5D to 6D BIM!
Real Estate

5D to 6D BIM!

On January 28 this year, when 11.5 km of the Nagpur Metro Aqua Line was thrown open to the public, it was one of the fastest constructions of a metro-rail project. In little less than a span of five years, Maharashtra Metro Rail Corporation (Maha Metro), had started passenger services on about 25 km of the total project length of 38 km. Earlier, Maha Metro had inaugurated passenger services on the Orange Line between its two stations of Sitabuldi Interchange and Khapri Metro Station.

Although Nagpur Metro was sanctioned and the foundation stone for the same was laid by Prime Minister Narendra Modi on August 21, 2014, actual construction commenced only on June 1, 2015.

The daunting task 

Nagpur Metro is a Rs 86.80-billion project comprising two corridors, 38.215 km in length, with 1,250 piers, 38 stations and two depots. The project has a tight completion timeframe. In addition, Maha Metro has also been entrusted the responsibility of constructing the Rs 110-million Pune Metro project with two corridors, 31.254-km-long with 30 stations and two depots. Although the Pune project is shorter in length than that of Nagpur, it is more complex owing to a 5-km underground section passing through difficult urban landscape.

The 69.5 km of metro rail being constructed in two cities makes it the largest project being constructed by one metro rail corporation in the country outside Delhi and Mumbai. Additionally, in both cities, Maha Metro is constructing an unprecedented level of office complexes, retail space, recreational spaces and other real-estate development to ensure that its non-fare box revenue is 60 per cent of the total revenue.

Even without the addition of a likely Phase 2 of the Nagpur and Pune metros and more responsibilities to be added to Maha Metro in the near future, the present task at hand is daunting—obstacles and challenges have to be negotiated, time conserved and money saved. Quite clearly, Maha Metro has its task cut out, tightly controlling delivery timelines, curbing and eliminating cost overruns, effecting a saving over the estimated cost, all while adhering to consistent quality output.

The success mantra: 5D BIM

Maha Metro is the first organisation in the country to implement 5D BIM project visualisation. For the uninitiated, 5D BIM is a digital project management concept that integrates many software seamlessly and employs five-dimensional building information modelling (BIM) to accurately predict outcomes and timelines. This unique system has enabled Maha Metro to very tightly control quality, cost and time.

Nagpur shows the way

During the construction of the Nagpur Metro, Maha Metro, by using 5D BIM, has achieved construction excellence, first converting future physical works into a prior virtual reality and then re-transporting it to the reality of the physical work. Such an amalgamation of convergence of physical and virtual reality in project management is unprecedented in the country, either in government or the corporate sector.

In a country where large infrastructure projects have gained notoriety for time and cost overruns and have often delivered dubious quality, using the new 5D project management platform, Nagpur Metro has broken from the traditional vicious circle of project management and delivered consistent quality along with timebound completion. Further, while doing so, it has effected a saving of 10 per cent over the estimated cost as provided in the DPR.

Maha Metro has already geared up to replicate the 5D-BIM benefits in the Pune Metro project as well.

Marching ahead to 6D

The success achieved with 5D-BIM indubitably has no parallel and peer in the country. But Maha Metro has just upped the ante. After successfully implementing 5D BIM,it is now exploring the 6D BIMmechanism—6D BIM refers to the intelligent linking of individual 3D components or assemblies with all aspects of project lifecycle management information.

It is expected that taking the lifecycle approach of 6D BIM over the next 25 years, Maha Metro will save about Rs 25 billion (Rs 14.50 billion in the Nagpur Metro itself).



Why 6D?

The typical lifecycle of a metro project is for 50 years, which includes four to five years on design and construction and 40 to 45 years on operations and maintenance (O&M). If one considers the complete lifecycle cost of the project, 20 per cent is typically the construction cost while the majority 80 per centis spent on O&M. Shifting to a 6D platform means that, during the construction phase itself, Maha Metro will capture all the assets in granular details on the digital platform; thus, the minutest information on them will be available at the click of a mouse during the O&M stage. While the Maha Metro has embraced construction excellencewith 5D, 6D becomes a digital twin that provides an online, real-time asset management system. 

6D makes post-construction handover seamless

An adjunct benefit of shifting to the 6D digital platform is that the handover of Maha Metro projects will become seamless and substantially reduce information loss, even eliminating it, at the time of the handover. Needless to say, handing over of completed assets in a complex metro project after construction to the O&M team, often within a short span of time, is a humungous task. But the new digital platform makes this handover seamless with final deliverables being 3D ‘as-built’ models rather than drawings, based on which the O&M team can plan the maintenance strategy and philosophy in advancewith ease.

The Asset Tag advantage

What’s more, to maintain asset information, Maha Metro has developed a unique Asset Tag, where 3D component information is linked, such as product details, O&M manuals, product specifications, etc. The same Asset Tag is used to identifyassets and perform maintenance activities. With the total number of assets estimated at over 500,000 this is an another innovative subcomponent of the digital platform, coveringrolling stock, MEP, signalling, telecom, OHE, power supply, viaduct, stations, etc. 

Maha Metro did not invent the 5D or 6D BIM versions. Infrastructure projects globally are using them. But what separates Maha Metro from even its global peers is the comprehensive manner in which it has been able to harness the full benefit of 5D in construction, and the way it is perfecting 6D for use in the O&M phase.

On January 28 this year, when 11.5 km of the Nagpur Metro Aqua Line was thrown open to the public, it was one of the fastest constructions of a metro-rail project. In little less than a span of five years, Maharashtra Metro Rail Corporation (Maha Metro), had started passenger services on about 25 km of the total project length of 38 km. Earlier, Maha Metro had inaugurated passenger services on the Orange Line between its two stations of Sitabuldi Interchange and Khapri Metro Station.Although Nagpur Metro was sanctioned and the foundation stone for the same was laid by Prime Minister Narendra Modi on August 21, 2014, actual construction commenced only on June 1, 2015.The daunting task Nagpur Metro is a Rs 86.80-billion project comprising two corridors, 38.215 km in length, with 1,250 piers, 38 stations and two depots. The project has a tight completion timeframe. In addition, Maha Metro has also been entrusted the responsibility of constructing the Rs 110-million Pune Metro project with two corridors, 31.254-km-long with 30 stations and two depots. Although the Pune project is shorter in length than that of Nagpur, it is more complex owing to a 5-km underground section passing through difficult urban landscape.The 69.5 km of metro rail being constructed in two cities makes it the largest project being constructed by one metro rail corporation in the country outside Delhi and Mumbai. Additionally, in both cities, Maha Metro is constructing an unprecedented level of office complexes, retail space, recreational spaces and other real-estate development to ensure that its non-fare box revenue is 60 per cent of the total revenue.Even without the addition of a likely Phase 2 of the Nagpur and Pune metros and more responsibilities to be added to Maha Metro in the near future, the present task at hand is daunting—obstacles and challenges have to be negotiated, time conserved and money saved. Quite clearly, Maha Metro has its task cut out, tightly controlling delivery timelines, curbing and eliminating cost overruns, effecting a saving over the estimated cost, all while adhering to consistent quality output.The success mantra: 5D BIMMaha Metro is the first organisation in the country to implement 5D BIM project visualisation. For the uninitiated, 5D BIM is a digital project management concept that integrates many software seamlessly and employs five-dimensional building information modelling (BIM) to accurately predict outcomes and timelines. This unique system has enabled Maha Metro to very tightly control quality, cost and time.Nagpur shows the wayDuring the construction of the Nagpur Metro, Maha Metro, by using 5D BIM, has achieved construction excellence, first converting future physical works into a prior virtual reality and then re-transporting it to the reality of the physical work. Such an amalgamation of convergence of physical and virtual reality in project management is unprecedented in the country, either in government or the corporate sector.In a country where large infrastructure projects have gained notoriety for time and cost overruns and have often delivered dubious quality, using the new 5D project management platform, Nagpur Metro has broken from the traditional vicious circle of project management and delivered consistent quality along with timebound completion. Further, while doing so, it has effected a saving of 10 per cent over the estimated cost as provided in the DPR.Maha Metro has already geared up to replicate the 5D-BIM benefits in the Pune Metro project as well.Marching ahead to 6DThe success achieved with 5D-BIM indubitably has no parallel and peer in the country. But Maha Metro has just upped the ante. After successfully implementing 5D BIM,it is now exploring the 6D BIMmechanism—6D BIM refers to the intelligent linking of individual 3D components or assemblies with all aspects of project lifecycle management information.It is expected that taking the lifecycle approach of 6D BIM over the next 25 years, Maha Metro will save about Rs 25 billion (Rs 14.50 billion in the Nagpur Metro itself).Why 6D?The typical lifecycle of a metro project is for 50 years, which includes four to five years on design and construction and 40 to 45 years on operations and maintenance (O&M). If one considers the complete lifecycle cost of the project, 20 per cent is typically the construction cost while the majority 80 per centis spent on O&M. Shifting to a 6D platform means that, during the construction phase itself, Maha Metro will capture all the assets in granular details on the digital platform; thus, the minutest information on them will be available at the click of a mouse during the O&M stage. While the Maha Metro has embraced construction excellencewith 5D, 6D becomes a digital twin that provides an online, real-time asset management system. 6D makes post-construction handover seamlessAn adjunct benefit of shifting to the 6D digital platform is that the handover of Maha Metro projects will become seamless and substantially reduce information loss, even eliminating it, at the time of the handover. Needless to say, handing over of completed assets in a complex metro project after construction to the O&M team, often within a short span of time, is a humungous task. But the new digital platform makes this handover seamless with final deliverables being 3D ‘as-built’ models rather than drawings, based on which the O&M team can plan the maintenance strategy and philosophy in advancewith ease.The Asset Tag advantageWhat’s more, to maintain asset information, Maha Metro has developed a unique Asset Tag, where 3D component information is linked, such as product details, O&M manuals, product specifications, etc. The same Asset Tag is used to identifyassets and perform maintenance activities. With the total number of assets estimated at over 500,000 this is an another innovative subcomponent of the digital platform, coveringrolling stock, MEP, signalling, telecom, OHE, power supply, viaduct, stations, etc. Maha Metro did not invent the 5D or 6D BIM versions. Infrastructure projects globally are using them. But what separates Maha Metro from even its global peers is the comprehensive manner in which it has been able to harness the full benefit of 5D in construction, and the way it is perfecting 6D for use in the O&M phase.CW also recently conducted a webinar on The New Metro Life-Line. Read more here.

Next Story
Infrastructure Transport

Railway stations in Prayagraj undergo major passenger facility expansion

The Railway Board Chairman and CEO, Satish Kumar, conducted an extensive inspection on Saturday alongside the General Manager of Northern Railway and the officiating General Manager of North Central Railway. Their visit focused on various ongoing projects at multiple stations across the Northern and North Central Railway zones, with particular attention to enhancing facilities for the upcoming Maha Kumbh. During the inspection, Chairman Kumar reviewed the construction of a vital bridge over the River Ganga, specifically between Jhunsi and Prayagraj Rambagh. This bridge is expected to significa..

Next Story
Infrastructure Transport

Madurai-Thoothukudi broad gauge line works under review

The construction of the Madurai-Thoothukudi broad gauge line, which includes the crucial Melmarudur-Tiruparankundram project, is currently under careful review. This update comes from Southern Railway's assistant public information officer, J Kumarasubramanian, following an RTI inquiry made by a concerned citizen, Dayanand Krishnan. The new broad gauge line is projected to cover a total length of 143.5 km, with the initial 18 km stretch between Milavittan and Melmarudur completed and sanctioned by the Commission of Railway Safety on March 8, 2022. While substantial progress has been made on t..

Next Story
Real Estate

DLF expects Rs 26,000 cr from super luxury project in Gurugram

Realty giant DLF is projecting impressive revenue of Rs 26,000 crore from its newly unveiled super-luxury project, The Dahlias, situated in the heart of Gurugram. Ashok Tyagi, the Managing Director of DLF, shared these insights during a recent conference call with market analysts, highlighting the project's potential amidst rising demand for high-end residential properties. The Dahlias project spans an expansive 17 acres and is set to feature approximately 420 ultra-luxury apartments, each boasting a minimum size of 10,300 square feet. This ambitious development has already garnered significan..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000