Slipforms for hydropower projects

HCC opted for slipforms for the concreting of a 115-m-deep surge shaft for the Punatsangchhu hydropower project Stage I, a 1,200-mw, run-of-the-river project in Western Bhutan.

“We opted for slip-forming because it enables continuous, non-interrupted, cast-in-place jointless concrete structures that have superior performance characteristics compared to piece-wise construction using discrete form elements,” says S D Jeur, Senior Vice-President, Projects, HCC.

Slipforms with a three-layered platform structure were used. The entire formwork structure was built in-house. The top platform was used to erect the reinforcement concrete, the middle platform was used for general movement, and the bottom one was used to provide the finishing to the concrete surface.

Slipforms have to be in a continuous motion so that the concrete does not stick to them. The speed of this formwork depends on several factors like the weather condition, the amount of concrete poured at a time and the size of the structure. As the slipform can move (slipping rate, usually between 5 and 30 cm/hour) whenever the concrete can carry the load of its weight in the lowest parts of form sheet, the likely concrete setting time was determined based on the weather conditions (temperature, humidity, etc), cement ratio, type of cement, slump and admixtures.

Usually, the slipform structure rises up with the daily progress of 0.75 m/day in standard conditions. However, at Punatsangchhu-I HEP, the daily progress harnessed from slipform was at an average of 1 m/day. The concrete lining thickness varied from 850 mm at the top, 1,200 mm in the middle and 1,500 mm at the bottom. Concrete was poured into the forms in layers of about 200 mm.

CHARU BAHRI

Related Stories

Colliers India Transacts 207,000 sq ft office space at Embassy TechVillage
Ensemble Infrastructure India Appoints Suman Saha as Director of Design
Ribbon Vanity by Küche7: Fluid Design Meets Everyday Elegance