Case Studies of Indian companies following Lean Construction
ROADS & HIGHWAYS

Case Studies of Indian companies following Lean Construction

When HCC was constructing the two-tier Bogibeel Bridge—the country’s longest rail-cum-road bridge—placing the 125-m long fully-welded steel spans, each weighing 1,700 tonne, on the pillars embedded in the riverbed was a challenge. “On-site engineers had two choices for a more practical and economical method, either lifting the spans with floating cranes or erecting them with a launching truss,” shares Amit Uplenchwar, CEO, HCC E&C. “After weighing the pros and cons, the team came up with a third solution of pulling the steel trusses with a set of jacks and winches on the pillars. This eliminated the need to enter the river. Besides, it also ensured safer working conditions, precluded the mobilisation of a giant setup on either side of the river and accelerated the project’s pace. The strategy proved testament to the global practice of Lean construction, which is changing the way projects are executed from design to construction.”

Shapoorji Pallonji Engineering & Construction has implemented Lean for an IT park spread over 40 acre with a built-up area of 3.5 m sq ft. It required coordination among 46 contractors having more than 2,000 workers at a time. “The project was struggling with coordination issues within and among teams, and wastage of material and labour at the same time,” says SC Dixit, Executive Director, Shapoorji Pallonji Engineering & Construction. “The implementation of Lean tools such as Last Planner System (LPS) helped in coordination and streamlining communication, while Value Stream Mapping (VSM) practices helped in reducing man days and improving productivity. Further, pull-based planning ensured optimistic targets, which is further reinforced by the rest of the tools, resulting in improved productivity; and a sense of waste reduction is nurtured in the team, which resulted in improved coordination and higher percentage plan completion.”

At one of Tata Realty and Infrastructure’s recent projects in Gurugram, a large SEZ project of about 5 million sq ft, “we have implemented Lean and created a Big Room,” says Prakash Patil, Secretary General, The Institute for Lean Construction Excellence, and Vice President-Projects, Tata Realty and Infrastructure. “We are using the Last Planner (r) System (LPS), Pull Planning, BIM etc, extensively here.”

- SERAPHINA D’SOUZA

When HCC was constructing the two-tier Bogibeel Bridge—the country’s longest rail-cum-road bridge—placing the 125-m long fully-welded steel spans, each weighing 1,700 tonne, on the pillars embedded in the riverbed was a challenge. “On-site engineers had two choices for a more practical and economical method, either lifting the spans with floating cranes or erecting them with a launching truss,” shares Amit Uplenchwar, CEO, HCC E&C. “After weighing the pros and cons, the team came up with a third solution of pulling the steel trusses with a set of jacks and winches on the pillars. This eliminated the need to enter the river. Besides, it also ensured safer working conditions, precluded the mobilisation of a giant setup on either side of the river and accelerated the project’s pace. The strategy proved testament to the global practice of Lean construction, which is changing the way projects are executed from design to construction.”Shapoorji Pallonji Engineering & Construction has implemented Lean for an IT park spread over 40 acre with a built-up area of 3.5 m sq ft. It required coordination among 46 contractors having more than 2,000 workers at a time. “The project was struggling with coordination issues within and among teams, and wastage of material and labour at the same time,” says SC Dixit, Executive Director, Shapoorji Pallonji Engineering & Construction. “The implementation of Lean tools such as Last Planner System (LPS) helped in coordination and streamlining communication, while Value Stream Mapping (VSM) practices helped in reducing man days and improving productivity. Further, pull-based planning ensured optimistic targets, which is further reinforced by the rest of the tools, resulting in improved productivity; and a sense of waste reduction is nurtured in the team, which resulted in improved coordination and higher percentage plan completion.”At one of Tata Realty and Infrastructure’s recent projects in Gurugram, a large SEZ project of about 5 million sq ft, “we have implemented Lean and created a Big Room,” says Prakash Patil, Secretary General, The Institute for Lean Construction Excellence, and Vice President-Projects, Tata Realty and Infrastructure. “We are using the Last Planner (r) System (LPS), Pull Planning, BIM etc, extensively here.”- SERAPHINA D’SOUZA

Next Story
Infrastructure Urban

Campal Stadium Project Delayed

The football stadium and parade ground project in Campal, Panaji, which was initiated under the smart city plan, has yet to be completed, even though it is over a year past its original deadline. The project started on March 21, 2022, and according to the initial work order, it was supposed to be finished by September 20, 2023. Imagine Panaji Smart City Development Ltd (IPSCDL) has reported that 98% of the work is complete, with the final 2% expected to be finished by March 2025. "A small area where the concrete batching plant is situated needs completion," they said. The project's total est..

Next Story
Infrastructure Urban

Cleanliness Control Centre to Monitor Work, Complaints 24X7

Jaipur's cleanliness management system is set to be more efficient with the Integrated Command and Control Centre now operating 24/7. On Friday, Arun Kumar Hasija, CEO of Jaipur Smart City Limited, issued orders to implement this change. Hasija explained that the centre will supervise door-to-door refuse collection, sanitation operations, and mechanized cleaning activities. Special attention is being given to night-time cleaning across the city, with advanced machinery being used to sanitize road dividers in areas like the Walled City. The centre will now operate round-the-clock to improve c..

Next Story
Infrastructure Urban

Rs 1 Bn Plan for Waste Disposal at Bandhwari Landfill

A Rs 1 billion plan for disposing of over 10 lakh tonnes of legacy waste at the Bandhwari Solid Waste Treatment Plant has been submitted to the Department of Urban Local Bodies (ULB) for approval. The proposal is expected to be approved in an upcoming purchase committee meeting led by Haryana Chief Minister Nayab Singh Saini, officials from the Municipal Corporation of Gurugram (MCG) said. This proposal follows the December 17 deadline set by the National Green Tribunal (NGT) for MCG to submit an update on waste disposal progress at Bandhwari. Earlier this year, MCG had assured the NGT in an a..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000