Maharashtra leads the states with 129 delayed projects
PORTS & SHIPPING

Maharashtra leads the states with 129 delayed projects

There’s an undeniable reason for project delays: States working in silos, thus disrupting project execution.  
An analysis of the September 2018 Flash Report, published by the Ministry of Statistics and Planning, reveals the top five states, with more than 400 projects together, who are costing the exchequer Rs 6 trillion. In return, the expenditure on these projects seems to be subdued as these five states have spent a mere Rs 2.52 billion over the past two decades. 

Topping the chart is Maharashtra. The state has witnessed a cost overrun in 129 projects to the tune of Rs 1.99 trillion. However, when it comes to expenditure, Maharashtra has spent merely Rs 688.89 billion. The next in line is Uttar Pradesh. While the state has crossed a century in project delays, the cost overrun attributed to these projects was Rs 1.31 trillion as against Rs 1.27 trillion. Again, just Rs 485.88 billion was spent on these projects.

Bihar has also faced delays and cost overruns in 90 projects amounting to Rs 1.12 trillion as against the original cost of Rs 754.87 billion. Odisha, which recently witnessed the launch of numerous projects by Prime Minister Narendra Modi, is not far behind! The state’s 81 projects have incurred cost overruns to the tune of Rs 970.21 billion, spending Rs 288.95 billion. Last, Tamil Nadu witnessed Rs 1.31 trillion of cost overruns against the original Rs 1.27 trillion for 70 projects. 

The state has spent Rs 611.08 billion on these projects. 
The numbers aside, it is evident that the country is witnessing an infrastructure boom. Sectors such as railways (mainly metro), roads, smart cities, port-led development projects and greenfield industrial cities are drawing huge investments and providing immense opportunities to medium to large developers and contractors. 

Notable upcoming projects include the Mumbai Coastal Road, the bullet train, industrial corridors, and projects being awarded under the Bharatmala and Sagarmala schemes. However, the delay relay needs to reach its finish line to ensure these landmarks see the light of day – soon.

SHRIYAL SETHUMADHAVAN and RAHUL KAMAT

There’s an undeniable reason for project delays: States working in silos, thus disrupting project execution.   An analysis of the September 2018 Flash Report, published by the Ministry of Statistics and Planning, reveals the top five states, with more than 400 projects together, who are costing the exchequer Rs 6 trillion. In return, the expenditure on these projects seems to be subdued as these five states have spent a mere Rs 2.52 billion over the past two decades.  Topping the chart is Maharashtra. The state has witnessed a cost overrun in 129 projects to the tune of Rs 1.99 trillion. However, when it comes to expenditure, Maharashtra has spent merely Rs 688.89 billion. The next in line is Uttar Pradesh. While the state has crossed a century in project delays, the cost overrun attributed to these projects was Rs 1.31 trillion as against Rs 1.27 trillion. Again, just Rs 485.88 billion was spent on these projects. Bihar has also faced delays and cost overruns in 90 projects amounting to Rs 1.12 trillion as against the original cost of Rs 754.87 billion. Odisha, which recently witnessed the launch of numerous projects by Prime Minister Narendra Modi, is not far behind! The state’s 81 projects have incurred cost overruns to the tune of Rs 970.21 billion, spending Rs 288.95 billion. Last, Tamil Nadu witnessed Rs 1.31 trillion of cost overruns against the original Rs 1.27 trillion for 70 projects.  The state has spent Rs 611.08 billion on these projects.  The numbers aside, it is evident that the country is witnessing an infrastructure boom. Sectors such as railways (mainly metro), roads, smart cities, port-led development projects and greenfield industrial cities are drawing huge investments and providing immense opportunities to medium to large developers and contractors.  Notable upcoming projects include the Mumbai Coastal Road, the bullet train, industrial corridors, and projects being awarded under the Bharatmala and Sagarmala schemes. However, the delay relay needs to reach its finish line to ensure these landmarks see the light of day – soon. SHRIYAL SETHUMADHAVAN and RAHUL KAMAT

Next Story
Infrastructure Urban

Campal Stadium Project Delayed

The football stadium and parade ground project in Campal, Panaji, which was initiated under the smart city plan, has yet to be completed, even though it is over a year past its original deadline. The project started on March 21, 2022, and according to the initial work order, it was supposed to be finished by September 20, 2023. Imagine Panaji Smart City Development Ltd (IPSCDL) has reported that 98% of the work is complete, with the final 2% expected to be finished by March 2025. "A small area where the concrete batching plant is situated needs completion," they said. The project's total est..

Next Story
Infrastructure Urban

Cleanliness Control Centre to Monitor Work, Complaints 24X7

Jaipur's cleanliness management system is set to be more efficient with the Integrated Command and Control Centre now operating 24/7. On Friday, Arun Kumar Hasija, CEO of Jaipur Smart City Limited, issued orders to implement this change. Hasija explained that the centre will supervise door-to-door refuse collection, sanitation operations, and mechanized cleaning activities. Special attention is being given to night-time cleaning across the city, with advanced machinery being used to sanitize road dividers in areas like the Walled City. The centre will now operate round-the-clock to improve c..

Next Story
Infrastructure Urban

Rs 1 Bn Plan for Waste Disposal at Bandhwari Landfill

A Rs 1 billion plan for disposing of over 10 lakh tonnes of legacy waste at the Bandhwari Solid Waste Treatment Plant has been submitted to the Department of Urban Local Bodies (ULB) for approval. The proposal is expected to be approved in an upcoming purchase committee meeting led by Haryana Chief Minister Nayab Singh Saini, officials from the Municipal Corporation of Gurugram (MCG) said. This proposal follows the December 17 deadline set by the National Green Tribunal (NGT) for MCG to submit an update on waste disposal progress at Bandhwari. Earlier this year, MCG had assured the NGT in an a..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000