373 projects show cost overruns of Rs 3.89 trillion
ECONOMY & POLICY

373 projects show cost overruns of Rs 3.89 trillion

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion.

The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects.

Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months.

Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported.

Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion. The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months. Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported. Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

Next Story
Building Material

Raising the Bar!

In a game-changing move for the construction industry, the First Construction Council (FCC) made waves in 2018-19 with its critical analysis of thermo-mechanically treated (TMT) bars – a cornerstone of reinforced concrete construction. Through a rigorous sample test of 26 TMT bar brands, the results revealed a startling reality: 18 out of 26 brands failed to meet quality parameters, as crucial elements like phosphorous and sulphur exceeded acceptable limits. The tests were conducted at a time when India’s infrastructure sector was surging, with an estimated Rs 5.97 trillion earmarked ..

Next Story
Infrastructure Transport

HCC-TPL JV Secures Indore Metro’s Underground Package IN-05R

"Madhya Pradesh Metro Rail Corporation Ltd (MPMRCL) has announced Hindustan Construction Co. Ltd. – Tata Projects Ltd. (HCC – TPL Indore Metro JV) as the lowest bidder for Package IN-05R, the first and only underground section of Indore Metro Phase 1’s Yellow Line.Originally, MPMRCL invited bids for Package IN-05 in February 2024 but later cancelled the tender and reissued it as Package IN-05R, with an estimated cost of ₹2,550 crore and a four-year completion timeline. When technical bids were opened in November 2024, six firms had submitted their proposals. However, Afcons-Sam India J..

Next Story
Infrastructure Transport

TBM Kurinji Launched for Corridor 5 Expansion for Chennai Metro

Tata Projects Limited has launched the first Tunnel Boring Machine (TBM) for Corridor 5 of its Phase II expansion project. Named TBM Kurinji, the machine was deployed at the Kolathur Ramp on February 19, 2025, marking a significant milestone in Chennai’s metro development.Following the successful implementation of Phase I and its extension, CMRL has embarked on an ambitious Phase II expansion, covering 118.9 km across three new corridors, backed by international funding from JICA, ADB, AIIB, and NDB. Corridor 5, spanning 47 km, originates at Madhavaram Milk Colony and passes through key loca..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?