Innovation helped construct Delhi-Meerut Expressway Package 3
ROADS & HIGHWAYS

Innovation helped construct Delhi-Meerut Expressway Package 3

Union Minister for Road Transport & Highways and MSMEs Nitin Gadkari recently inaugurated Package 3 of the Delhi-Meerut Expressway, built at a civil cost of Rs 10.57 billion. The project is expected to help decongest the NCR, reduce travel time and heavy traffic jams in this section, and bring a significant reduction in the pollution level owing to lower fuel consumption.

The APCO Chetak Expressway JV executed work on this package. Innovative planning, design and construction methods marked the construction of the viaduct of this project for reducing construction time by the selection of materials, technology and sequence of operations.

The aim
The construction scheme was evolved looking at the traffic congestion, safety, traffic management through the construction zone and safety of commuters and mitigation of environment parameters. Hence, highlights Sanjay Shrivastava, Vice President, APCO Chetak Expressway, it was decided that maximum off-site activities would be promoted, such as:

Precast pre-stressed I-girders (28.1-m x 1.9-m-high) in casting yard.
Precast pier caps in two parts 7.6 m each (cantilever length of 8.4 m). Section sizes were selected for ease of construction, handling and erection (mostly weight governed).
A module of continuous integrated span totaling to 90 m (3 x 30 m) has intermediate piers, are monolithic with the deck and the deck is made to rest on free bearing only on expansion joints. The foundation pile cap required to support the elevated viaduct structure of 7.3 m x 7.3 m, accommodating eight piles of 1,000 mm dia, at every 30 m centre to centre. The size of pier is 1.6 m x 6 m, with a pier cap of 22.8-m-long. The top deck slab of 25.65 m has a base of seven I-shaped PSC girders, stationed on the pier cap.

Construction methodology
The viaduct part of the project involved construction of 1,097 precast pre-stressed I-girders of 1.9 m height, 310 precast post-stressed pier caps 7.6 m x 3.0 m, 1,148 piles (cast in-situ) of 1,000 mm x 24-m-deep, 157 pile caps (cast in-situ) 7.3 m x 7.3 m, 157 piers (cast in-situ) 1.6 m x 6 m, deck slab (cast in-situ) 156 nos x 30 m x 25.65 m, 120,042 sq m, 416 pot bearing and 104 guided bearing, single strip seal expansion joint – 53 nos.

The structural scheme developed mainly considered maximum off site activities, and assembling it in-place, says Shrivastava. “It was decided to construct girders in ‘precast casting yard’ of 12,000 sq m, having 12 beds, for three girders casting at a time at one bed. The expected production is 108 girders per month and staking capacity of 220 nos. It was arrived that in case of reduction of cycle time, the girder production can be increased to 180 nos per month by using early setting admixture or application of steam curing. Accordingly, four boilers (600 kg) were also commissioned for steam or hot water curing. The precast pier cap casting unit was also developed with 25 beds, for a production cycle of 25 nos per month. A steel cutting bending and binding automatic yard was conceived (50 m x 18 m), accommodating a shear line, a bend line, a straightening machine, three automatic stirrup benders, spiral, etc.”

The key construction activities and parameters that helped complete the project in a record time are:

  • Casting of precast pre-tensioned girders – off-site
  • Casting of precast post-stressed pier caps – off-site
  • Drilling for piles – in-situ
  • Fabrication of cages – off-site
  • Casting of piles – in-situ
  • Casting of pile caps – in-situ
  • Casting of piers – in-situ
  • Stitching and cast in-situ pier cap in flange over pier – in-situ
  • Stitching and casting of precast pier cap in web portion – in-situ
  • Post stressing three stage of pier caps – in-situ
  • Erection of girders by gantries
  • Erection of precast pier cap by gantries
  • Girder stitching with pier cap – in-situ
  • Casting of deck slab – in-situ
  • Finishing

Adds Shrivastava, “All the above mentioned activities are in a series, but by selecting two major activities as precast activities – I-girders and pier caps – they are operational on parallel basis. By these two precast activities the working width on the actual road reduced to 8.5 m in the road centre, with free flowing traffic on either side. The erection of precast I-girders and pier caps are being done with the help of gantries (tracks at 30 m centre to centre) instead of crane launching, thereby reducing the stoppage of traffic.”

Innovative improvisation
When asked what is the USP of the innovation and what were the improvised construction techniques to obtain ‘the aim’, Shrivastava elaborates:

a. Pre-cast girders at casting yard three numbers at a time, resulting in excellent and precision quality factory like output of I-girders.
b. Using of two gantries in casting yard to achieve higher quality and efficient production output.
c. High grade RCC, M55 grade with micro silica and admixture, to obtain early strength of 45 N per sq mm, within four to five days, required for de-stressing the HT cables, and early de-moulding.
d. Use of steam boilers for gaining early strength is an improvement technique lifted from working in cold country techniques.
e. Completion of pier cap in seven stages of construction work is a new innovation in the field of road construction. The detailed stages are as: (1) Pre-casting of left pier cap segment (2) Pre-casting of right pier cap     segment (3) Stitching and casting of flange porting over pier (4) Stitching and casting of web portion (5) Stressing of two cables of the pier cap after completion of casting, thereby removing of bottom supports        (6) Stressing of next two cables of the pier cap after erection of seven I-girders (7) Stressing of the last two cables of the pier cap after completion of deck slab casting (8) Pre-stressing the pier cap and removal of      bottom supports.
f. Erection of I-Girders (seven nos in one span) over the pier cap.
g. Use of deck sheet for deck slab casting.

The above methodology resulted in ease of construction at site by breaking down of activities and has largely resulted in decreased traffic congestion, increased safety, better traffic management through the construction zone, safety of commuters and better mitigation of environment parameters.

Most importantly, the pioneered technologies used in this project are easy to adopt and do not attract any upfront working capital. “This innovation will leave a lasting impression on every forthcoming project in the nation on state and national highways. It will be an extraordinary practice, if adapted in road construction,” prides Shrivastava.

- SERAPHINA D’SOUZA

Union Minister for Road Transport & Highways and MSMEs Nitin Gadkari recently inaugurated Package 3 of the Delhi-Meerut Expressway, built at a civil cost of Rs 10.57 billion. The project is expected to help decongest the NCR, reduce travel time and heavy traffic jams in this section, and bring a significant reduction in the pollution level owing to lower fuel consumption. The APCO Chetak Expressway JV executed work on this package. Innovative planning, design and construction methods marked the construction of the viaduct of this project for reducing construction time by the selection of materials, technology and sequence of operations. The aim The construction scheme was evolved looking at the traffic congestion, safety, traffic management through the construction zone and safety of commuters and mitigation of environment parameters. Hence, highlights Sanjay Shrivastava, Vice President, APCO Chetak Expressway, it was decided that maximum off-site activities would be promoted, such as: Precast pre-stressed I-girders (28.1-m x 1.9-m-high) in casting yard. Precast pier caps in two parts 7.6 m each (cantilever length of 8.4 m). Section sizes were selected for ease of construction, handling and erection (mostly weight governed). A module of continuous integrated span totaling to 90 m (3 x 30 m) has intermediate piers, are monolithic with the deck and the deck is made to rest on free bearing only on expansion joints. The foundation pile cap required to support the elevated viaduct structure of 7.3 m x 7.3 m, accommodating eight piles of 1,000 mm dia, at every 30 m centre to centre. The size of pier is 1.6 m x 6 m, with a pier cap of 22.8-m-long. The top deck slab of 25.65 m has a base of seven I-shaped PSC girders, stationed on the pier cap. Construction methodology The viaduct part of the project involved construction of 1,097 precast pre-stressed I-girders of 1.9 m height, 310 precast post-stressed pier caps 7.6 m x 3.0 m, 1,148 piles (cast in-situ) of 1,000 mm x 24-m-deep, 157 pile caps (cast in-situ) 7.3 m x 7.3 m, 157 piers (cast in-situ) 1.6 m x 6 m, deck slab (cast in-situ) 156 nos x 30 m x 25.65 m, 120,042 sq m, 416 pot bearing and 104 guided bearing, single strip seal expansion joint – 53 nos. The structural scheme developed mainly considered maximum off site activities, and assembling it in-place, says Shrivastava. “It was decided to construct girders in ‘precast casting yard’ of 12,000 sq m, having 12 beds, for three girders casting at a time at one bed. The expected production is 108 girders per month and staking capacity of 220 nos. It was arrived that in case of reduction of cycle time, the girder production can be increased to 180 nos per month by using early setting admixture or application of steam curing. Accordingly, four boilers (600 kg) were also commissioned for steam or hot water curing. The precast pier cap casting unit was also developed with 25 beds, for a production cycle of 25 nos per month. A steel cutting bending and binding automatic yard was conceived (50 m x 18 m), accommodating a shear line, a bend line, a straightening machine, three automatic stirrup benders, spiral, etc.” The key construction activities and parameters that helped complete the project in a record time are: Casting of precast pre-tensioned girders – off-siteCasting of precast post-stressed pier caps – off-site Drilling for piles – in-situ Fabrication of cages – off-site Casting of piles – in-situ Casting of pile caps – in-situ Casting of piers – in-situ Stitching and cast in-situ pier cap in flange over pier – in-situ Stitching and casting of precast pier cap in web portion – in-situ Post stressing three stage of pier caps – in-situ Erection of girders by gantries Erection of precast pier cap by gantries Girder stitching with pier cap – in-situ Casting of deck slab – in-situ Finishing Adds Shrivastava, “All the above mentioned activities are in a series, but by selecting two major activities as precast activities – I-girders and pier caps – they are operational on parallel basis. By these two precast activities the working width on the actual road reduced to 8.5 m in the road centre, with free flowing traffic on either side. The erection of precast I-girders and pier caps are being done with the help of gantries (tracks at 30 m centre to centre) instead of crane launching, thereby reducing the stoppage of traffic.” Innovative improvisation When asked what is the USP of the innovation and what were the improvised construction techniques to obtain ‘the aim’, Shrivastava elaborates: a. Pre-cast girders at casting yard three numbers at a time, resulting in excellent and precision quality factory like output of I-girders. b. Using of two gantries in casting yard to achieve higher quality and efficient production output. c. High grade RCC, M55 grade with micro silica and admixture, to obtain early strength of 45 N per sq mm, within four to five days, required for de-stressing the HT cables, and early de-moulding. d. Use of steam boilers for gaining early strength is an improvement technique lifted from working in cold country techniques. e. Completion of pier cap in seven stages of construction work is a new innovation in the field of road construction. The detailed stages are as: (1) Pre-casting of left pier cap segment (2) Pre-casting of right pier cap     segment (3) Stitching and casting of flange porting over pier (4) Stitching and casting of web portion (5) Stressing of two cables of the pier cap after completion of casting, thereby removing of bottom supports        (6) Stressing of next two cables of the pier cap after erection of seven I-girders (7) Stressing of the last two cables of the pier cap after completion of deck slab casting (8) Pre-stressing the pier cap and removal of      bottom supports. f. Erection of I-Girders (seven nos in one span) over the pier cap. g. Use of deck sheet for deck slab casting. The above methodology resulted in ease of construction at site by breaking down of activities and has largely resulted in decreased traffic congestion, increased safety, better traffic management through the construction zone, safety of commuters and better mitigation of environment parameters. Most importantly, the pioneered technologies used in this project are easy to adopt and do not attract any upfront working capital. “This innovation will leave a lasting impression on every forthcoming project in the nation on state and national highways. It will be an extraordinary practice, if adapted in road construction,” prides Shrivastava. - SERAPHINA D’SOUZA

Next Story
Infrastructure Urban

bauma Conexpo 2024 is it the largest edition, with 1,000 exhibitors

India's construction equipment industry is experiencing significant growth, fueled by rapid infrastructure development, expanding mining activities, and increasing urbanisation. bauma Conexpo India will bring together leaders, global players and decision-makers from the international trade fair for construction machinery, building material machines, mining machines and construction vehicles under one roof. The exhibition will host its biannual event at the India Expo Centre, Greater Noida  from 11 to 14 December 2024.In 2023, the exhibition attracted 41,108 participants as well as 601 exh..

Next Story
Infrastructure Urban

Our commitment to excellence and innovation drives our success

In India's dynamic industrial landscape, Gmmco, a comprehensive solutions provider across the construction, resources and energy transportation industries, stands as a testament to innovation. As a powerhouse of the CK Birla Group with a legacy spanning over five decades, the company has evolved from a traditional equipment supplier to a full-spectrum solutions provider, prioritising technology, innovation and sustainability. Its distinctive approach includes rental solutions, used equipment options, financing support, rebuilt options and tailored product support solutions, setting new benchma..

Next Story
Infrastructure Urban

Vedanta plans $2 billion investment in Saudi Arabia copper projects

Vedanta announced its plan to invest $2 billion in major copper projects in Saudi Arabia. Vedanta Copper International, a wholly-owned subsidiary of the company, has signed an agreement with Saudi Arabia's Ministry of Investment and Ministry of Industries & Mineral Resources. The agreement outlines the establishment of a greenfield copper smelter and refinery with a capacity of 400 kilo tonnes per annum (KTPA) and a 300 KTPA copper rod project. According to the company, this collaboration aligns with Saudi Arabia's Vision 2030 and aims to invest $2 billion in significant copper projects withi..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000