Cement, steel availability and prices regularised?
Cement

Cement, steel availability and prices regularised?

Photo courtesy: L&T

The migration of labour workforce and supply chain disruptions affected a large number of infra projects.

When CW conducted our webinar on Roads to Recovery  on April 21, speaking about construction works commencing at the time, Devendra Jain, Executive Director & CEO, Dilip Buildcon, told us then that at the time the company had been connecting with cement and steel industries, but their manufacturers did not have drivers and hence were unable to supply these materials. “Transportation is a major factor; and the supply chain now is the biggest problem. For cement, we do not keep an inventory for more than 15 days and for steel of more than 20-25 days. So here, the supply chain remains the main challenge. Another challenge is the manpower and labour. The morale of the labourers is low and they would probably want to go to their villages once transportation picks up. After that we will be the monsoon season. So, we will have to see where the red zones are going to be.”

And commenting on the spike in the prices of cement, Sandeep Garg, Managing Director & CEO, Welspun Enterprises, had again pointed out to it being a matter of the supply chain. “There is a demand and supply gap. It is a matter of time. We will have to wait and see regarding the cement prices.”

CW once again connected with leading contractors to understand if the availability for materials such as cement and steel have regularised; if prices are in tandem; and disruptions in the supply chain affecting output, if any.

GR Infraprojects (GRIL) initially had to face a lot of difficulty as there were many scheduled activities that were suddenly halted. As Ratan Lal Kashyap, Senior Vice President-Procurement, GR Infraprojects, tells us, “Supply chain logistics were stuck at various stages; a few were billed and ready for dispatch; a few loaded and dispatched; a few got stuck enroute while others were stuck at district and state borders; and a few reached the destination but could not be unloaded owing to the fear of Coronavirus. Logistics was one of the biggest hindrances in the lockdown. Logistics because of the paucity of drivers were affected initially but now the supply chains are smoothened except in areas badly affected by COVID-19. They are almost back to normal but extra efforts are being made to align deliveries to project requirements.” He adds that cement availability was a problem across all geographical areas as manufacturing plants were completely shutdown during the lockdown period and that rates have spiked owing to high production cost and low demand. “The steel industry, though, was positive; availability was smooth and prices were regulated.”

Yogesh Kumar Jain, Managing Director, PNC Infratech, reveals that during May and early June, there was an acute paucity in the supply of cement and manufacturing items, and a consequent rise in their prices, “plausibly because of a demand-supply mismatch owing to suspension of production during the lockdown spell”. Though both supplies and the process are getting stabilised gradually, he believes it may take some more time for normalisation.

K Jalandhar Reddy, Executive Director, KNR Constructions, believes there is improvement in the movement of goods like steel and cement and that supply of these materials has improved to a greater extent with the Government lifting lockdown in a staggered manner. With regard to prices, he shares that prices of cement have increased from 25-40 per cent in different parts of the country while there is a slight reduction in steel prices. “We hope the supply chain movement will improve further.”

On the other hand, Tata Projects did not face any issues with regards to supply chains as “our supply lines have always been robust with adequate supplies,” says Himanshu Chaturvedi, Chief Strategy Officer, Tata Projects.

And for SN Subrahmanyan, CEO & Managing Director, L&T, disruptions in the supply chain are only to be expected with the entire country in a lockdown. “Supply of critical material like cement and steel is still not there but the situation is improving by the day and we hope things will almost be back to normal soon.” When asked if prices of these materials are in tandem, he responds that the prices have not fluctuated alarmingly: “We are confident this situation will not change significantly going forward.”

Also read:

  • How are construction cos managing operations at sites? 
  • How are contractors working towards revival post-COVID? 
  • Photo courtesy: L&TThe migration of labour workforce and supply chain disruptions affected a large number of infra projects. When CW conducted our webinar on Roads to Recovery  on April 21, speaking about construction works commencing at the time, Devendra Jain, Executive Director & CEO, Dilip Buildcon, told us then that at the time the company had been connecting with cement and steel industries, but their manufacturers did not have drivers and hence were unable to supply these materials. “Transportation is a major factor; and the supply chain now is the biggest problem. For cement, we do not keep an inventory for more than 15 days and for steel of more than 20-25 days. So here, the supply chain remains the main challenge. Another challenge is the manpower and labour. The morale of the labourers is low and they would probably want to go to their villages once transportation picks up. After that we will be the monsoon season. So, we will have to see where the red zones are going to be.” And commenting on the spike in the prices of cement, Sandeep Garg, Managing Director & CEO, Welspun Enterprises, had again pointed out to it being a matter of the supply chain. “There is a demand and supply gap. It is a matter of time. We will have to wait and see regarding the cement prices.”CW once again connected with leading contractors to understand if the availability for materials such as cement and steel have regularised; if prices are in tandem; and disruptions in the supply chain affecting output, if any. GR Infraprojects (GRIL) initially had to face a lot of difficulty as there were many scheduled activities that were suddenly halted. As Ratan Lal Kashyap, Senior Vice President-Procurement, GR Infraprojects, tells us, “Supply chain logistics were stuck at various stages; a few were billed and ready for dispatch; a few loaded and dispatched; a few got stuck enroute while others were stuck at district and state borders; and a few reached the destination but could not be unloaded owing to the fear of Coronavirus. Logistics was one of the biggest hindrances in the lockdown. Logistics because of the paucity of drivers were affected initially but now the supply chains are smoothened except in areas badly affected by COVID-19. They are almost back to normal but extra efforts are being made to align deliveries to project requirements.” He adds that cement availability was a problem across all geographical areas as manufacturing plants were completely shutdown during the lockdown period and that rates have spiked owing to high production cost and low demand. “The steel industry, though, was positive; availability was smooth and prices were regulated.” Yogesh Kumar Jain, Managing Director, PNC Infratech, reveals that during May and early June, there was an acute paucity in the supply of cement and manufacturing items, and a consequent rise in their prices, “plausibly because of a demand-supply mismatch owing to suspension of production during the lockdown spell”. Though both supplies and the process are getting stabilised gradually, he believes it may take some more time for normalisation. K Jalandhar Reddy, Executive Director, KNR Constructions, believes there is improvement in the movement of goods like steel and cement and that supply of these materials has improved to a greater extent with the Government lifting lockdown in a staggered manner. With regard to prices, he shares that prices of cement have increased from 25-40 per cent in different parts of the country while there is a slight reduction in steel prices. “We hope the supply chain movement will improve further.” On the other hand, Tata Projects did not face any issues with regards to supply chains as “our supply lines have always been robust with adequate supplies,” says Himanshu Chaturvedi, Chief Strategy Officer, Tata Projects. And for SN Subrahmanyan, CEO & Managing Director, L&T, disruptions in the supply chain are only to be expected with the entire country in a lockdown. “Supply of critical material like cement and steel is still not there but the situation is improving by the day and we hope things will almost be back to normal soon.” When asked if prices of these materials are in tandem, he responds that the prices have not fluctuated alarmingly: “We are confident this situation will not change significantly going forward.” Also read: How are construction cos managing operations at sites?  How are contractors working towards revival post-COVID? 

    Next Story
    Infrastructure Urban

    Larsen & Toubro Secures Contract from Defence Ministry

    The Ministry of Defence, Government of India, has awarded a significant contract to Larsen & Toubro (L&T) for supplying K9 Vajra-T Artillery Platforms to the Indian Army. As per the company's project classification, the contract is valued between Rs 50 billion and Rs 100 billion. The K9 Vajra-T, a 155 mm, 52-calibre tracked self-propelled artillery platform, is an adaptation of the globally renowned South Korean K9 Thunder howitzer. It has been co-developed by L&T and Hanwha Aerospace to meet the Indian Army's specific operational needs across diverse terrains, including deserts, plains, and..

    Next Story
    Real Estate

    Delhi-NCR Housing Market sees 25% Sales Growth

    The Delhi-NCR property market has maintained its momentum during the December quarter, with housing sales and new supply estimated to grow by 25 per cent and 59 per cent, respectively, as reported by PropEquity. Data from the real estate analytics firm suggests that housing sales in Delhi-NCR are likely to rise to 12,915 units during the October-December period of this year, compared to 10,354 units in the corresponding period of the previous year. New supply in the region is expected to increase significantly, reaching 11,223 units, a 59 per cent rise from 7,072 units in the year-ago quarter..

    Next Story
    Infrastructure Urban

    DDC Approves Five Key Projects Under Kasaragod Development Package

    The District Development Committee (DDC) has approved a budget of Rs 100.08 million for five key projects under the Kasaragod Development Package. This funding is part of the Rs 700 million allocated in the State budget for the 2024-25 financial year, with administrative approval formally amended to incorporate these initiatives. The decision was made during a meeting chaired by District Collector K. Inbasekar on Saturday, December 21. The approved projects include Rs 40.99 million for constructing Udayapuram Thungal Road in Kottom Belur grama panchayat and Rs 20.56 million for setting up a ..

    Hi There!

    "Now get regular updates from CW Magazine on WhatsApp!

    Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

    Click the link below to join"

    +91 81086 03000