Maharashtra leads the states with 129 delayed projects
PORTS & SHIPPING

Maharashtra leads the states with 129 delayed projects

There’s an undeniable reason for project delays: States working in silos, thus disrupting project execution.  
An analysis of the September 2018 Flash Report, published by the Ministry of Statistics and Planning, reveals the top five states, with more than 400 projects together, who are costing the exchequer Rs 6 trillion. In return, the expenditure on these projects seems to be subdued as these five states have spent a mere Rs 2.52 billion over the past two decades. 

Topping the chart is Maharashtra. The state has witnessed a cost overrun in 129 projects to the tune of Rs 1.99 trillion. However, when it comes to expenditure, Maharashtra has spent merely Rs 688.89 billion. The next in line is Uttar Pradesh. While the state has crossed a century in project delays, the cost overrun attributed to these projects was Rs 1.31 trillion as against Rs 1.27 trillion. Again, just Rs 485.88 billion was spent on these projects.

Bihar has also faced delays and cost overruns in 90 projects amounting to Rs 1.12 trillion as against the original cost of Rs 754.87 billion. Odisha, which recently witnessed the launch of numerous projects by Prime Minister Narendra Modi, is not far behind! The state’s 81 projects have incurred cost overruns to the tune of Rs 970.21 billion, spending Rs 288.95 billion. Last, Tamil Nadu witnessed Rs 1.31 trillion of cost overruns against the original Rs 1.27 trillion for 70 projects. 

The state has spent Rs 611.08 billion on these projects. 
The numbers aside, it is evident that the country is witnessing an infrastructure boom. Sectors such as railways (mainly metro), roads, smart cities, port-led development projects and greenfield industrial cities are drawing huge investments and providing immense opportunities to medium to large developers and contractors. 

Notable upcoming projects include the Mumbai Coastal Road, the bullet train, industrial corridors, and projects being awarded under the Bharatmala and Sagarmala schemes. However, the delay relay needs to reach its finish line to ensure these landmarks see the light of day – soon.

SHRIYAL SETHUMADHAVAN and RAHUL KAMAT

There’s an undeniable reason for project delays: States working in silos, thus disrupting project execution.   An analysis of the September 2018 Flash Report, published by the Ministry of Statistics and Planning, reveals the top five states, with more than 400 projects together, who are costing the exchequer Rs 6 trillion. In return, the expenditure on these projects seems to be subdued as these five states have spent a mere Rs 2.52 billion over the past two decades.  Topping the chart is Maharashtra. The state has witnessed a cost overrun in 129 projects to the tune of Rs 1.99 trillion. However, when it comes to expenditure, Maharashtra has spent merely Rs 688.89 billion. The next in line is Uttar Pradesh. While the state has crossed a century in project delays, the cost overrun attributed to these projects was Rs 1.31 trillion as against Rs 1.27 trillion. Again, just Rs 485.88 billion was spent on these projects. Bihar has also faced delays and cost overruns in 90 projects amounting to Rs 1.12 trillion as against the original cost of Rs 754.87 billion. Odisha, which recently witnessed the launch of numerous projects by Prime Minister Narendra Modi, is not far behind! The state’s 81 projects have incurred cost overruns to the tune of Rs 970.21 billion, spending Rs 288.95 billion. Last, Tamil Nadu witnessed Rs 1.31 trillion of cost overruns against the original Rs 1.27 trillion for 70 projects.  The state has spent Rs 611.08 billion on these projects.  The numbers aside, it is evident that the country is witnessing an infrastructure boom. Sectors such as railways (mainly metro), roads, smart cities, port-led development projects and greenfield industrial cities are drawing huge investments and providing immense opportunities to medium to large developers and contractors.  Notable upcoming projects include the Mumbai Coastal Road, the bullet train, industrial corridors, and projects being awarded under the Bharatmala and Sagarmala schemes. However, the delay relay needs to reach its finish line to ensure these landmarks see the light of day – soon. SHRIYAL SETHUMADHAVAN and RAHUL KAMAT

Next Story
Real Estate

The Only Way is Up!

In 2025, India’s real-estate market will be driven by a confluence of economic, demographic and policy-driven factors. Among these, Boman Irani, President, CREDAI National, counts rapid urbanisation, the rise of the middle class, policy reforms like RERA and GST rationalisation, and the Government’s decision to allow 100 per cent FDI in construction development projects (including townships, housing, built-up infrastructure, and real-estate broking services).In the top metros, especially Bengaluru, followed by Hyderabad and Pune, the key drivers will continue to be job creation a..

Next Story
Building Material

Organisations valuing gender diversity achieve higher profitability

The building materials industry is projected to grow by 8-12 per cent over the next five years. How is Aparna Enterprises positioning itself to leverage this momentum and solidify its market presence?The Indian construction and building materials industry is projected to witness significant expansion, with estimates suggesting an 8-12 per cent compound annual growth rate (CAGR) over the next five years. This growth is fuelled by rapid urbanisation, increased infrastructure investments and sustainability-focused policies. With India's real-estate market expected to reach $ 1 trillion by 2030, t..

Next Story
Real Estate

Dealing with Delays

Delays have beleaguered many a construction project in India, hampering the country from building to its ability and potential, and leading to additional costs incurred by the contractor. The reasons for delayIn India, delays mainly occur owing to obtaining statutory approvals, non-provisioning of right of way, utility diversion and approval of drawings and design. Delays are broadly classified based on responsibility and effect. Excusable delays arise from factors beyond the contractor’s control, such as force majeure events or employer-induced delays. These delays generally entitle th..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?