Maharashtra leads the states with 129 delayed projects
PORTS & SHIPPING

Maharashtra leads the states with 129 delayed projects

There’s an undeniable reason for project delays: States working in silos, thus disrupting project execution.  
An analysis of the September 2018 Flash Report, published by the Ministry of Statistics and Planning, reveals the top five states, with more than 400 projects together, who are costing the exchequer Rs 6 trillion. In return, the expenditure on these projects seems to be subdued as these five states have spent a mere Rs 2.52 billion over the past two decades. 

Topping the chart is Maharashtra. The state has witnessed a cost overrun in 129 projects to the tune of Rs 1.99 trillion. However, when it comes to expenditure, Maharashtra has spent merely Rs 688.89 billion. The next in line is Uttar Pradesh. While the state has crossed a century in project delays, the cost overrun attributed to these projects was Rs 1.31 trillion as against Rs 1.27 trillion. Again, just Rs 485.88 billion was spent on these projects.

Bihar has also faced delays and cost overruns in 90 projects amounting to Rs 1.12 trillion as against the original cost of Rs 754.87 billion. Odisha, which recently witnessed the launch of numerous projects by Prime Minister Narendra Modi, is not far behind! The state’s 81 projects have incurred cost overruns to the tune of Rs 970.21 billion, spending Rs 288.95 billion. Last, Tamil Nadu witnessed Rs 1.31 trillion of cost overruns against the original Rs 1.27 trillion for 70 projects. 

The state has spent Rs 611.08 billion on these projects. 
The numbers aside, it is evident that the country is witnessing an infrastructure boom. Sectors such as railways (mainly metro), roads, smart cities, port-led development projects and greenfield industrial cities are drawing huge investments and providing immense opportunities to medium to large developers and contractors. 

Notable upcoming projects include the Mumbai Coastal Road, the bullet train, industrial corridors, and projects being awarded under the Bharatmala and Sagarmala schemes. However, the delay relay needs to reach its finish line to ensure these landmarks see the light of day – soon.

SHRIYAL SETHUMADHAVAN and RAHUL KAMAT

There’s an undeniable reason for project delays: States working in silos, thus disrupting project execution.   An analysis of the September 2018 Flash Report, published by the Ministry of Statistics and Planning, reveals the top five states, with more than 400 projects together, who are costing the exchequer Rs 6 trillion. In return, the expenditure on these projects seems to be subdued as these five states have spent a mere Rs 2.52 billion over the past two decades.  Topping the chart is Maharashtra. The state has witnessed a cost overrun in 129 projects to the tune of Rs 1.99 trillion. However, when it comes to expenditure, Maharashtra has spent merely Rs 688.89 billion. The next in line is Uttar Pradesh. While the state has crossed a century in project delays, the cost overrun attributed to these projects was Rs 1.31 trillion as against Rs 1.27 trillion. Again, just Rs 485.88 billion was spent on these projects. Bihar has also faced delays and cost overruns in 90 projects amounting to Rs 1.12 trillion as against the original cost of Rs 754.87 billion. Odisha, which recently witnessed the launch of numerous projects by Prime Minister Narendra Modi, is not far behind! The state’s 81 projects have incurred cost overruns to the tune of Rs 970.21 billion, spending Rs 288.95 billion. Last, Tamil Nadu witnessed Rs 1.31 trillion of cost overruns against the original Rs 1.27 trillion for 70 projects.  The state has spent Rs 611.08 billion on these projects.  The numbers aside, it is evident that the country is witnessing an infrastructure boom. Sectors such as railways (mainly metro), roads, smart cities, port-led development projects and greenfield industrial cities are drawing huge investments and providing immense opportunities to medium to large developers and contractors.  Notable upcoming projects include the Mumbai Coastal Road, the bullet train, industrial corridors, and projects being awarded under the Bharatmala and Sagarmala schemes. However, the delay relay needs to reach its finish line to ensure these landmarks see the light of day – soon. SHRIYAL SETHUMADHAVAN and RAHUL KAMAT

Next Story
Infrastructure Energy

REC Transfers HVDC Project to Power Grid

REC Limited has successfully handed over the Special Purpose Vehicle (SPV) for a High-Voltage Direct Current (HVDC) transmission project to Power Grid Corporation of India Limited (PGCIL). This strategic move aligns with the nation's objectives to strengthen its power transmission network. Key Highlights: Project Overview: The HVDC project, under the inter-state transmission system (ISTS) initiative, is a critical component of India's push toward robust and efficient electricity transmission. It aims to handle bulk power transfer across long distances while ensuring minimal losses. Role of RE..

Next Story
Infrastructure Transport

NF Railway Collaborates with IIT Guwahati

The Northeast Frontier (NF) Railway has signed strategic Memorandums of Understanding (MoUs) with IIT Guwahati to foster technological advancements and improve railway operations in the region. This partnership focuses on innovative solutions to enhance safety, efficiency, and sustainability in rail infrastructure. Key Highlights: Purpose of MoUs: The collaboration aims to leverage IIT Guwahati's expertise in technology and research for implementing cutting-edge solutions across railway operations. Key areas of focus include: Automation and digitization in maintenance. Sustainability initiati..

Next Story
Infrastructure Transport

Danapur Division Modernization Plans Revealed

The Railway Board has unveiled ambitious plans for the expansion and modernization of the Danapur Division, a critical hub under the East Central Railway. The initiative focuses on infrastructure development, enhanced passenger amenities, and operational efficiency. Key Highlights: Scope of Modernization: The Railway Board's blueprint emphasizes: Upgrading existing infrastructure to accommodate more passenger and freight traffic. Improving station facilities, such as platforms, waiting areas, and connectivity. Introducing advanced signal systems for safer and smoother operations. Freig..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000