Funding challenges in HAM projects for roads
ROADS & HIGHWAYS

Funding challenges in HAM projects for roads

On the government’s part, there has been a conscious shift in strategy from traditional BOT model towards EPC and HAM. 

That said, it is evident that NHAI would need to significantly improve visibility of raising funds on their balance sheet, failing which, there may be speculations about their limited financial bandwidth,” says Sandeep Upadhyay, Managing Director- Infrastructure Advisory, Centrum Capital. “One of the primary challenge today is funding these projects for the next 15 years; so lenders and other stakeholders have to take a call on NHAIs leveraging capabilities over the next 15-20 years. The second impediment is the reluctance of Banks to fund HAM projects given the greenfield risks associated with it. The third risk is associated with the ability of promoters to bring in their contribution of 12-15 per cent of the total capex as equity in HAM projects.” Apart from the these challenges being faced for long term financing,  the EPC companies are facing a huge push back from the Banks on the issuance of non-fund based limits against new orders on account of huge NPA fallout with EPC firms due to their BGs being invoked on account of non performance.

Of the total 108 HAM projects awarded to date, 60-odd projects have been awarded in FY2018. “Of these, as on February 7, 2019, around 45 per cent projects are yet to complete financial closure (FC) including 20 per cent wherein documents are yet to be submitted,” confirms Vishal Kotecha, Associate Director, India Ratings and Research (Fitch Group). A delay in FC is evident, for which, Kotecha points to “the lack of participation of PSU banks.” 

HAM was introduced following the failure of the BOT toll model owing to aggressive initial traffic estimates. As Vijay Agrawal, Executive Director, Equirus Capital, says, “HAM was introduced to alleviate toll estimation pressures, get wider market participation in the PPP model and reduce funding pressures on the authority.” Nonetheless, he avers that HAM is also singing a similar tune as the BOT toll model. 

Awards in HAM assets have significantly dried up, the main reasons being delay in promised land acquisition by NHAI and large lead times in obtaining other regulatory clearances.  

SHRIYAL SETHUMADHAVAN

Shift from Toll to HAM and back to EPC– Transition

On the government’s part, there has been a conscious shift in strategy from traditional BOT model towards EPC and HAM. That said, it is evident that NHAI would need to significantly improve visibility of raising funds on their balance sheet, failing which, there may be speculations about their limited financial bandwidth,” says Sandeep Upadhyay, Managing Director- Infrastructure Advisory, Centrum Capital. “One of the primary challenge today is funding these projects for the next 15 years; so lenders and other stakeholders have to take a call on NHAIs leveraging capabilities over the next 15-20 years. The second impediment is the reluctance of Banks to fund HAM projects given the greenfield risks associated with it. The third risk is associated with the ability of promoters to bring in their contribution of 12-15 per cent of the total capex as equity in HAM projects.” Apart from the these challenges being faced for long term financing,  the EPC companies are facing a huge push back from the Banks on the issuance of non-fund based limits against new orders on account of huge NPA fallout with EPC firms due to their BGs being invoked on account of non performance.Of the total 108 HAM projects awarded to date, 60-odd projects have been awarded in FY2018. “Of these, as on February 7, 2019, around 45 per cent projects are yet to complete financial closure (FC) including 20 per cent wherein documents are yet to be submitted,” confirms Vishal Kotecha, Associate Director, India Ratings and Research (Fitch Group). A delay in FC is evident, for which, Kotecha points to “the lack of participation of PSU banks.” HAM was introduced following the failure of the BOT toll model owing to aggressive initial traffic estimates. As Vijay Agrawal, Executive Director, Equirus Capital, says, “HAM was introduced to alleviate toll estimation pressures, get wider market participation in the PPP model and reduce funding pressures on the authority.” Nonetheless, he avers that HAM is also singing a similar tune as the BOT toll model. Awards in HAM assets have significantly dried up, the main reasons being delay in promised land acquisition by NHAI and large lead times in obtaining other regulatory clearances.   SHRIYAL SETHUMADHAVANShift from Toll to HAM and back to EPC– Transition

Next Story
Infrastructure Energy

REC Transfers HVDC Project to Power Grid

REC Limited has successfully handed over the Special Purpose Vehicle (SPV) for a High-Voltage Direct Current (HVDC) transmission project to Power Grid Corporation of India Limited (PGCIL). This strategic move aligns with the nation's objectives to strengthen its power transmission network. Key Highlights: Project Overview: The HVDC project, under the inter-state transmission system (ISTS) initiative, is a critical component of India's push toward robust and efficient electricity transmission. It aims to handle bulk power transfer across long distances while ensuring minimal losses. Role of RE..

Next Story
Infrastructure Transport

NF Railway Collaborates with IIT Guwahati

The Northeast Frontier (NF) Railway has signed strategic Memorandums of Understanding (MoUs) with IIT Guwahati to foster technological advancements and improve railway operations in the region. This partnership focuses on innovative solutions to enhance safety, efficiency, and sustainability in rail infrastructure. Key Highlights: Purpose of MoUs: The collaboration aims to leverage IIT Guwahati's expertise in technology and research for implementing cutting-edge solutions across railway operations. Key areas of focus include: Automation and digitization in maintenance. Sustainability initiati..

Next Story
Infrastructure Transport

Danapur Division Modernization Plans Revealed

The Railway Board has unveiled ambitious plans for the expansion and modernization of the Danapur Division, a critical hub under the East Central Railway. The initiative focuses on infrastructure development, enhanced passenger amenities, and operational efficiency. Key Highlights: Scope of Modernization: The Railway Board's blueprint emphasizes: Upgrading existing infrastructure to accommodate more passenger and freight traffic. Improving station facilities, such as platforms, waiting areas, and connectivity. Introducing advanced signal systems for safer and smoother operations. Freig..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000