delivered, with the remaining awaiting completion.

Supertech’s proposal, submitted to NCLAT, was accepted by the project's sole lender, Bank of Baroda, through a one-time settlement and repayment plan. Co-developer EBI Projects & Developments LLP has already deposited ?75 lakh as upfront payment, with ?42.5 million to be paid after NCLAT's approval and the remaining ?530 million in installments over 12 months.

The project has also received the consent of homebuyers, and an intervention application supporting Supertech’s request was filed. The interim resolution professional (IRP), Hitesh Goyal, confirmed there were no objections from stakeholders, clearing the way for construction to resume.

The tribunal’s decision, delivered on September 25, marks a key step toward the completion of the much-delayed Doon Square project.

Related Stories

NCLAT Assigns NBCC as Project Manager for 16 Supertech Projects
Supertech opposes NBCC's plan to take over and finish 14,000 flats
Yamuna Expressway toll rates to increase from October 1
Greaves Electric Mobility Files for IPO
IREDA Approves Rs 30 Billion for Odisha's Renewable Energy Projects